21110 W OXNARD ST 91367

Certificate Information: 21110 W OXNARD ST 91367

Application / Permit
18010-10000-02438
Plan Check / Job No.
B18LA10242
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
NEW 7 STORY HOTEL, WITH ONE LEVEL BASEMENT (170 GUESTROOMS).
Permit Issued
Issued on 6/10/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2018 APPLICANT
Disabled Access Plans Picked Up 6/6/2018 APPLICANT
Green Plans Picked Up 6/6/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 JOE VO
Corrections Issued 6/22/2018 JOE VO
Quality Review Completed 6/28/2018 GARO TELMI
Building Plans Picked Up 7/2/2018 APPLICANT
Applicant returned to address corrections 1/9/2019 JOE VO
Plan Check Approved 6/6/2019 JOE VO
Issued 6/10/2019 LADBS
TCO Issued (Expire Date: 07-19-2022) 1/20/2022 RICKEY JACKSON
TCO Issued (Expire Date: 01-08-2023) 7/12/2022 JEFFREY DURAN
CofO in Progress 7/15/2022 JEFFREY DURAN
Permit Finaled 7/18/2022 JEFFREY DURAN
CofO Issued 7/18/2022 JEFFREY DURAN
Permit Finaled 7/18/2022 JEFFREY DURAN

Permit Application Clearance Information

Public Swimming Pool approval Cleared 10/10/2018 LACDHS APPROVED
Work Adjacent to Public Way Cleared 11/13/2018 BOK GOH
Highway dedication Cleared 12/14/2018 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 1/31/2019 JOHN CONNEALLY
Food Service Establishment Cleared 2/25/2019 AMPHORN WONG
Fire Marshall Fire Life Safety Cleared 2/27/2019 VIDAL GARCIA
Low Impact Development Cleared 2/28/2019 MARTIN FRAGOSO
DAS Clearance Cleared 3/14/2019 WAI LAU
Permit Cleared 3/18/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 3/18/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 3/18/2019 ELENA LOPEZ
Construction near power lines Cleared 3/21/2019 OSCAR CASTRO
Construction within easement Cleared 3/21/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 3/27/2019 ADRIAN SANCHEZ
Sewer availability Cleared 3/27/2019 ADRIAN SANCHEZ
Green Code Cleared 4/9/2019 DONALD CRICHLOW
Driveway location Cleared 5/15/2019 SHIRLEY ZAMORA
Specific Plan Cleared 5/20/2019 ANNA VAN
CPC Cleared 5/21/2019 ANNA VAN
Site Plan review Cleared 5/21/2019 ANNA VAN
ZA Case Cleared 5/21/2019 ANNA VAN
Food establishment approval Cleared 6/6/2019 LACDHS APPROVED
Miscellaneous Cleared 6/6/2019 JOE VO

Contact Information

Architect Nichols,, Robert B; Lic. No.: C29164 P O BOX 55384      VALENCIA, CA 91385
Contractor Ebco General Contractor Lp; Lic. No.: 1030694-B 305 W GILLIS AVENUE      CAMERON, TX 76520
Engineer Biddulph,, Sandra; Lic. No.: S4225 7488 PASEO CRISTAL      CARLSBAD, CA 92009
Engineer Chapman,, Ryan Scott; Lic. No.: C86076 N95W29130 FAWN CT      COLGATE, WI 53017
Engineer Jordan,, Ricardo; Lic. No.: C68436 1050 ISLAND AVE UNIT 109      SAN DIEGO, CA 92101

