15350 W OXNARD ST BLDG C 91411

Certificate Information: 15350 W OXNARD ST BLDG C 91411

Application / Permit
18010-10000-02212
Plan Check / Job No.
B18LA09645
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
NEW 3-STORY TYPE II-B SELF-STORAGE BUILDING PER ZA-2017-4087-ZAA-SPR
Permit Issued
Issued on 9/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2018 APPLICANT
Green Plans Picked Up 5/31/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 RICARDO SUPAN
Corrections Issued 6/18/2018 RICARDO SUPAN
Quality Review Completed 7/5/2018 MINYE PAK
Disabled Access Plans Picked Up 7/9/2018 APPLICANT
Building Plans Picked Up 7/12/2018 APPLICANT
Applicant returned to address corrections 8/27/2018 RICARDO SUPAN
Applicant returned to address corrections 1/31/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 4/11/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 4/18/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 4/24/2019 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 4/25/2019 CAROLYNN NEPOMUCENO
Plan Check Approved 5/14/2019 CAROLYNN NEPOMUCENO
Plan Check Approved 5/16/2019 CAROLYNN NEPOMUCENO
Issued 9/2/2020 APPLICANT
CofO in Progress 8/27/2021 JEFFREY DURAN
CofO Issued 9/15/2021 RICKEY JACKSON
Permit Finaled 9/15/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 8/7/2018 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/7/2018 JOHN DALLAS
Miscellaneous Cleared 8/7/2018 LEE GUILBEAUX
DAS Clearance Cleared 8/24/2018 RICARDO SUPAN
Green Code Cleared 8/31/2018 DONALD CRICHLOW
Low Impact Development Cleared 2/7/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/19/2019 CHRISTINE REUSCH
Bicycle Parking Cleared 2/26/2019 LEE GUILBEAUX
Sewer availability Cleared 2/26/2019 LEE GUILBEAUX
Miscellaneous Cleared 4/16/2019 MARKOS PEREZ-BRAN
Prkng lot landscape/Water mgmt Cleared 4/23/2019 SOPHIE GABEL-SCHEINBAU
Site Plan review Cleared 4/23/2019 SOPHIE GABEL-SCHEINBAU
Tract Map conditions Cleared 4/23/2019 SOPHIE GABEL-SCHEINBAU
Tract Map conditions Cleared 4/23/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 4/23/2019 SOPHIE GABEL-SCHEINBAU
ZI Cleared 4/23/2019 SOPHIE GABEL-SCHEINBAU
Internal circulation Cleared 4/26/2019 DURRE SHAMSI
Trees in Parkway Cleared 4/26/2019 JOHN KIM
Disturb/Remove Protected Trees Cleared 5/3/2019 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 5/13/2019 GUILLERMO PETRA
Highway dedication Cleared 5/13/2019 GUILLERMO PETRA
Miscellaneous Cleared 5/13/2019 GUILLERMO PETRA
Permit Cleared 5/13/2019 GUILLERMO PETRA
Building over 3-story or 36-ft Cleared 5/14/2019 CALOSHA APPROVED

Contact Information

Architect Vakili, Shabnam; Lic. No.: C26298 25341 COMMERCENTRE DRIVE SUITE 100   KSP STUDIO    LAKE FOREST, CA 92630
Contractor Alston Construction; Lic. No.: 759899-B 8775 FOLSOM BLVD STE 201      SACRAMENTO, CA 95826
Engineer Maier,, John Luke; Lic. No.: C74894 3100 N ASHWOOD ST      ORANGE, CA 92865
Engineer Mckee,, Christopher Shannon; Lic. No.: C74414 160 S OLD SPRINGS RD STE 210      ANAHEIM, CA 92808
Engineer Shakerin, Kayvon; Lic. No.: C46202 25341 COMMERCENTRE DR STE 100      LAKE FOREST, CA 92630

