11603 W PEARL PL 90064

Certificate Information: 11603 W PEARL PL 90064

Application / Permit
18010-10000-02259
Plan Check / Job No.
B18LA09774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW CONSTRUCTION OF 2-CAR GARAGE WITH ADU STUDIO ABOVE TOTALING 418 SF WITH A ROOF DECK ABOVE ADU
Permit Issued
Issued on 8/17/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/23/2019
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2018 APPLICANT
Green Plans Picked Up 6/6/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 LARRY LEE
Corrections Issued 6/11/2018 LARRY LEE
Quality Review Completed 6/12/2018 CHARLES CHANG
Building Plans Picked Up 6/19/2018 APPLICANT
Applicant returned to address corrections 6/22/2018 LARRY LEE
Applicant returned to address corrections 7/25/2018 LARRY LEE
Plan Check Approved 8/14/2018 LARRY LEE
Issued 8/17/2018 LADBS
CofO in Progress 9/17/2019 KEVIN BEAULIEU
Permit Finaled 9/23/2019 VINCENT COTTON
CofO Issued 9/23/2019 VINCENT COTTON
Permit Finaled 9/23/2019 VINCENT COTTON

Permit Application Clearance Information

CPC Cleared 6/29/2018 BRIAN CARR
CPC Cleared 6/29/2018 BRIAN CARR
CPC Cleared 6/29/2018 BRIAN CARR
Address approval Cleared 7/26/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/26/2018 STEVE MELGAR
Permit Cleared 7/26/2018 STEVE MELGAR
Sewer availability Cleared 7/26/2018 STEVE MELGAR
Green Code Cleared 8/3/2018 COLIN LOREDO
Green Code Cleared 8/3/2018 LARRY LEE
Low Impact Development Cleared 8/10/2018 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 8/10/2018 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Wu, Tzuoh-Jaw; Lic. No.: S5002 511 MISSION ST      SOUTH PASADENA, CA 91030

Inspector Information

ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/21/2018 Approved ANTHONY MCDOWALL
PLUMBING-Rough 9/21/2018 Approved ANTHONY MCDOWALL
Deputy Wood Construction 10/17/2018 Conditional Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 12/10/2018 Approved ANTHONY MCDOWALL
ELECTRICAL-Rough 1/25/2019 Corrections Issued ANTHONY MCDOWALL
HVAC-Rough 1/25/2019 Approved ANTHONY MCDOWALL
PLUMBING-Rough 1/25/2019 Corrections Issued ANTHONY MCDOWALL
BUILDING-Rough-Frame 1/31/2019 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 1/31/2019 Approved ANTHONY MCDOWALL
Green Building Rough 1/31/2019 Approved ANTHONY MCDOWALL
MERV13>=Rough 1/31/2019 Not Ready for Inspection ANTHONY MCDOWALL
Verify Sprinkler Sign Off 1/31/2019 Not Ready for Inspection ANTHONY MCDOWALL
Wood Frame 1/31/2019 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 2/13/2019 Approved ANTHONY MCDOWALL
Insulation 4/5/2019 Corrections Issued EVAN COOPER
Insulation 4/10/2019 Approved KEVIN BEAULIEU
Interior/Exterior Lathing 4/10/2019 Not Ready for Inspection KEVIN BEAULIEU
Shower Pan 4/10/2019 Not Ready for Inspection KEVIN BEAULIEU
Drywall Nailing 4/16/2019 Approved KEVIN BEAULIEU
Shower Pan 4/16/2019 Approved KEVIN BEAULIEU
BUILDING-Rough-Frame 7/10/2019 Conditional Approval KEVIN BEAULIEU
Final 7/10/2019 Not Ready for Inspection KEVIN BEAULIEU
Footing/Foundation/Slab 7/10/2019 Approved KEVIN BEAULIEU
Green Building Final 7/10/2019 Not Ready for Inspection KEVIN BEAULIEU
MERV13>=Final 7/10/2019 Approved KEVIN BEAULIEU
MERV13>=Rough 7/10/2019 Approved KEVIN BEAULIEU
SGSOV-Seismic Gas S/O Valve 7/10/2019 SGSOV Not Ready KEVIN BEAULIEU
Service/Power Release 7/10/2019 Not Ready for Inspection KEVIN BEAULIEU
Smoke Detectors 7/10/2019 Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 7/10/2019 Not Ready for Inspection KEVIN BEAULIEU
ELECTRICAL-Final 7/24/2019 Approved KEVIN BEAULIEU
PLUMBING-Final 7/24/2019 Approved KEVIN BEAULIEU
Service/Power Release 8/14/2019 Approved KEVIN BEAULIEU
BUILDING-Rough-Frame 9/9/2019 Approved KEVIN BEAULIEU
Final 9/9/2019 OK to Issue CofO KEVIN BEAULIEU
Gas Test 9/9/2019 Approved KEVIN BEAULIEU
Green Building Final 9/9/2019 Approved KEVIN BEAULIEU
SGSOV-Seismic Gas S/O Valve 9/9/2019 SGSOV Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 9/9/2019 Approved KEVIN BEAULIEU