15038 W GAULT ST 91405
Certificate Information: 15038 W GAULT ST 91405
- Application / Permit
- 18010-10000-01814
- Plan Check / Job No.
- B18LA08241
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD W/ATTACHED GARAGE
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 3/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | ZAW HAN |
| Corrections Issued | 6/14/2018 | ZAW HAN |
| Quality Review Completed | 6/15/2018 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/22/2019 | ZAW HAN |
| Applicant returned to address corrections | 9/10/2019 | ZAW HAN |
| Applicant returned to address corrections | 3/19/2020 | ZAW HAN |
| Plan Check Approved | 3/31/2020 | ZAW HAN |
| Building Plans Picked Up | 4/1/2020 | APPLICANT |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 3/1/2022 | MICHAEL TEMPLE |
| Permit Finaled | 3/1/2022 | RONALD MYRICK |
| CofO Issued | 3/1/2022 | RONALD MYRICK |
| Permit Finaled | 3/1/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2018 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2018 | JAMES MORALEZ |
| Permit | Cleared | 5/15/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 5/24/2019 | OSCAR SALGADO JR |
| Miscellaneous | Cleared | 1/17/2020 | JASON CHAN |
| Miscellaneous | Cleared | 1/17/2020 | JASON CHAN |
| ZA Case | Cleared | 1/17/2020 | JASON CHAN |
| Green Code | Cleared | 2/18/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 2/26/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/26/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/27/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | , ; Lic. No.: C33262 | , |
| Contractor | Owner-Builder | , |
| Engineer | Lam, Chsung Say; Lic. No.: C78287 | 6919 THELMA AVE BUENA PARK, CA 90620 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 8/27/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/20/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 10/20/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 10/20/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Wood Frame | 10/20/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/25/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/25/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 11/25/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Wood Frame | 11/25/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 1/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 1/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/17/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/17/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/17/2021 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/17/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/1/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 4/1/2021 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/15/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 4/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 4/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 4/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Wood Frame | 4/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/21/2021 | Corrections Issued | CHARLES POWELL |
| BUILDING-Rough-Frame | 4/27/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/27/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 4/27/2021 | Approved | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 4/27/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/13/2021 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 5/14/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 1/20/2022 | No Access for Inspection | RICHARD DOCKUS |
| Final | 1/20/2022 | No Access for Inspection | RICHARD DOCKUS |
| Green Building Final | 1/20/2022 | No Access for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 1/20/2022 | No Access for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 1/20/2022 | No Access for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 1/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 1/26/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 1/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 1/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 1/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 1/26/2022 | Approved | RICHARD DOCKUS |
| Final | 2/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 2/1/2022 | Approved | RICHARD DOCKUS |
| Service/Power Release | 2/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Pre-Inspection | 2/4/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 2/7/2022 | Corrections Issued | MICHAEL TEMPLE |
| Service/Power Release | 2/7/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 3/1/2022 | OK to Issue CofO | MICHAEL TEMPLE |
| Service/Power Release | 3/1/2022 | Approved | MICHAEL TEMPLE |