4718 W FRANKLIN AVE 90027

Certificate Information: 4718 W FRANKLIN AVE 90027

Application / Permit
18010-10000-01786
Plan Check / Job No.
B18LA08166
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
3 STORY 6 UNIT TYPEVA APARTMENT BUILDING OVER ONE LEVEL TYPE IA SUBTERRANEAN PARKING BASEMENT GARAGE
Permit Issued
Issued on 11/24/2020
Issuing Office
Metro
Current Status
Issued on 11/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/26/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 DEAN LEE
Corrections Issued 6/21/2018 DEAN LEE
Quality Review Completed 6/28/2018 SIAVOSH POURSABAHIAN
Disabled Access Plans Picked Up 6/29/2018 APPLICANT
Green Plans Picked Up 6/29/2018 APPLICANT
Applicant returned to address corrections 10/31/2018 DEAN LEE
Applicant returned to address corrections 12/5/2018 DEAN LEE
Applicant returned to address corrections 10/18/2019 DEAN LEE
Applicant returned to address corrections 12/11/2019 DEAN LEE
Applicant returned to address corrections 1/8/2020 DEAN LEE
Applicant returned to address corrections 1/29/2020 DEAN LEE
Applicant returned to address corrections 9/10/2020 DEAN LEE
Plan Check Approved 10/20/2020 DEAN LEE
Issued 11/24/2020 APPLICANT
Building Plans Picked Up 12/1/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/31/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/31/2018 STEVE MELGAR
Highway dedication Cleared 10/31/2018 STEVE MELGAR
Sewer availability Cleared 10/31/2018 STEVE MELGAR
Permit Cleared 11/15/2018 JAMES MORALEZ
Excavation more than 5-ft deep Cleared 1/17/2019 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/25/2019 DEAN LEE
Low Impact Development Cleared 7/3/2019 JORGE MEJIA LEMUS
Encroachment in public way Cleared 7/30/2019 KAREN LE
Hydrant and Access approval Cleared 7/30/2019 GEORGE SUCHAND
Green Code Cleared 8/12/2019 DEAN LEE
DAS Clearance Cleared 8/20/2019 ELIZABETH TOMS
Fire Marshall Fire Life Safety Cleared 10/23/2019 WILLIAM JOHNS
Opn space landscape/Water mgmt Cleared 11/18/2019 ANNA VIDAL
Specific Plan Cleared 11/18/2019 ANNA VIDAL
Tract Map conditions Cleared 11/18/2019 ANNA VIDAL
ZA Case Cleared 11/18/2019 ANNA VIDAL
ZA Case Cleared 11/18/2019 ANNA VIDAL
Specific Plan Cleared 12/10/2019 COLLINS ALLAN
Work Adjacent to Public Way Cleared 8/14/2020 ARMEN SARKISIAN
Roof/Waste drainage to street Cleared 8/28/2020 NGOC KIEM

Contact Information

Architect Kil,, Andrew Han; Lic. No.: C31817 13005 MESA VERDE WAY      SYLMAR, CA 91342
Contractor Agm Development Inc; Lic. No.: 968439-B 2181 VENICE BLVD STE 200      LOS ANGELES, CA 90006
Engineer Jones,, Ryan Keith; Lic. No.: GE2852 1253 W MASLINE ST      COVINA, CA 91722
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 1/26/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/9/2021 Conditional Approval DANIEL MC AULIFFE
Piling/Pier/Caisson 3/8/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Steel/Welding 3/23/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 3/24/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 3/25/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 3/30/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/5/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/18/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/1/2021 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/3/2021 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 7/15/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 7/29/2021 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 9/23/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/6/2021 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 11/30/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/1/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/2/2022 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 3/21/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/21/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/21/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval DANIEL MC AULIFFE
Green Building Rough 4/22/2022 Approved DANIEL MC AULIFFE
Verify Sprinkler Sign Off 4/22/2022 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 8/4/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval DAVID BURKHEAD
Wood Frame 4/29/2024 Corrections Issued DAVID BURKHEAD
Pre-Inspection 7/30/2024 Approved DAVID BURKHEAD
Wood Frame 7/30/2024 Pending Review
Deputy Wood Construction 8/12/2024 Conditional Approval MICHAEL ROSENBERG
Wood Frame 8/20/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/29/2024 Partial Approval DAVID BURKHEAD
Wood Frame 9/5/2024 Partial Inspection DAVID BURKHEAD
Wood Frame 10/10/2024 Partial Approval DAVID BURKHEAD
Insulation 10/22/2024 Partial Inspection DAVID BURKHEAD
Wood Frame 10/22/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/28/2024 Partial Approval DAVID BURKHEAD
Insulation 10/28/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 10/28/2024 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 11/4/2024 Approved DAVID BURKHEAD
Drywall Nailing 11/13/2024 Partial Approval DAVID BURKHEAD
Wood Frame 11/13/2024 Partial Approval DAVID BURKHEAD
Wood Frame 11/20/2024 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 12/11/2024 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 12/11/2024 Approved DAVID BURKHEAD
Pre-Inspection 12/16/2024 Approved DAVID BURKHEAD
Insulation 12/19/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 12/19/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 12/31/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 1/17/2025 Not Ready for Inspection EDWIN GREGORYONA
T-Bar Ceiling 1/17/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 1/17/2025 Partial Approval EDWIN GREGORYONA
Insulation 1/22/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 1/30/2025 Partial Approval DAVID BURKHEAD
Insulation 2/7/2025 Partial Approval DAVID BURKHEAD
Drywall Nailing 2/21/2025 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 3/7/2025 Not Ready for Inspection DAVID BURKHEAD
Insulation 3/12/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/12/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/24/2025 Partial Approval DAVID BURKHEAD
Wood Frame 4/4/2025 Partial Approval DAVID BURKHEAD
Insulation 4/17/2025 Partial Approval DAVID BURKHEAD
Drywall Nailing 4/21/2025 Partial Approval DAVID BURKHEAD
Insulation 4/21/2025 Not Ready for Inspection DAVID BURKHEAD
Insulation 4/23/2025 Approved DAVID BURKHEAD
Drywall Nailing 5/7/2025 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/27/2025 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/29/2025 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 6/3/2025 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 8/6/2025 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 8/6/2025 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 8/6/2025 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 8/13/2025 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 8/13/2025 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/29/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Pre-Inspection 8/29/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 8/29/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 9/12/2025 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/17/2025 Approved DAVID BURKHEAD
Masonry Wall/Backfill 11/25/2025 Partial Approval DAVID BURKHEAD
Special/Order Compliance 1/26/2026 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 2/4/2026 Approved RAFAEL ESPINOZA