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/1/2020 Corrections Issued JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 10/2/2020 Corrections Issued JEFFREY DURAN
Footing/Foundation/Slab 10/7/2020 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 10/13/2020 Corrections Issued JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 10/15/2020 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 10/21/2020 Approved HAMID PISHEHVAR
Reinforced Concrete Frame 10/22/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 10/23/2020 Approved HAMID PISHEHVAR
Green Building Rough 10/23/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Masonry Frame 10/23/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 10/23/2020 Not Ready for Inspection HAMID PISHEHVAR
Deputy Reinf. Masonry 10/28/2020 Approved HAMID PISHEHVAR
Green Building Rough 10/28/2020 Partial Approval HAMID PISHEHVAR
Reinforced Masonry Frame 10/28/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 10/28/2020 Not Ready for Inspection HAMID PISHEHVAR
Deputy Reinf. Masonry 10/29/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 10/30/2020 Conditional Approval DANIEL VARNUM
Reinforced Concrete Frame 10/30/2020 Approved DANIEL VARNUM
Footing/Foundation/Slab 11/4/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 11/17/2020 Approved HAMID PISHEHVAR
Pre-Inspection 11/18/2020 Approved HAMID PISHEHVAR
Reinforced Concrete Frame 11/18/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/20/2020 Approved HAMID PISHEHVAR
Reinforced Concrete Frame 11/20/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/23/2020 Conditional Approval RICKEY JACKSON
Green Building Rough 11/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 11/23/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/24/2020 Conditional Approval RICKEY JACKSON
Deputy Reinf. Masonry 11/25/2020 Approved SORIN CIRSTOIU
Masonry Wall/Backfill 11/25/2020 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 11/30/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/30/2020 Conditional Approval SORIN CIRSTOIU
Green Building Rough 11/30/2020 Partial Approval HAMID PISHEHVAR
Reinforced Masonry Frame 11/30/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 11/30/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 12/1/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/2/2020 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 12/2/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/4/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/4/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 12/7/2020 Approved JEFFREY DURAN
Green Building Rough 12/7/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 12/7/2020 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 12/7/2020 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 12/8/2020 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 12/8/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/9/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/9/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 12/10/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/11/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/11/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 12/14/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/15/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/15/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 12/16/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/16/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 12/17/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/17/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 12/18/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 12/21/2020 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 12/22/2020 Partial Approval ROBERT DAVIS
Green Building Rough 1/4/2021 Partial Approval HAMID PISHEHVAR
Structural Steel Frame 1/4/2021 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 1/4/2021 Not Ready for Inspection HAMID PISHEHVAR
Deputy Reinf. Concrete 1/5/2021 Approved HAMID PISHEHVAR
Deputy Drilled-In Anchors 1/6/2021 Approved HAMID PISHEHVAR
Deputy Drilled-In Anchors 1/8/2021 Approved HAMID PISHEHVAR
Green Building Rough 1/8/2021 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 1/8/2021 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/8/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/14/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/15/2021 Conditional Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 1/19/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 1/20/2021 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 2/2/2021 Partial Approval CAMERON CHABAN
Green Building Rough 2/5/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 2/5/2021 Not Ready for Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 2/5/2021 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 2/9/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 2/9/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 2/10/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 2/16/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 2/17/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 2/17/2021 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 2/17/2021 Not Ready for Inspection CAMERON CHABAN
Deputy Drilled-In Anchors 2/18/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/25/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 2/25/2021 Partial Approval HAMID PISHEHVAR
Masonry Wall/Backfill 2/26/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/2/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 3/2/2021 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 3/3/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/4/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/5/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 3/8/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 3/15/2021 Approved HAMID PISHEHVAR
Green Building Rough 3/15/2021 Partial Inspection CAMERON CHABAN
Reinforced Masonry Frame 3/15/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 3/15/2021 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Masonry 3/16/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/17/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/18/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/18/2021 Partial Inspection CAMERON CHABAN
Reinforced Masonry Frame 3/18/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 3/18/2021 Partial Inspection CAMERON CHABAN
Deputy Reinf. Masonry 3/19/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 3/19/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 3/26/2021 Partial Inspection CAMERON CHABAN
Structural Steel Frame 3/26/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 3/26/2021 Partial Approval CAMERON CHABAN
Green Building Rough 3/31/2021 Not Ready for Inspection CAMERON CHABAN
Structural Steel Frame 3/31/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 3/31/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 4/6/2021 Partial Approval HAMID PISHEHVAR
Structural Steel Frame 4/6/2021 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 4/6/2021 Not Ready for Inspection HAMID PISHEHVAR
Green Building Rough 4/8/2021 Not Ready for Inspection JEFFREY FULTON
Structural Steel Frame 4/8/2021 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 4/8/2021 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval DANIEL VARNUM
Insulation 4/19/2021 Approved CAMERON CHABAN
Drywall Nailing 5/4/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 5/4/2021 Conditional Approval CAMERON CHABAN
Drywall Nailing 5/7/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 5/7/2021 Not Ready for Inspection CAMERON CHABAN
Insulation 5/24/2021 Conditional Approval CAMERON CHABAN
Special/Order Compliance 5/27/2021 Partial Approval HAMID PISHEHVAR
Interior/Exterior Lathing 6/2/2021 Approved CAMERON CHABAN
Drywall Nailing 7/15/2021 Approved JEFF BYTHEWAY
Final 7/15/2021 Corrections Issued JEFF BYTHEWAY
Footing/Foundation/Slab 7/15/2021 Approved JEFF BYTHEWAY
Green Building Final 7/15/2021 Approved JEFF BYTHEWAY
Green Building Rough 7/15/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 7/15/2021 Approved JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 7/15/2021 SGSOV Approved JEFF BYTHEWAY
Smoke Detectors 7/15/2021 Approved JEFF BYTHEWAY
Structural Steel Frame 7/15/2021 Approved JEFF BYTHEWAY
Verify Sprinkler Sign Off 7/15/2021 Approved JEFF BYTHEWAY
Final 7/19/2021 Conditional Approval CAMERON CHABAN
Final 7/21/2021 Partial Inspection CAMERON CHABAN
Special/Order Compliance 8/2/2021 Corrections Issued CAMERON CHABAN