3551 E 4TH ST 90063
Certificate Information: 3551 E 4TH ST 90063
- Application / Permit
- 18010-10000-02239
- Plan Check / Job No.
- B18LA09687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED ONE STORY (TYPE VB) EIGHT UNIT APARTMENT BUILDING W/ ATTACHED LAUNDRY/TRASH/RECYCLING AREA. THIS IS A TOC (TIER 3) PROJECT. NO PARKING REQUIRED SINCE THIS IS 100% RESTRICTED AFFORDABLE UNITS PER TOC GUIDELINES
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | JOHN VASQUEZ |
| Disabled Access Plans Picked Up | 6/12/2018 | APPLICANT |
| Green Plans Picked Up | 6/12/2018 | APPLICANT |
| Corrections Issued | 6/19/2018 | JOHN VASQUEZ |
| Quality Review Completed | 6/22/2018 | CHARLES CHANG |
| Building Plans Picked Up | 6/28/2018 | APPLICANT |
| Applicant returned to address corrections | 2/28/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 6/16/2022 | MANUEL MONTUFAR |
| Plan Check Approved | 7/6/2022 | MANUEL MONTUFAR |
| Issued | 7/6/2022 | APPLICANT |
| TCO Issued (Expire Date: 07-26-2025) | 1/27/2025 | RAFAEL ESPINOZA |
| TCO Issued (Expire Date: 01-12-2026) | 7/16/2025 | RAFAEL ESPINOZA |
| TCO Issued (Expire Date: 07-04-2026) | 1/5/2026 | RAFAEL ESPINOZA |
| CofO in Progress | 4/7/2026 | RAFAEL CORTES |
| Permit Finaled | 4/7/2026 | RAFAEL ESPINOZA |
| CofO Issued | 4/7/2026 | RAFAEL ESPINOZA |
| Permit Finaled | 4/7/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2018 | STEVE MELGAR |
| Highway dedication | Cleared | 9/25/2018 | STEVE MELGAR |
| Certificate of Compliance | Cleared | 10/17/2018 | SOPHIE GABEL-SCHEINBAU |
| Hydrant and Access approval | Cleared | 6/19/2019 | GILBERT URREA |
| City owned building/parcel | Cleared | 7/10/2019 | HAROOT AVANESIAN |
| "Q" conditions | Cleared | 7/11/2019 | SARAHI ORTEGA |
| Clean Up Green Up | Cleared | 7/11/2019 | SARAHI ORTEGA |
| Permit | Cleared | 7/11/2019 | JEANETTE VONG |
| Green Code | Cleared | 8/13/2019 | SARAH ABOULHOSN |
| Frnt yard landscape/Water mgmt | Cleared | 10/1/2019 | ANNA VAN |
| Opn space landscape/Water mgmt | Cleared | 10/1/2019 | ANNA VAN |
| Public Housing | Cleared | 10/4/2019 | GLEN OLIVER |
| DAS Clearance | Cleared | 10/23/2019 | JOHN VASQUEZ |
| Low Impact Development | Cleared | 2/18/2021 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/25/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/30/2021 | JEANIE LAM |
| Density Bonus 12.22.A.31 | Cleared | 4/4/2022 | JAMES MCCARTHY |
Contact Information
| Architect | Lehrer, Michael Berryl; Lic. No.: C12115 | 2140 HYPERION AVENUE LEHRER ARCHITECTS LA INC LOS ANGELES, CA 90027 |
| Contractor | Lloveras Carlos J; Lic. No.: 1082043-B | 965 SERFAS CLUB DRIVE CORONA, CA 92882 |
| Engineer | Mahlow, Elizabeth Joy Johnson; Lic. No.: C80463 | 4215 TOLAND WAY LOS ANGELES, CA 90065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2022 | Approved | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 9/27/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 12/20/2022 | Conditional Approval | RAFAEL ESPINOZA |
| Pre-Inspection | 2/28/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | LARRY ARNICK |
| Pre-Inspection | 6/28/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Insulation | 8/28/2023 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 8/31/2023 | Approved | LARRY ARNICK |
| Drywall Nailing | 9/11/2023 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 9/18/2023 | Not Ready for Inspection | LARRY ARNICK |
| Drywall Nailing | 9/20/2023 | Approved | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/18/2023 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 10/19/2023 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 1/24/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 9/4/2024 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 9/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 9/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 9/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 9/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 9/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 9/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/27/2024 | Approved | RAFAEL ESPINOZA |
| Green Building Final | 9/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Rough | 9/27/2024 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | RAFAEL ESPINOZA |
| Smoke Detectors | 9/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 9/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 9/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 1/7/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 1/7/2025 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 1/7/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 1/7/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 1/7/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 1/22/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 1/22/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 1/22/2025 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 1/22/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 1/22/2025 | Partial Approval | RAFAEL CORTES |
| Special/Order Compliance | 7/1/2025 | Approved | RAFAEL ESPINOZA |
| Special/Order Compliance | 12/10/2025 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 12/16/2025 | Approved | RAFAEL CORTES |
| Final | 4/1/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 4/1/2026 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 4/1/2026 | Approved | RAFAEL CORTES |
| Wood Frame | 4/1/2026 | Approved | RAFAEL CORTES |
| Final | 4/7/2026 | OK to Issue CofO | RAFAEL CORTES |