13243 W RAVEN ST 91342

Certificate Information: 13243 W RAVEN ST 91342

Application / Permit
18010-10000-02088
Plan Check / Job No.
B18LA09082
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAINTAIN (E) BASEMENT AND ADD (N) 2 STORY SFD
Permit Issued
Issued on 10/4/2018
Issuing Office
Valley
Current Status
CofO Issued on 12/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 MONICA RAMIREZ
Corrections Issued 6/26/2018 ANA AVELAR
Quality Review Completed 6/27/2018 TIEN JEN WANG
Building Plans Picked Up 7/3/2018 APPLICANT
Green Plans Picked Up 7/3/2018 APPLICANT
Plan Check Approved 10/3/2018 ANA AVELAR
Issued 10/4/2018 LADBS
CofO in Progress 11/13/2020 MISAEL ESPARZA
CofO Issued 12/29/2021 MICHAEL SMITH
Permit Finaled 12/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 8/24/2018 KHEDER ALRAZAA
Address approval Cleared 9/6/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 9/6/2018 MICHAEL CASTILLO
Sewer availability Cleared 9/6/2018 MICHAEL CASTILLO
Low Impact Development Cleared 9/18/2018 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 9/20/2018 MICHAEL CASTILLO

Contact Information

Contractor A And M Construction Inc; Lic. No.: 1037084-B 724 GENEVA ST      GLENDALE, CA 91206
Engineer Kazarians, Ardashes; Lic. No.: C36687 1528 CANADA BLVD STE 206      GLENDALE, CA 91208

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/14/2018 Approved ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 11/15/2018 Corrections Issued CHARLES POWELL
Special/Order Compliance 11/15/2018 Approved PIERRE VEGA
Footing/Foundation/Slab 11/19/2018 Not Ready for Inspection CHARLES POWELL
Deputy Drilled-In Anchors 4/30/2019 Approved CHARLES POWELL
Footing/Foundation/Slab 6/5/2019 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 7/11/2019 Corrections Issued CHARLES POWELL
Green Building Rough 7/11/2019 Not Ready for Inspection CHARLES POWELL
Special/Order Compliance 7/11/2019 Approved ROBERT MINASSIANS
PLUMBING-Rough 7/17/2019 Not Ready for Inspection CHARLES POWELL
Special/Order Compliance 7/17/2019 Approved ROBERT MINASSIANS
Wood Frame 7/17/2019 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 7/26/2019 Not Ready for Inspection CHARLES POWELL
Green Building Rough 7/26/2019 Not Ready for Inspection CHARLES POWELL
Special/Order Compliance 7/26/2019 Approved ROBERT MINASSIANS
BUILDING-Rough-Frame 8/5/2019 Partial Approval CHARLES POWELL
Green Building Rough 8/5/2019 Not Ready for Inspection CHARLES POWELL
Special/Order Compliance 8/5/2019 Approved ROBERT MINASSIANS
Insulation 8/7/2019 Partial Approval CHARLES POWELL
PLUMBING-Rough 8/7/2019 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 8/9/2019 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/2/2019 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 2/12/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 2/12/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/21/2020 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Inspection WILLIAM KUEHN
Green Building Rough 2/21/2020 Not Ready for Inspection WILLIAM KUEHN
PLUMBING-Rough 2/21/2020 Not Ready for Inspection WILLIAM KUEHN
Deputy Drilled-In Anchors 3/9/2020 Conditional Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 3/10/2020 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 3/10/2020 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 3/10/2020 Not Ready for Inspection TROY SANDERS
Special/Order Compliance 3/10/2020 Approved CHARLES POWELL
Special/Order Compliance 3/10/2020 Partial Inspection ROBERT MINASSIANS
ELECTRICAL-Rough 3/18/2020 Not Ready for Inspection TROY SANDERS
Excavation/Setback/Form/Re-Bar 3/18/2020 Partial Approval TROY SANDERS
PLUMBING-Rough 3/23/2020 Not Ready for Inspection TROY SANDERS
Wood Frame 3/23/2020 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 4/1/2020 Not Ready for Inspection TROY SANDERS
Green Building Rough 4/1/2020 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 4/1/2020 Not Ready for Inspection TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Approved TROY SANDERS
Shower Pan 4/7/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 4/15/2020 Conditional Approval TROY SANDERS
ELECTRICAL-Rough 4/15/2020 Approved TROY SANDERS
Green Building Rough 4/15/2020 Approved TROY SANDERS
PLUMBING-Rough 4/15/2020 Approved TROY SANDERS
HVAC-Rough 4/17/2020 Approved TROY SANDERS
Insulation 4/20/2020 Approved TROY SANDERS
Drywall Nailing 5/5/2020 Approved TROY SANDERS
Interior/Exterior Lathing 5/11/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 8/11/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 8/11/2020 Not Ready for Inspection MISAEL ESPARZA
Final 8/11/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/11/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 8/11/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 8/11/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 8/24/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/24/2020 SGSOV Not Ready MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Not Ready MISAEL ESPARZA
Final 10/16/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/22/2020 Approved MISAEL ESPARZA
Final 10/22/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/22/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 10/22/2020 Approved MISAEL ESPARZA
Final 10/28/2020 Corrections Issued MISAEL ESPARZA
Final 10/30/2020 Partial Approval MISAEL ESPARZA
ELECTRICAL-Final 11/13/2020 Approved MISAEL ESPARZA
Final 11/13/2020 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 11/13/2020 Approved MISAEL ESPARZA