Inspector Information

MELVIN GIRTON, (818) 374-1128 Office Hours: 7:00-8:00 AM MON-FRI
RICKEY JACKSON, (818) 374-1128 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY DURAN, (818) 374-1128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/19/2019 Partial Inspection MILLARD ARDOIN
Pre-Inspection 7/24/2019 Partial Inspection DANNY RODRIGUEZ
Deputy Grading 7/25/2019 Conditional Approval JEFFREY DURAN
Deputy Grading 7/26/2019 Conditional Approval JEFFREY DURAN
Pre-Inspection 9/27/2019 Partial Inspection JEFFREY DURAN
Pre-Inspection 10/25/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/31/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/12/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/14/2019 Approved JEFFREY DURAN
Pre-Inspection 11/14/2019 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 11/15/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/18/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/20/2019 Approved JEFFREY DURAN
Pre-Inspection 11/20/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 11/21/2019 Approved JEFFREY DURAN
Footing/Foundation/Slab 11/21/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/22/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/22/2019 Conditional Approval RICKEY JACKSON
Deputy Reinf. Concrete 11/23/2019 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 11/27/2019 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 12/2/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/2/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/3/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/4/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/4/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 12/5/2019 Conditional Approval JEFFREY DURAN
Pre-Inspection 12/5/2019 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 12/6/2019 Conditional Approval JEFFREY DURAN
Pre-Inspection 12/6/2019 Partial Approval JEFFREY DURAN
Pre-Inspection 12/7/2019 Off-Hour Fees Due
Reinforced Concrete Frame 12/10/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/11/2019 Approved JEFFREY DURAN
Reinforced Concrete Frame 12/11/2019 Partial Approval JEFFREY DURAN
Deputy Other (see comments) 12/12/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/12/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/13/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/16/2019 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/16/2019 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/17/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 12/17/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/17/2019 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 12/17/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/18/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/19/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/19/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 12/23/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/24/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/26/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/31/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 1/2/2020 Approved JEFFREY DURAN
Masonry Wall/Backfill 1/2/2020 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 1/3/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 1/8/2020 Conditional Approval JAMES STEPHENS
Deputy Pre-Stress Concrete 1/9/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 1/10/2020 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/10/2020 Partial Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/16/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/17/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/22/2020 Corrections Issued JEFFREY DURAN
Footing/Foundation/Slab 1/22/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/24/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/28/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/31/2020 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/4/2020 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 2/5/2020 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/5/2020 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 2/20/2020 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 2/25/2020 Partial Approval JEFFREY DURAN
Structural Steel Frame 2/26/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/11/2020 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/16/2020 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 4/6/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 4/13/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 4/14/2020 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/15/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 4/20/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 5/5/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 5/11/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/13/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 6/2/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 6/8/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 6/17/2020 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 7/6/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/14/2020 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 8/19/2020 Approved SORIN CIRSTOIU
Deputy Steel/Welding 8/20/2020 Conditional Approval SORIN CIRSTOIU
Deputy Wood Construction 8/21/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 8/24/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/25/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/26/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/27/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/28/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 8/28/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/31/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/1/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/2/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/3/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/3/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/4/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/4/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/8/2020 Conditional Approval ALAN NOVAK
Deputy Wood Construction 9/9/2020 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 9/9/2020 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 9/10/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 9/10/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/14/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/15/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/15/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/16/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 9/16/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 9/16/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/17/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/17/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/18/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/18/2020 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 9/18/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 9/21/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/21/2020 Conditional Approval JEFFREY FULTON
Structural Steel Frame 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Deputy Steel/Welding 9/22/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/22/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/23/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 9/23/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/24/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/24/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/25/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/25/2020 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 9/25/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 9/28/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/29/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/29/2020 Approved HAMID PISHEHVAR
Drywall Nailing 9/29/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 9/30/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/30/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/1/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/1/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/2/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/2/2020 Conditional Approval JEFFREY FULTON
Drywall Nailing 10/2/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 10/5/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/6/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 10/7/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/7/2020 Conditional Approval JEFFREY FULTON
