411 S HAMEL ROAD 1-37 90048

Certificate Information: 411 S HAMEL ROAD 1-37 90048

Application / Permit
18010-10000-02245
Plan Check / Job No.
B18LA09721
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
4 STORY TYPE IIIA 38 UNIT APARTMENT OVER 1 LEVEL BASEMENT GARAGE
Permit Issued
Issued on 3/12/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2018 APPLICANT
Green Plans Picked Up 5/29/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 HERNAN ARREOLA
Disabled Access Plans Picked Up 6/7/2018 APPLICANT
Corrections Issued 6/25/2018 HERNAN ARREOLA
Quality Review Completed 7/5/2018 MINYE PAK
Building Plans Picked Up 7/6/2018 APPLICANT
Applicant returned to address corrections 9/21/2018 HERNAN ARREOLA
Applicant returned to address corrections 10/1/2018 HERNAN ARREOLA
Plan Check Approved 2/5/2019 HERNAN ARREOLA
No Progress 2/8/2019 HERNAN ARREOLA
Plan Check Approved 3/12/2019 HERNAN ARREOLA
Issued 3/12/2019 LADBS
TCO Issued (Expire Date: 03-13-2023) 9/14/2022 ERNESTO CORRAL
CofO in Progress 10/20/2022 EDWIN GREGORYONA
CofO in Progress 10/20/2022 EDWIN GREGORYONA
CofO Issued 11/8/2022 TED RIES
Permit Finaled 11/8/2022 TED RIES

Permit Application Clearance Information

Address approval Cleared 8/1/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/1/2018 ADRIAN SANCHEZ
Highway dedication Cleared 8/1/2018 ADRIAN SANCHEZ
Green Code Cleared 10/19/2018 COLIN LOREDO
Sewer availability Cleared 10/30/2018 CELINA MORENO
DAS Clearance Cleared 11/8/2018 ELIZABETH TOMS
Construction near power lines Cleared 11/16/2018 RIDWAN HARDY
Fire Marshall Fire Life Safety Cleared 11/21/2018 VIDAL GARCIA
Hydrant and Access approval Cleared 11/21/2018 JOHN CONNEALLY
Low Impact Development Cleared 12/7/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/10/2018 STEVE MELGAR
Building over 3-story or 36-ft Cleared 12/11/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/11/2018 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 12/11/2018 EDBER MACEDO
Opn space landscape/Water mgmt Cleared 12/11/2018 EDBER MACEDO

Contact Information

Architect Tsai,, Kuo-Huei; Lic. No.: C33710 834 S BROADWAY SUITE 1206      LOS ANGELES, CA 90014
Contractor Etco Homes Inc; Lic. No.: 879789-B 8447 WILSHIRE BLVD #400      BEVERLY HILLS, CA 902113209
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Noori,, Abdul Wahab; Lic. No.: C81696 6 BIENVENIDO      ALISO VIEJO, CA 92656

