137-139 E 104TH ST 90003

Certificate Information: 137-139 E 104TH ST 90003

Application / Permit
18010-10000-02159
Plan Check / Job No.
B18LA09401
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2-story duplex with attached 1-car garage at front and 2-car garage at rear of building.
Permit Issued
Issued on 4/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2018 APPLICANT
Green Plans Picked Up 5/29/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 ZAW HAN
Corrections Issued 6/11/2018 ZAW HAN
Quality Review Completed 6/15/2018 HERNAN ARREOLA
Building Plans Picked Up 6/19/2018 APPLICANT
Plan Check Approved 2/20/2020 ZAW HAN
Issued 4/23/2020 LADBS
CofO in Progress 11/16/2020 ANSON MAGLASANG
CofO in Progress 11/20/2020 ANSON MAGLASANG
CofO in Progress 11/23/2020 ANSON MAGLASANG
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 1/16/2020 ORVAL HERNANDEZ-MARCI
Green Code Cleared 1/22/2020 NEGAR NEJAD
Hydrant and Access approval Cleared 1/24/2020 JOHN CONNEALLY
Address approval Cleared 1/27/2020 JEANETTE VONG
Address approval Cleared 1/27/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/27/2020 JEANETTE VONG
Permit Cleared 1/27/2020 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/27/2020 JEANETTE VONG
Sewer availability Cleared 1/27/2020 JEANETTE VONG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2020 Approved EUGENE CASSIDY
Deputy Other (see comments) 5/20/2020 Conditional Approval BRIAN CHRISTIAN
Deputy Reinf. Concrete 5/20/2020 Conditional Approval BRIAN CHRISTIAN
PLUMBING-Rough 5/29/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 5/29/2020 Approved EUGENE CASSIDY
Wood Frame 5/29/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Partial Approval BRIAN CHRISTIAN
Insulation 6/2/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/18/2020 Partial Approval BRIAN CHRISTIAN
Deputy Other (see comments) 7/2/2020 Conditional Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/7/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/7/2020 Approved EUGENE CASSIDY
Gas Test 8/7/2020 Approved EUGENE CASSIDY
Green Building Rough 8/7/2020 Approved EUGENE CASSIDY
HVAC-Rough 8/7/2020 Conditional Approval EUGENE CASSIDY
PLUMBING-Rough 8/7/2020 Approved EUGENE CASSIDY
Sewer 8/7/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 8/7/2020 Approved EUGENE CASSIDY
Insulation 8/11/2020 Approved EUGENE CASSIDY
Drywall Nailing 8/19/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/19/2020 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 8/26/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/9/2020 Approved EUGENE CASSIDY
Final 11/9/2020 OK to Issue CofO EUGENE CASSIDY
Gas Test 11/9/2020 Approved EUGENE CASSIDY
Green Building Final 11/9/2020 Approved EUGENE CASSIDY
HVAC-Final 11/9/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/9/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 11/9/2020 Approved EUGENE CASSIDY
Smoke Detectors 11/9/2020 Approved EUGENE CASSIDY