Drywall Nailing 10/7/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 10/8/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/9/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/9/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/13/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/13/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/14/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/15/2020 Approved HAMID PISHEHVAR
Drywall Nailing 10/15/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/16/2020 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 10/20/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/20/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/21/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/21/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 10/22/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/22/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 10/23/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/23/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/27/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/28/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/29/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 10/30/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/2/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/4/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 11/4/2020 Partial Approval HAMID PISHEHVAR
Deputy Steel/Welding 11/5/2020 Conditional Approval RICKEY JACKSON
Deputy Wood Construction 11/5/2020 Conditional Approval RICKEY JACKSON
Deputy Steel/Welding 11/6/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/6/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/9/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/10/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/10/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/12/2020 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 11/12/2020 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 11/13/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/13/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/16/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/16/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/17/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/17/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/18/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/18/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/19/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/19/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/20/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/23/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/23/2020 Conditional Approval RICKEY JACKSON
Drywall Nailing 11/23/2020 Partial Approval JOHN KITCKO
Deputy Steel/Welding 11/24/2020 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 11/25/2020 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 11/30/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/30/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 12/1/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/1/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 12/2/2020 Conditional Approval RICKEY JACKSON
Deputy Wood Construction 12/2/2020 Conditional Approval RICKEY JACKSON
Deputy Steel/Welding 12/3/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/3/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 12/4/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/4/2020 Approved HAMID PISHEHVAR
Drywall Nailing 12/4/2020 Partial Approval HAMID PISHEHVAR
Deputy Wood Construction 12/9/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/10/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/11/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/14/2020 Conditional Approval RICKEY JACKSON
Deputy Wood Construction 12/15/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/16/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/17/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/18/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/23/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/29/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 12/30/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/5/2021 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 1/6/2021 Approved HAMID PISHEHVAR
Light Gage Steel Frame 1/6/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/7/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/8/2021 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/8/2021 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 1/11/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/12/2021 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 1/12/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/13/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/14/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/15/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 1/20/2021 Approved HAMID PISHEHVAR
Drywall Nailing 1/22/2021 Approved HAMID PISHEHVAR
Structural Steel Frame 1/22/2021 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 1/25/2021 Partial Approval CAMERON CHABAN
Deputy Wood Construction 2/4/2021 Conditional Approval JEFFREY DURAN
Interior/Exterior Lathing 2/10/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 2/11/2021 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 2/12/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 2/18/2021 Partial Approval CAMERON CHABAN
Deputy Wood Construction 2/25/2021 Approved HAMID PISHEHVAR
Drywall Nailing 2/26/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 2/26/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 3/8/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 3/15/2021 Partial Approval CAMERON CHABAN
Drywall Nailing 3/16/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 3/16/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 4/9/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 4/30/2021 Partial Approval CAMERON CHABAN
Drywall Nailing 5/12/2021 Partial Approval CAMERON CHABAN
Interior/Exterior Lathing 5/20/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 5/28/2021 Partial Approval JONATHAN QUACH
Footing/Foundation/Slab 6/3/2021 Partial Approval CAMERON CHABAN
Special/Order Compliance 6/7/2021 Order to Comply Issued JEFFREY FULTON
Footing/Foundation/Slab 6/14/2021 Partial Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 6/15/2021 Partial Approval CAMERON CHABAN
Structural Steel Frame 7/8/2021 Not Ready for Inspection CAMERON CHABAN
Structural Steel Frame 7/12/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 7/13/2021 Partial Inspection CAMERON CHABAN
Drywall Nailing 7/15/2021 Partial Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 7/22/2021 Partial Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 7/23/2021 Conditional Approval CAMERON CHABAN
T-Bar Ceiling 8/9/2021 Corrections Issued CAMERON CHABAN
T-Bar Ceiling 8/24/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/9/2021 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 9/10/2021 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 9/13/2021 Approved CAMERON CHABAN
Footing/Foundation/Slab 10/18/2021 Not Ready for Inspection DANIEL VARNUM
Green Building Final 10/18/2021 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 10/18/2021 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 10/18/2021 Not Ready for Inspection DANIEL VARNUM
Reinforced Masonry Frame 10/18/2021 Not Ready for Inspection DANIEL VARNUM
Smoke Detectors 10/18/2021 Not Ready for Inspection DANIEL VARNUM
Pre-Inspection 10/19/2021 No Access for Inspection DANIEL VARNUM
Smoke Detectors 11/3/2021 Partial Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 11/4/2021 Partial Inspection DANIEL VARNUM
Final 1/10/2022 Partial Inspection DANIEL VARNUM
Footing/Foundation/Slab 1/10/2022 Approved DANIEL VARNUM
Green Building Final 1/10/2022 Approved DANIEL VARNUM
Green Building Rough 1/10/2022 Approved DANIEL VARNUM
Reinforced Concrete Frame 1/10/2022 Approved DANIEL VARNUM
Reinforced Masonry Frame 1/10/2022 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 1/10/2022 SGSOV Approved DANIEL VARNUM
Smoke Detectors 1/10/2022 Approved DANIEL VARNUM
Verify Sprinkler Sign Off 1/10/2022 Approved DANIEL VARNUM
Final 1/27/2022 Partial Inspection DANIEL VARNUM
Special/Order Compliance 2/10/2022 Corrections Issued JEFFREY DURAN
Verify Rec and Parks Fee Memo 2/25/2022 Partial Approval DANIEL VARNUM
Special/Order Compliance 6/22/2022 Conditional Approval JEFFREY DURAN
Final 7/18/2022 OK to Issue CofO JEFFREY DURAN