836 1/2 N MCCADDEN PL 90038

Certificate Information: 836 1/2 N MCCADDEN PL 90038

Application / Permit
18010-10000-02289
Plan Check / Job No.
B18LA09892
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
3-STORY SFD WITH ATTACHED GARAGE. SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE PARCEL MAP NO. AA-2017-328-PMLA-SL. PARCEL A
Permit Issued
Issued on 3/7/2019
Issuing Office
Metro
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2018 APPLICANT
Green Plans Picked Up 6/11/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 MOHAMMAD FIROUZBAKHT
Corrections Issued 6/19/2018 MOHAMMAD FIROUZBAKHT
Quality Review Completed 6/19/2018 DAVID CHANG
Building Plans Picked Up 6/19/2018 APPLICANT
Plan Check Approved 2/27/2019 MOHAMMAD FIROUZBAKHT
Issued 3/7/2019 LADBS
CofO in Progress 4/21/2021 ALEJANDRO DE ARTOLA
Permit Finaled 4/24/2021 DEROLD HAUFF
CofO Issued 4/24/2021 DEROLD HAUFF
Permit Finaled 4/24/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/17/2018 JAMES MORALEZ
Hydrant and Access approval Cleared 7/17/2018 JOHN CONNEALLY
Permit Cleared 7/17/2018 JAMES MORALEZ
Highway dedication Cleared 7/25/2018 CARLA VALLADARES
Low Impact Development Cleared 8/10/2018 SAM NAVID
Address approval Cleared 10/17/2018 KARAN PATEL
Roof/Waste drainage to street Cleared 10/17/2018 KARAN PATEL
Green Code Cleared 10/23/2018 KHEDER ALRAZAA
Miscellaneous Cleared 1/10/2019 SOPHIE GABEL-SCHEINBAU
Sewer availability Cleared 2/27/2019 ADRIAN SANCHEZ

Contact Information

Architect , ; Lic. No.: C34253 3684 GRAYBURN AVE      LOS ANGELES, CA 90018
Contractor Cheng Joseph; Lic. No.: 947594-B 3929 ELMA RD      PASADENA, CA 91107
Engineer Lai, Wilson; Lic. No.: S4965 1424 FILMORE PL      CHULA VISTA, CA 91913

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 5/31/2019 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 1/14/2020 Conditional Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/15/2020 Conditional Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/15/2020 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/23/2020 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 4/17/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 4/21/2020 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 4/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval ALEJANDRO DE ARTOLA
Insulation 4/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Insulation 4/28/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/8/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/15/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 5/19/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/21/2020 Partial Approval ALEJANDRO DE ARTOLA
Insulation 5/21/2020 Partial Approval ALEJANDRO DE ARTOLA
Deck 5/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/27/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 5/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/23/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/26/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 7/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/1/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 7/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 7/21/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/21/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/21/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/22/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/22/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 7/22/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 7/22/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/22/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/22/2020 Approved ALEJANDRO DE ARTOLA
Insulation 7/29/2020 Approved ALEJANDRO DE ARTOLA
Shower Pan 7/29/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 8/5/2020 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/5/2020 Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/5/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 10/14/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/9/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 11/9/2020 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 11/16/2020 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/18/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/3/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/3/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/3/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/22/2020 Approved ALEJANDRO DE ARTOLA
Gas Test 1/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/19/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 1/19/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 1/27/2021 Approved ALEJANDRO DE ARTOLA
Final 2/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/12/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 2/12/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 2/12/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 2/12/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 2/12/2021 Approved ALEJANDRO DE ARTOLA
Final 3/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/2/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Final 3/24/2021 Conditional Approval ALEJANDRO DE ARTOLA