1532 N SARGENT PL 90026
Certificate Information: 1532 N SARGENT PL 90026
- Application / Permit
- 18010-10000-02278
- Plan Check / Job No.
- B18LA09858
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 10/25/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2018 | REZA HAGHIGHAT |
| Green Plans Picked Up | 6/26/2018 | APPLICANT |
| Corrections Issued | 7/5/2018 | REZA HAGHIGHAT |
| Quality Review Completed | 7/10/2018 | TIEN JEN WANG |
| Building Plans Picked Up | 7/12/2018 | APPLICANT |
| Applicant returned to address corrections | 9/13/2018 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 10/16/2018 | REZA HAGHIGHAT |
| Plan Check Approved | 10/23/2018 | SERGIO SILVA |
| Issued | 10/25/2018 | LADBS |
| CofO in Progress | 12/13/2023 | THOMAS LOGRASSO |
| Permit Finaled | 12/21/2023 | DEROLD HAUFF |
| CofO Issued | 12/21/2023 | DEROLD HAUFF |
| Permit Finaled | 12/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| BHO/Hillside ordinance | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| BHO/Hillside ordinance | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| BHO/Hillside ordinance | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| Permit | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 7/17/2018 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 7/27/2018 | GILBERT URREA |
| Green Code | Cleared | 8/16/2018 | SARAH ABOULHOSN |
| Low Impact Development | Cleared | 10/15/2018 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/15/2018 | STEVE MELGAR |
Contact Information
| Architect | Neubert, Aaron Douglas; Lic. No.: C29005 | 3052 BERKELEY CIRCLE LOS ANGELES, CA 90026 |
| Contractor | Samwon Construction; Lic. No.: 862299-B | 3470 WILSHIRE BLVD STE 9301N LOS ANGELES, CA 90010 |
| Engineer | Phillips, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/19/2019 | Corrections Issued | DAVID CHAN |
| Piling/Pier/Caisson | 4/1/2019 | Approved | DAVID CHAN |
| Piling/Pier/Caisson | 4/30/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 6/12/2019 | Not Ready for Inspection | DAVID CHAN |
| Grounding or Bonding | 6/14/2019 | Off-Hour Fees Due | |
| Underground Mechanical | 6/14/2019 | Off-Hour Fees Due | |
| Underground Mechanical | 6/17/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Concrete | 6/18/2019 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 7/1/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Concrete | 7/5/2019 | Conditional Approval | DAVID CHAN |
| Wood Frame | 8/26/2019 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2019 | Conditional Approval | DAVID CHAN |
| Wood Frame | 10/23/2019 | Partial Approval | DAVID CHAN |
| Deputy Wood Construction | 10/25/2019 | Conditional Approval | DAVID CHAN |
| ELECTRICAL-Rough | 6/15/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/15/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/15/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 6/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 6/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/24/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 6/24/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 6/24/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/29/2020 | Approved | ROBERT VORHIS |
| HVAC-Rough | 6/29/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/7/2020 | Corrections Issued | STUART CHAPMAN |
| Grading Pre-Inspection | 7/7/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/7/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/7/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 8/7/2020 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 8/10/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2020 | SGSOV Approved | STUART CHAPMAN |
| Sewer | 8/27/2020 | Approved | STUART CHAPMAN |
| Underground Mechanical | 8/27/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 9/17/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/1/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 10/22/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 10/22/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/24/2020 | Approved | ROBERT VORHIS |
| Sewer | 1/22/2021 | Partial Inspection | SCOTT FINNILA |
| Sewer | 1/26/2021 | Partial Approval | OSVALDO PARAMO |
| Special/Order Compliance | 1/18/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 3/1/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/5/2023 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 4/5/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/19/2023 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 5/17/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/3/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 7/3/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 7/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 7/20/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/1/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/1/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 8/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 8/1/2023 | Approved | THOMAS LOGRASSO |
| Final | 9/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 11/8/2023 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 12/12/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 12/12/2023 | Approved | THOMAS LOGRASSO |