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 6/6/2019 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 6/7/2019 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 6/7/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 6/7/2019 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 6/7/2019 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 6/13/2019 Partial Approval FELIX CEBALLOS
METHANE-Barrier 6/13/2019 Approved FELIX CEBALLOS
METHANE-Subgrade 6/13/2019 Partial Approval FELIX CEBALLOS
Excavation/Setback/Form/Re-Bar 6/17/2019 Partial Approval DAVID BURKHEAD
Reinforced Concrete Frame 6/17/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/26/2019 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 6/26/2019 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 6/26/2019 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 7/1/2019 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 7/1/2019 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 7/12/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 7/12/2019 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 8/1/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 8/1/2019 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 8/8/2019 Partial Approval DAVID BURKHEAD
Green Building Rough 8/8/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 8/8/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 8/8/2019 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 8/8/2019 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/8/2019 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 8/13/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 8/13/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 8/13/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 8/13/2019 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 8/13/2019 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 8/13/2019 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/16/2019 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 8/23/2019 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 8/23/2019 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 8/28/2019 Partial Approval DAVID BURKHEAD
Reinforced Concrete Frame 8/28/2019 Partial Approval DAVID BURKHEAD
METHANE-Rough 9/23/2019 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 9/23/2019 Approved DAVID BURKHEAD
Deputy Methane Barrier 9/24/2019 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 9/25/2019 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 9/26/2019 Partial Inspection DAVID BURKHEAD
Deputy Methane Barrier 9/27/2019 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/9/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/11/2019 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 10/17/2019 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 10/17/2019 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 10/18/2019 Corrections Issued GRANT WOODS
Pre-Inspection 10/18/2019 Partial Inspection GRANT WOODS
Excavation/Setback/Form/Re-Bar 10/22/2019 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/22/2019 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 12/2/2019 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 12/3/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/5/2019 Partial Approval LARRY ARNICK
Wood Frame 12/20/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/13/2020 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/29/2020 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 1/29/2020 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 2/4/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/10/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval LARRY ARNICK
Wood Frame 2/21/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 3/2/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval LARRY ARNICK
Wood Frame 3/19/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 3/20/2020 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 4/27/2020 No Access for Inspection LARRY ARNICK
Structural Steel Frame 4/30/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 4/30/2020 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 5/4/2020 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/7/2020 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 5/7/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 5/7/2020 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 5/7/2020 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/8/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 5/8/2020 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 5/8/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Not Ready for Inspection LARRY ARNICK
T-Bar Ceiling 5/20/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/20/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Partial Approval LARRY ARNICK
Wood Frame 5/21/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Approval LARRY ARNICK
Wood Frame 5/29/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 6/3/2020 Partial Inspection JONATHAN QUACH
Insulation 6/4/2020 Partial Approval JONATHAN QUACH
Insulation 6/9/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/11/2020 Approved LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval JONATHAN QUACH
Insulation 6/16/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 6/24/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 7/6/2020 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/6/2020 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Corrections Issued LARRY ARNICK
Deputy Wood Construction 7/10/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Partial Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/12/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 8/18/2020 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 8/21/2020 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/2/2020 Partial Approval LARRY ARNICK
Insulation 9/2/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval LARRY ARNICK
Insulation 9/4/2020 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/10/2020 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Approval LARRY ARNICK
Drywall Nailing 9/21/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Not Ready for Inspection LARRY ARNICK
Insulation 9/21/2020 Partial Approval LARRY ARNICK
Drywall Nailing 9/23/2020 Partial Approval LARRY ARNICK
Insulation 9/23/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Partial Approval LARRY ARNICK
Insulation 9/25/2020 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 10/5/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 10/8/2020 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 10/9/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 10/15/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 10/16/2020 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval LARRY ARNICK
Insulation 10/19/2020 Partial Approval LARRY ARNICK
Drywall Nailing 10/22/2020 Partial Approval LARRY ARNICK
Drywall Nailing 11/4/2020 Partial Approval LARRY ARNICK
Drywall Nailing 11/12/2020 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 11/16/2020 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 11/16/2020 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 11/20/2020 Conditional Approval LANNY MERRICK
Interior/Exterior Lathing 11/20/2020 Partial Approval EDWIN GREGORYONA
Wood Frame 11/20/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/25/2020 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Not Ready for Inspection LANNY MERRICK
Insulation 11/30/2020 Partial Approval LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/29/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 12/29/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 12/31/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 1/6/2021 Partial Approval LARRY ARNICK
T-Bar Ceiling 1/6/2021 Partial Approval LARRY ARNICK
Insulation 1/7/2021 Partial Approval LARRY ARNICK
T-Bar Ceiling 1/7/2021 Partial Approval LARRY ARNICK
Wood Frame 1/12/2021 Partial Approval LARRY ARNICK
Drywall Nailing 1/14/2021 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 1/15/2021 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 1/20/2021 Partial Approval LARRY ARNICK
Insulation 1/20/2021 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Partial Approval LARRY ARNICK
Insulation 1/21/2021 Partial Approval LARRY ARNICK
T-Bar Ceiling 1/21/2021 Partial Approval LARRY ARNICK
Drywall Nailing 1/27/2021 Partial Approval LARRY ARNICK
Drywall Nailing 2/11/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Insulation 2/11/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 2/16/2021 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 2/16/2021 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Partial Approval EDWIN GREGORYONA
Insulation 2/23/2021 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 3/5/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/11/2021 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 3/11/2021 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 3/22/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/6/2021 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 4/6/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/8/2021 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 4/20/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/11/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/14/2021 Partial Inspection EDWIN GREGORYONA
T-Bar Ceiling 6/8/2021 Partial Approval EDWIN GREGORYONA
Insulation 7/8/2021 Approved JONATHAN QUACH
Light Gage Steel Frame 7/14/2021 Partial Approval EDWIN GREGORYONA
Insulation 7/20/2021 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/4/2021 Partial Inspection EDWIN GREGORYONA
Special/Order Compliance 8/12/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/17/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/24/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 8/30/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 9/14/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/22/2021 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 9/22/2021 Approved EDWIN GREGORYONA
Final 10/28/2021 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 10/28/2021 Approved EDWIN GREGORYONA
Green Building Final 10/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 10/28/2021 Approved EDWIN GREGORYONA
METHANE-Final 10/28/2021 Approved EDWIN GREGORYONA
METHANE-Rough 10/28/2021 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 10/28/2021 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 10/28/2021 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 10/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Verify Rec and Parks Fee Memo 10/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/28/2021 Approved EDWIN GREGORYONA
Drywall Nailing 12/10/2021 Partial Approval EDWIN GREGORYONA
Grading Pre-Inspection 3/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 3/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 4/6/2022 Not Ready for Inspection EDWIN GREGORYONA
Final 6/8/2022 Partial Inspection EDWIN GREGORYONA
Green Building Final 6/8/2022 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 6/8/2022 Partial Inspection EDWIN GREGORYONA
Final 8/26/2022 Partial Inspection EDWIN GREGORYONA
Green Building Final 8/26/2022 Partial Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 8/26/2022 Approved EDWIN GREGORYONA
Final 10/20/2022 OK to Issue CofO EDWIN GREGORYONA
Green Building Final 10/20/2022 Approved EDWIN GREGORYONA