1363 W COLTON ST 1-47 90026

Certificate Information: 1363 W COLTON ST 1-47 90026

Application / Permit
18010-10000-01729
Plan Check / Job No.
B18LA07855
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(47)DWELLIG UNIT APARTMENT- (5) LEVELS (TYPE IIIA) OVER 1 LEVEL RESIDENTIAL (TYPE IA) OVER 1 LEVEL AT GRADE PARKING GARAGE OVER 1 LEVEL SUBTERRANEAN PARKING GARAGE PER DIR-2018-2653-TOC-SPP.
Permit Issued
Issued on 2/8/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/31/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2018 APPLICANT
Assigned to Plan Check Engineer 5/10/2018 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 5/11/2018 APPLICANT
Green Plans Picked Up 5/11/2018 APPLICANT
Corrections Issued 5/22/2018 ARMEN JIVALAGIAN
Quality Review Completed 5/22/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 6/5/2018 APPLICANT
Applicant returned to address corrections 7/9/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/13/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/20/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/7/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/21/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/5/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/9/2018 SAM CHANG
Applicant returned to address corrections 12/18/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/9/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/23/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/29/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/31/2019 ARMEN JIVALAGIAN
Plan Check Approved 2/8/2019 ARMEN JIVALAGIAN
Issued 2/8/2019 LADBS
TCO Issued (Expire Date: 08-10-2021) 2/11/2021 ERNESTO CORRAL
CofO in Progress 3/31/2021 RAFAEL ESPINOZA
Permit Finaled 3/31/2021 DAVID TSAU
CofO Issued 3/31/2021 DAVID TSAU
Permit Finaled 3/31/2021 DAVID TSAU

Permit Application Clearance Information

Abandoned oil well Cleared 6/20/2018 GEORGE SUCHAND
Abandoned oil well approval Cleared 6/20/2018 GEORGE SUCHAND
Hydrant and Access approval Cleared 6/20/2018 GEORGE SUCHAND
Green Code Cleared 7/17/2018 DONALD CRICHLOW
DAS Clearance Cleared 7/20/2018 SHINE LIN
Address approval Cleared 7/24/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 7/24/2018 NAZILA NOORIFAR
Highway dedication Cleared 7/24/2018 NAZILA NOORIFAR
Permit Cleared 7/24/2018 NAZILA NOORIFAR
Sewer availability Cleared 7/24/2018 NAZILA NOORIFAR
Internal circulation Cleared 7/27/2018 TAIMOUR TANAVOLI
Specific Plan Cleared 7/27/2018 TAIMOUR TANAVOLI
Fire Marshall Fire Life Safety Cleared 8/28/2018 VIDAL GARCIA
Low Impact Development Cleared 11/6/2018 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 11/9/2018 NAZILA NOORIFAR
Work Adjacent to Public Way Cleared 11/29/2018 BOK GOH
Building over 3-story or 36-ft Cleared 1/9/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/9/2019 CALOSHA APPROVED
GPI Written Notices Cleared 1/9/2019 ARMEN JIVALAGIAN
Grading Pre-Inspection Cleared 1/9/2019 ARMEN JIVALAGIAN
Miscellaneous Cleared 1/9/2019 WILLIAM JOHNS
Trees in Parkway Cleared 1/14/2019 ARMEN JIVALAGIAN
Construction near power lines Cleared 1/23/2019 WALTER RAMIREZ
Construction within easement Cleared 1/23/2019 WALTER RAMIREZ
DCP conditions approval Cleared 1/23/2019 KENNETH LE
Density Bonus 12.22.A.31 Cleared 1/23/2019 KENNETH LE
Frnt yard landscape/Water mgmt Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Opn space landscape/Water mgmt Cleared 1/29/2019 BLAYNE SUTTON-WILLS
Specific Plan Cleared 1/29/2019 BLAYNE SUTTON-WILLS

Contact Information

Architect Empakeris, Donatas Eduard; Lic. No.: C13779 1535 6TH STREET SUITE 101   DE ARCHITECTS    SANTA MONICA, CA 90401
Contractor Essey Construction Company Inc; Lic. No.: 566045-B 10801 NATIONAL BOULEVARD #345      LOS ANGELES, CA 90064
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Mazzei,, Anthony Paul; Lic. No.: GE2823 23320 BASSET STREET      WEST HILLS, CA 91307
Engineer Young,, Don Yuk-Man; Lic. No.: C35713 149 PASADENA AVE STE B      SOUTH PASADENA, CA 91030

