2641 N RICH ST 90039
Certificate Information: 2641 N RICH ST 90039
- Application / Permit
- 18010-10000-02181
- Plan Check / Job No.
- B18LA09511
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ACCESSORY DWELLING UNIT FOR AN (E) SINGLE-FAMILY RESIDENCE PER AB 494 AND SB 229.
- Permit Issued
- Issued on 10/1/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | MONICA RAMIREZ |
| Corrections Issued | 6/21/2018 | MONICA RAMIREZ |
| Green Plans Picked Up | 6/21/2018 | APPLICANT |
| Quality Review Completed | 6/26/2018 | TIEN JEN WANG |
| Building Plans Picked Up | 6/28/2018 | APPLICANT |
| Applicant returned to address corrections | 8/23/2018 | MONICA RAMIREZ |
| Plan Check Approved | 9/13/2018 | MONICA RAMIREZ |
| Issued | 10/1/2018 | LADBS |
| CofO in Progress | 11/15/2021 | JOSEPH MCGARRY |
| Permit Finaled | 12/30/2021 | RONALD MYRICK |
| CofO Issued | 12/30/2021 | RONALD MYRICK |
| Permit Finaled | 12/30/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 8/8/2018 | KHEDER ALRAZAA |
| ZI | Cleared | 8/16/2018 | FIPE LEILUA |
| Address approval | Cleared | 8/22/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 8/22/2018 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 8/22/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 8/22/2018 | ADRIAN SANCHEZ |
Contact Information
| Architect | , ; Lic. No.: C34617 | 949 CHUNG KING ROAD LOS ANGELES, CA 90012 |
| Contractor | J C Construction; Lic. No.: 756599-B | 13721 DE ALCALA DR LA MIRADA, CA 90638 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/21/2019 | No Access for Inspection | DAVID CHAN |
| PLUMBING-Rough | 10/21/2019 | No Access for Inspection | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 10/25/2019 | Partial Inspection | DAVID CHAN |
| PLUMBING-Rough | 10/25/2019 | Conditional Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 11/4/2019 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 11/4/2019 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 3/10/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 3/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 3/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 3/17/2020 | Approved | MICHAEL FAUNCE |
| Deputy Drilled-In Anchors | 3/31/2020 | Conditional Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/12/2020 | Corrections Issued | MATTHEW NUCKOLLS |
| ELECTRICAL-Rough | 6/12/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Green Building Rough | 6/12/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| HVAC-Rough | 6/12/2020 | Corrections Issued | MATTHEW NUCKOLLS |
| MERV13>=Rough | 6/12/2020 | Approved | MATTHEW NUCKOLLS |
| PLUMBING-Rough | 6/12/2020 | Corrections Issued | MATTHEW NUCKOLLS |
| Verify Sprinkler Sign Off | 6/12/2020 | Approved | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 6/19/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 6/19/2020 | Approved | COREY HUPP |
| Green Building Rough | 6/19/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 7/6/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/6/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/6/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/6/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 7/21/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/21/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/21/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/24/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 7/24/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/3/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/1/2021 | Corrections Issued | RUBEN SALAS |
| Final | 3/1/2021 | Corrections Issued | RUBEN SALAS |
| Green Building Final | 3/1/2021 | Corrections Issued | RUBEN SALAS |
| HVAC-Final | 3/1/2021 | Not Ready for Inspection | RUBEN SALAS |
| MERV13>=Final | 3/1/2021 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Final | 3/1/2021 | Corrections Issued | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 3/1/2021 | SGSOV Not Ready | RUBEN SALAS |
| Service/Power Release | 3/1/2021 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 3/1/2021 | Approved | RUBEN SALAS |
| Final | 6/25/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 6/25/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 6/25/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 6/25/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 6/25/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 6/25/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 6/25/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 7/2/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 7/2/2021 | Approved | JOSEPH MCGARRY |
| MERV13>=Final | 7/2/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 7/2/2021 | Not Required | JOSEPH MCGARRY |
| ELECTRICAL-Final | 11/9/2021 | Approved | JOSEPH MCGARRY |
| Final | 11/9/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 11/9/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 11/9/2021 | Approved | JOSEPH MCGARRY |