1032 N CORONADO ST 1-33 90026

Certificate Information: 1032 N CORONADO ST 1-33 90026

Application / Permit
18010-10000-01919
Plan Check / Job No.
B18LA08640
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5 Story 33 unit apartment 1 levels of subterranian parking with 4 units set aside for Extremely Low income units per 12.22.A.31 TOC Tier 3
Permit Issued
Issued on 11/12/2020
Issuing Office
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2018 APPLICANT
Disabled Access Plans Picked Up 5/23/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 HERNAN ARREOLA
Corrections Issued 6/12/2018 HERNAN ARREOLA
Quality Review Completed 6/19/2018 BILL STUTSMAN
Building Plans Picked Up 6/27/2018 APPLICANT
Plan Check Approved 7/31/2019 HERNAN ARREOLA
Issued 11/12/2020 APPLICANT
CofO in Progress 5/31/2024 DAVID BURKHEAD
Permit Finaled 5/31/2024 ERNESTO CORRAL
CofO Issued 5/31/2024 ERNESTO CORRAL
Permit Finaled 5/31/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/10/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 8/10/2018 NAZILA NOORIFAR
Permit Cleared 8/10/2018 NAZILA NOORIFAR
Sewer availability Cleared 8/10/2018 NAZILA NOORIFAR
Hydrant and Access approval Cleared 8/15/2018 GEORGE SUCHAND
Construction near power lines Cleared 1/18/2019 NADER ISKANDER
Highway dedication Cleared 1/18/2019 ADRIAN SANCHEZ
Density Bonus 12.22.A.31 Cleared 2/12/2019 MICHAEL ZIRBES
Frnt yard landscape/Water mgmt Cleared 3/8/2019 STEVEN WECHSLER
Miscellaneous Cleared 3/8/2019 STEVEN WECHSLER
Opn space landscape/Water mgmt Cleared 3/8/2019 STEVEN WECHSLER
Green Code Cleared 3/12/2019 DONALD CRICHLOW
Trees in Parkway Cleared 3/18/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 4/4/2019 MITESH PATEL
Fire Marshall Fire Life Safety Cleared 4/19/2019 OSCAR SALGADO JR
DAS Clearance Cleared 5/23/2019 WAI LAU
Roof/Waste drainage to street Cleared 6/21/2019 JEANETTE VONG
Building over 3-story or 36-ft Cleared 6/24/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 6/24/2019 CALOSHA APPROVED

Contact Information

Architect Maly,, Farzin; Lic. No.: C33731 7136 HASKELL AVENUE # 320      VAN NUYS, CA 91406
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/13/2020 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/10/2021 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 3/9/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/10/2021 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Shotcrete 3/11/2021 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 3/12/2021 Partial Inspection DANIEL MC AULIFFE
METHANE-Barrier 3/12/2021 Not Ready for Inspection DANIEL MC AULIFFE
METHANE-Subgrade 3/12/2021 Partial Inspection DANIEL MC AULIFFE
Deputy Shotcrete 3/15/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 3/16/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/19/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/6/2021 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/6/2021 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/8/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/13/2021 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 4/15/2021 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/15/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 4/15/2021 Partial Approval DANIEL MC AULIFFE
METHANE-Barrier 4/15/2021 Partial Inspection DANIEL MC AULIFFE
METHANE-Subgrade 4/15/2021 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Shotcrete 4/19/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/22/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 4/22/2021 Partial Approval DANIEL MC AULIFFE
METHANE-Barrier 4/22/2021 Approved DANIEL MC AULIFFE
METHANE-Subgrade 4/22/2021 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/29/2021 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/29/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/6/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/12/2021 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Drilled-In Anchors 5/14/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/14/2021 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 5/18/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/20/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/17/2021 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/22/2021 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/24/2021 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 7/6/2021 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 7/8/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 7/14/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 7/14/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 7/15/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 7/15/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 7/16/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 7/16/2021 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 7/19/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 7/21/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 7/23/2021 Conditional Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 8/12/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/2/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/10/2021 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 9/15/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/8/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/8/2021 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/9/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/10/2021 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval DANIEL MC AULIFFE
Wood Frame 12/7/2021 Partial Approval DANIEL MC AULIFFE
Wood Frame 12/21/2021 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Partial Approval DANIEL MC AULIFFE
Wood Frame 1/10/2022 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 1/11/2022 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/2/2022 Partial Approval DANIEL MC AULIFFE
Wood Frame 2/2/2022 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/18/2022 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 3/3/2022 Partial Approval DANIEL MC AULIFFE
Wood Frame 4/13/2022 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 4/14/2022 Conditional Approval DAVID BURKHEAD
Wood Frame 4/20/2022 Partial Approval DANIEL MC AULIFFE
Interior/Exterior Lathing 5/26/2022 Partial Approval TED RIES
Drywall Nailing 6/9/2022 Partial Approval NICK DANERI
Insulation 9/21/2022 Approved TED RIES
Drywall Nailing 10/13/2022 Partial Approval TED RIES
Interior/Exterior Lathing 10/13/2022 Corrections Issued TED RIES
Interior/Exterior Lathing 10/21/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 10/21/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 11/2/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/18/2023 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/18/2023 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 7/18/2023 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 7/19/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/26/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/26/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/26/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/3/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 8/3/2023 Partial Approval EDWIN GREGORYONA
Final 2/15/2024 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 2/15/2024 Approved DAVID BURKHEAD
METHANE-Final 2/15/2024 Approved DAVID BURKHEAD
METHANE-Rough 2/15/2024 Approved DAVID BURKHEAD
Reinforced Concrete Frame 2/15/2024 Approved DAVID BURKHEAD
Reinforced Masonry Frame 2/15/2024 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 2/15/2024 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 2/15/2024 Approved DAVID BURKHEAD
Final 2/26/2024 Partial Inspection DAVID BURKHEAD
Final 5/21/2024 Corrections Issued DAVID BURKHEAD
Final 5/24/2024 Partial Inspection DAVID BURKHEAD
Final 5/30/2024 OK to Issue CofO DAVID BURKHEAD