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 5/20/2019 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 5/21/2019 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 5/31/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Barrier 6/5/2019 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 6/5/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 6/26/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 6/26/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 6/26/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Subgrade 6/26/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 6/27/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 6/28/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/2/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 7/2/2019 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 7/2/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 7/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/9/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/9/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 7/9/2019 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 7/9/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 7/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/10/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 7/10/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/11/2019 Conditional Approval LESLIE TRUJILLO
Structural Steel Frame 7/15/2019 Partial Approval LESLIE TRUJILLO
Structural Steel Frame 7/16/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 7/18/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Rough 7/18/2019 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 7/18/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/18/2019 Partial Inspection LESLIE TRUJILLO
Green Building Rough 7/23/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 7/23/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 7/23/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/23/2019 Partial Inspection LESLIE TRUJILLO
Structural Steel Frame 7/25/2019 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 7/26/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 7/29/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 7/29/2019 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/29/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 8/2/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Rough 8/2/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/2/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/16/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/20/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/20/2019 Approved LESLIE TRUJILLO
METHANE-Subgrade 8/20/2019 Partial Approval LESLIE TRUJILLO
METHANE-Rough 8/27/2019 Partial Inspection LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 9/5/2019 Partial Approval LESLIE TRUJILLO
METHANE-Rough 9/5/2019 Approved LESLIE TRUJILLO
Green Building Rough 9/12/2019 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 9/12/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 9/12/2019 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Masonry Frame 9/16/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 10/2/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/2/2019 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/2/2019 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/4/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/4/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/4/2019 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/16/2019 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 10/16/2019 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 10/16/2019 Not Ready for Inspection DANIEL MC AULIFFE
Structural Steel Frame 10/17/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/22/2019 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 10/22/2019 Partial Inspection ERNESTO CORRAL
Green Building Rough 11/13/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 11/13/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 11/13/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/13/2019 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/3/2020 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/8/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 1/14/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/14/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 1/14/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/27/2020 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/30/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 2/3/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Masonry Frame 2/3/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/3/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 3/2/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 3/2/2020 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 3/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/5/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/6/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval LESLIE TRUJILLO
Wood Frame 3/11/2020 Not Ready for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 3/19/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 3/19/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 3/19/2020 Conditional Approval LESLIE TRUJILLO
Wall Anchors 3/19/2020 Partial Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/24/2020 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 3/31/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 3/31/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 3/31/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 4/14/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/14/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 4/14/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 4/21/2020 Conditional Approval LESLIE TRUJILLO
Insulation 4/21/2020 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/21/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 4/21/2020 Conditional Approval LESLIE TRUJILLO
Wood Frame 4/21/2020 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 5/5/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 5/5/2020 Approved RAFAEL ESPINOZA
Wood Frame 5/5/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/20/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/21/2020 Partial Approval RAFAEL ESPINOZA
Insulation 5/27/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/27/2020 Partial Approval RAFAEL ESPINOZA
Insulation 5/29/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/29/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/3/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 6/3/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/5/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/9/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/9/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/10/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/10/2020 Partial Inspection RAFAEL ESPINOZA
Insulation 6/15/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/17/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/19/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/7/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/9/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/10/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/10/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/17/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/17/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/17/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/22/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/22/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/22/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/27/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 7/27/2020 Approved RAFAEL ESPINOZA
Drywall Nailing 7/28/2020 Partial Inspection RAFAEL ESPINOZA
Insulation 7/28/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/28/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/30/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/30/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/4/2020 Partial Approval RAFAEL ESPINOZA
Insulation 8/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 8/4/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/6/2020 Partial Approval KATY RAMIREZ
Insulation 8/6/2020 Partial Approval KATY RAMIREZ
Insulation 8/12/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/12/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/18/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/21/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/25/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/25/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/1/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval RAFAEL ESPINOZA
Insulation 9/4/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/9/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/16/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 9/16/2020 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 9/18/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/24/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 10/1/2020 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 10/13/2020 Partial Approval RAFAEL ESPINOZA
Insulation 10/13/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/21/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/27/2020 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 10/28/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 10/29/2020 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 11/12/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/12/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 11/23/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 12/2/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 12/17/2020 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 12/29/2020 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 1/14/2021 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 1/19/2021 Partial Inspection RAFAEL ESPINOZA
Structural Steel Frame 1/20/2021 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 1/21/2021 Partial Approval EDWIN GREGORYONA
Pre-Inspection 1/29/2021 Partial Inspection RAFAEL ESPINOZA
Green Building Rough 2/12/2021 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 2/12/2021 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/12/2021 Approved RAFAEL ESPINOZA
Final 3/30/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/30/2021 Approved RAFAEL ESPINOZA
Green Building Final 3/30/2021 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 3/30/2021 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 3/30/2021 Approved RAFAEL ESPINOZA