Deputy Methane Barrier
|
6/6/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Methane Barrier
|
6/7/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/7/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
6/7/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
6/7/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/13/2019
|
Partial Approval
|
FELIX CEBALLOS
|
|
METHANE-Barrier
|
6/13/2019
|
Approved
|
FELIX CEBALLOS
|
|
METHANE-Subgrade
|
6/13/2019
|
Partial Approval
|
FELIX CEBALLOS
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
6/17/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
6/26/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/26/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
6/26/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
7/1/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
7/1/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
7/12/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
7/12/2019
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/1/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/1/2019
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/8/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
8/8/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Rough
|
8/8/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/8/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
8/8/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
8/8/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/13/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Green Building Rough
|
8/13/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Rough
|
8/13/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/13/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
8/13/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
8/13/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/23/2019
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
8/23/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/28/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
8/28/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Rough
|
9/23/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
9/23/2019
|
Approved
|
DAVID BURKHEAD
|
|
Deputy Methane Barrier
|
9/24/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Methane Barrier
|
9/25/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
9/26/2019
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Methane Barrier
|
9/27/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/9/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
10/11/2019
|
Partial Approval
|
TIMOTHY BUXTON
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2019
|
Partial Approval
|
TIMOTHY BUXTON
|
|
Footing/Foundation/Slab
|
10/17/2019
|
Partial Approval
|
TIMOTHY BUXTON
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2019
|
Corrections Issued
|
GRANT WOODS
|
|
Pre-Inspection
|
10/18/2019
|
Partial Inspection
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
10/22/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/22/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
12/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Pre-Inspection
|
12/3/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
12/5/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
12/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
1/13/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
1/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
1/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
2/4/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/6/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
2/21/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
3/2/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/9/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
3/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
3/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
4/27/2020
|
No Access for Inspection
|
LARRY ARNICK
|
|
Structural Steel Frame
|
4/30/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/30/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
5/4/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
5/7/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
5/7/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
5/7/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Structural Steel Frame
|
5/7/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
5/8/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
5/8/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Structural Steel Frame
|
5/8/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
5/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
5/20/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
5/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
5/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/3/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Wood Frame
|
6/3/2020
|
Partial Inspection
|
JONATHAN QUACH
|
|
Insulation
|
6/4/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Insulation
|
6/9/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/11/2020
|
Approved
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/15/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/16/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Insulation
|
6/16/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Wood Frame
|
6/24/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/25/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Drywall Nailing
|
7/6/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
7/6/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2020
|
Corrections Issued
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
7/10/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/13/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/15/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/20/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/23/2020
|
Partial Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/27/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
8/12/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/14/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/18/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
8/21/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
8/26/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/1/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/2/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/2/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/4/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/4/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
9/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/21/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/21/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
9/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/25/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
10/5/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/8/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
10/8/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
10/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/15/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/16/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/19/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/19/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/22/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/4/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/12/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
11/16/2020
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
11/16/2020
|
Partial Approval
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
11/20/2020
|
Conditional Approval
|
LANNY MERRICK
|
|
Interior/Exterior Lathing
|
11/20/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
11/20/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/25/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/25/2020
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/30/2020
|
Not Ready for Inspection
|
LANNY MERRICK
|
|
Insulation
|
11/30/2020
|
Partial Approval
|
LANNY MERRICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/4/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
12/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/31/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
1/6/2021
|
Partial Approval
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
1/6/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/7/2021
|
Partial Approval
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
1/7/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
1/12/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/14/2021
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/15/2021
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/20/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/20/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/21/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/21/2021
|
Partial Approval
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
1/21/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/27/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/11/2021
|
Not Ready for Inspection
|
RUSSELL BONVOULOIR
|
|
Insulation
|
2/11/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
2/16/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
2/16/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
2/23/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/5/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/11/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/11/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/22/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/22/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/25/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/6/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/6/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/8/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
4/20/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/11/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/14/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
6/8/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
7/8/2021
|
Approved
|
JONATHAN QUACH
|
|
Light Gage Steel Frame
|
7/14/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
7/20/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/4/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
8/12/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/17/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/24/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
8/30/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
9/14/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
9/22/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
9/22/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
10/28/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Final
|
10/28/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
METHANE-Final
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
10/28/2021
|
SGSOV Not Ready
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
10/28/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Rec and Parks Fee Memo
|
10/28/2021
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/10/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Grading Pre-Inspection
|
3/21/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Final
|
3/21/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Final
|
4/6/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Final
|
6/8/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Final
|
6/8/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
6/8/2022
|
SGSOV Not Ready
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
6/8/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Final
|
8/26/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Final
|
8/26/2022
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
8/26/2022
|
SGSOV Approved
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
8/26/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
10/20/2022
|
OK to Issue CofO
|
EDWIN GREGORYONA
|
|
Green Building Final
|
10/20/2022
|
Approved
|
EDWIN GREGORYONA
|