804 N HARVARD BLVD 90029
Certificate Information: 804 N HARVARD BLVD 90029
- Application / Permit
- 18010-10000-02312
- Plan Check / Job No.
- B18LA09962
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT AT REAR PER AB 494 & SB 229.
- Permit Issued
- Issued on 10/24/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2018 | APPLICANT |
| Green Plans Picked Up | 5/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | YOUNG KIM |
| Corrections Issued | 6/19/2018 | YOUNG KIM |
| Quality Review Completed | 6/19/2018 | DAVID CHANG |
| Building Plans Picked Up | 6/22/2018 | APPLICANT |
| Applicant returned to address corrections | 9/14/2018 | YOUNG KIM |
| Applicant returned to address corrections | 10/9/2018 | YOUNG KIM |
| Applicant returned to address corrections | 10/16/2018 | YOUNG KIM |
| Plan Check Approved | 10/18/2018 | YOUNG KIM |
| Issued | 10/24/2018 | LADBS |
| CofO in Progress | 6/5/2020 | JOSEPH MCGARRY |
| Permit Finaled | 6/18/2020 | DEROLD HAUFF |
| CofO Issued | 6/18/2020 | DEROLD HAUFF |
| Permit Finaled | 6/18/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 7/23/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 7/31/2018 | NEGAR NEJAD |
| Hydrant and Access approval | Cleared | 8/3/2018 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 8/22/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/14/2018 | JAMES MORALEZ |
Contact Information
| Engineer | Kim, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/26/2018 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/10/2019 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 1/31/2019 | No Access for Inspection | LUIS BARRALES |
| Footing/Foundation/Slab | 2/1/2019 | Approved | LUIS BARRALES |
| Deputy Drilled-In Anchors | 4/2/2019 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 4/3/2019 | Not Ready for Inspection | LUIS BARRALES |
| Green Building Rough | 4/3/2019 | Not Ready for Inspection | LUIS BARRALES |
| MERV13>=Rough | 4/3/2019 | Not Ready for Inspection | LUIS BARRALES |
| Verify Sprinkler Sign Off | 4/3/2019 | Not Ready for Inspection | LUIS BARRALES |
| ELECTRICAL-Rough | 4/8/2019 | Corrections Issued | LUIS BARRALES |
| PLUMBING-Rough | 4/8/2019 | Approved | LUIS BARRALES |
| ELECTRICAL-Rough | 5/7/2019 | Partial Approval | LUIS BARRALES |
| HVAC-Rough | 5/7/2019 | Partial Approval | LUIS BARRALES |
| Insulation | 5/7/2019 | Partial Approval | LUIS BARRALES |
| Underground Mechanical | 5/7/2019 | Partial Approval | LUIS BARRALES |
| Drywall Nailing | 5/29/2019 | Approved | LUIS BARRALES |
| Green Building Rough | 5/29/2019 | Approved | LUIS BARRALES |
| PLUMBING-Rough | 10/15/2019 | Partial Approval | LUIS BARRALES |
| PLUMBING-Rough | 3/13/2020 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Final | 4/30/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 4/30/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| MERV13>=Final | 4/30/2020 | Approved | JOSEPH MCGARRY |
| MERV13>=Rough | 4/30/2020 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/30/2020 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 4/30/2020 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 4/30/2020 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 4/30/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/13/2020 | Approved | JOSEPH MCGARRY |
| Final | 5/13/2020 | Corrections Issued | JOSEPH MCGARRY |
| Gas Test | 5/13/2020 | Approved | JOSEPH MCGARRY |
| Green Building Final | 5/13/2020 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 5/13/2020 | Not Required | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/13/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 6/4/2020 | Approved | JOSEPH MCGARRY |
| Final | 6/4/2020 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 6/4/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 6/4/2020 | Approved | JOSEPH MCGARRY |