137-139 E 104TH ST 90003
Certificate Information: 137-139 E 104TH ST 90003
- Application / Permit
- 18010-10000-02159
- Plan Check / Job No.
- B18LA09401
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2-story duplex with attached 1-car garage at front and 2-car garage at rear of building.
- Permit Issued
- Issued on 4/23/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/25/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2018 | APPLICANT |
| Green Plans Picked Up | 5/29/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | ZAW HAN |
| Corrections Issued | 6/11/2018 | ZAW HAN |
| Quality Review Completed | 6/15/2018 | HERNAN ARREOLA |
| Building Plans Picked Up | 6/19/2018 | APPLICANT |
| Plan Check Approved | 2/20/2020 | ZAW HAN |
| Issued | 4/23/2020 | LADBS |
| CofO in Progress | 11/16/2020 | ANSON MAGLASANG |
| CofO in Progress | 11/20/2020 | ANSON MAGLASANG |
| CofO in Progress | 11/23/2020 | ANSON MAGLASANG |
| Permit Finaled | 11/25/2020 | DEROLD HAUFF |
| CofO Issued | 11/25/2020 | DEROLD HAUFF |
| Permit Finaled | 11/25/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/16/2020 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 1/22/2020 | NEGAR NEJAD |
| Hydrant and Access approval | Cleared | 1/24/2020 | JOHN CONNEALLY |
| Address approval | Cleared | 1/27/2020 | JEANETTE VONG |
| Address approval | Cleared | 1/27/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | JEANETTE VONG |
| Permit | Cleared | 1/27/2020 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/27/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 1/27/2020 | JEANETTE VONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2020 | Approved | EUGENE CASSIDY |
| Deputy Other (see comments) | 5/20/2020 | Conditional Approval | BRIAN CHRISTIAN |
| Deputy Reinf. Concrete | 5/20/2020 | Conditional Approval | BRIAN CHRISTIAN |
| PLUMBING-Rough | 5/29/2020 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 5/29/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 5/29/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 6/2/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2020 | Partial Approval | BRIAN CHRISTIAN |
| Deputy Other (see comments) | 7/2/2020 | Conditional Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/7/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/7/2020 | Approved | EUGENE CASSIDY |
| Gas Test | 8/7/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/7/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/7/2020 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 8/7/2020 | Approved | EUGENE CASSIDY |
| Sewer | 8/7/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 8/7/2020 | Approved | EUGENE CASSIDY |
| Insulation | 8/11/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/19/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/19/2020 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/26/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/9/2020 | Approved | EUGENE CASSIDY |
| Final | 11/9/2020 | OK to Issue CofO | EUGENE CASSIDY |
| Gas Test | 11/9/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 11/9/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 11/9/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/9/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 11/9/2020 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/9/2020 | Approved | EUGENE CASSIDY |