13243 W RAVEN ST 91342
Certificate Information: 13243 W RAVEN ST 91342
- Application / Permit
- 18010-10000-02088
- Plan Check / Job No.
- B18LA09082
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAINTAIN (E) BASEMENT AND ADD (N) 2 STORY SFD
- Permit Issued
- Issued on 10/4/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | MONICA RAMIREZ |
| Corrections Issued | 6/26/2018 | ANA AVELAR |
| Quality Review Completed | 6/27/2018 | TIEN JEN WANG |
| Building Plans Picked Up | 7/3/2018 | APPLICANT |
| Green Plans Picked Up | 7/3/2018 | APPLICANT |
| Plan Check Approved | 10/3/2018 | ANA AVELAR |
| Issued | 10/4/2018 | LADBS |
| CofO in Progress | 11/13/2020 | MISAEL ESPARZA |
| CofO Issued | 12/29/2021 | MICHAEL SMITH |
| Permit Finaled | 12/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 8/24/2018 | KHEDER ALRAZAA |
| Address approval | Cleared | 9/6/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 9/6/2018 | MICHAEL CASTILLO |
| Low Impact Development | Cleared | 9/18/2018 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 9/20/2018 | MICHAEL CASTILLO |
Contact Information
| Contractor | A And M Construction Inc; Lic. No.: 1037084-B | 724 GENEVA ST GLENDALE, CA 91206 |
| Engineer | Kazarians, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/14/2018 | Approved | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 11/15/2018 | Corrections Issued | CHARLES POWELL |
| Special/Order Compliance | 11/15/2018 | Approved | PIERRE VEGA |
| Footing/Foundation/Slab | 11/19/2018 | Not Ready for Inspection | CHARLES POWELL |
| Deputy Drilled-In Anchors | 4/30/2019 | Approved | CHARLES POWELL |
| Footing/Foundation/Slab | 6/5/2019 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/11/2019 | Corrections Issued | CHARLES POWELL |
| Green Building Rough | 7/11/2019 | Not Ready for Inspection | CHARLES POWELL |
| Special/Order Compliance | 7/11/2019 | Approved | ROBERT MINASSIANS |
| PLUMBING-Rough | 7/17/2019 | Not Ready for Inspection | CHARLES POWELL |
| Special/Order Compliance | 7/17/2019 | Approved | ROBERT MINASSIANS |
| Wood Frame | 7/17/2019 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/26/2019 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 7/26/2019 | Not Ready for Inspection | CHARLES POWELL |
| Special/Order Compliance | 7/26/2019 | Approved | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 8/5/2019 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 8/5/2019 | Not Ready for Inspection | CHARLES POWELL |
| Special/Order Compliance | 8/5/2019 | Approved | ROBERT MINASSIANS |
| Insulation | 8/7/2019 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 8/7/2019 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2019 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2019 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 2/12/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/12/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2020 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/21/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 2/21/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 2/21/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Deputy Drilled-In Anchors | 3/9/2020 | Conditional Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 3/10/2020 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 3/10/2020 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 3/10/2020 | Not Ready for Inspection | TROY SANDERS |
| Special/Order Compliance | 3/10/2020 | Approved | CHARLES POWELL |
| Special/Order Compliance | 3/10/2020 | Partial Inspection | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 3/18/2020 | Not Ready for Inspection | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 3/23/2020 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 3/23/2020 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 4/1/2020 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 4/1/2020 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 4/1/2020 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2020 | Approved | TROY SANDERS |
| Shower Pan | 4/7/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/15/2020 | Conditional Approval | TROY SANDERS |
| ELECTRICAL-Rough | 4/15/2020 | Approved | TROY SANDERS |
| Green Building Rough | 4/15/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/15/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 4/17/2020 | Approved | TROY SANDERS |
| Insulation | 4/20/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 5/5/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/11/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/11/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/11/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/11/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/11/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 8/11/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 8/11/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/24/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/24/2020 | SGSOV Not Ready | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Not Ready | MISAEL ESPARZA |
| Final | 10/16/2020 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/22/2020 | Approved | MISAEL ESPARZA |
| Final | 10/22/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/22/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/22/2020 | Approved | MISAEL ESPARZA |
| Final | 10/28/2020 | Corrections Issued | MISAEL ESPARZA |
| Final | 10/30/2020 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/13/2020 | Approved | MISAEL ESPARZA |
| Final | 11/13/2020 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 11/13/2020 | Approved | MISAEL ESPARZA |