2221 S WESTERN AVE 90018

Certificate Information: 2221 S WESTERN AVE 90018

Application / Permit
18010-10000-01617
Plan Check / Job No.
B18LA07235
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
PROPOSED 5 STORY, MIXED USE 48 UNIT APARTMENT, RETAIL AND BASEMENT GARAGE. STAIRS AND RAILS ARE DEFERRED
Permit Issued
Issued on 2/3/2021
Issuing Office
Metro
Current Status
CofO Issued on 6/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2018 APPLICANT
Assigned to Plan Check Engineer 7/12/2018 JOHN VASQUEZ
Corrections Issued 8/1/2018 JOHN VASQUEZ
Quality Review Completed 8/6/2018 CHARLES CHANG
Building Plans Picked Up 8/7/2018 APPLICANT
Applicant returned to address corrections 2/27/2019 JOHN VASQUEZ
Applicant returned to address corrections 3/11/2019 JOHN VASQUEZ
Applicant returned to address corrections 3/26/2019 JOHN VASQUEZ
Applicant returned to address corrections 4/5/2019 JOHN VASQUEZ
Applicant returned to address corrections 5/1/2019 JOHN VASQUEZ
Applicant returned to address corrections 6/27/2019 JOHN VASQUEZ
Applicant returned to address corrections 12/3/2019 JOHN VASQUEZ
Applicant returned to address corrections 12/9/2019 JOHN VASQUEZ
Applicant returned to address corrections 12/12/2019 JOHN VASQUEZ
Applicant returned to address corrections 2/12/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/1/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/15/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/21/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/29/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/11/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/29/2020 JOHN VASQUEZ
Plan Check Approved 6/26/2020 JOHN VASQUEZ
Issued 2/3/2021 APPLICANT
CofO in Progress 6/11/2024 JAMES POWERS
Permit Finaled 6/13/2024 ERNESTO CORRAL
CofO Issued 6/13/2024 ERNESTO CORRAL
Permit Finaled 6/13/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/24/2018 ADRIAN SANCHEZ
Tract Map conditions Cleared 8/24/2018 DANALYNN DOMINGUEZ
Site Plan review Cleared 10/3/2018 NORA DRESSER
Miscellaneous Cleared 11/1/2018 STEVE GARCIA
Trees in Parkway Cleared 2/15/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/21/2019 ELAINE LEI
Highway dedication Cleared 3/11/2019 KARAN PATEL
Driveway location Cleared 5/2/2019 WESTON PRINGLE
Internal circulation Cleared 5/2/2019 WESTON PRINGLE
DAS Clearance Cleared 5/7/2019 WAI LAU
Permit Cleared 5/21/2019 ELAINE LEI
Abandoned oil well Cleared 6/3/2019 ROBERT DUFF
Abandoned oil well approval Cleared 6/3/2019 ROBERT DUFF
Hydrant and Access approval Cleared 6/3/2019 ROBERT DUFF
Sewer availability Cleared 6/3/2019 KARAN PATEL
Green Code Cleared 6/11/2019 DONALD CRICHLOW
Low Impact Development Cleared 6/11/2019 JOHN VASQUEZ
Stormwater Pollution Mitigatn Cleared 6/11/2019 RYAN HUDSON
Opn space landscape/Water mgmt Cleared 10/11/2019 SOPHIE GABEL-SCHEINBAU
Bicycle Parking Cleared 10/18/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 12/4/2019 THOMAS LANG
Community Plan Implem. Overlay Cleared 12/9/2019 SOPHIE GABEL-SCHEINBAU
Community Plan Implem. Overlay Cleared 12/9/2019 THOMAS LANG
Community Plan Implem. Overlay Cleared 12/11/2019 EDUARDO HERMOSO
Community Plan Implem. Overlay Cleared 12/17/2019 WALTER RAMIREZ
Community Plan Implem. Overlay Cleared 1/6/2020 JOHN KIM
Prkng lot landscape/Water mgmt Cleared 2/6/2020 JASON CHAN
Building over 3-story or 36-ft Cleared 2/7/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 2/7/2020 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 4/17/2020 TERRY PHAN
Fire Marshall Fire Life Safety Cleared 5/27/2020 WILLIAM JOHNS

Contact Information

Architect Denari,, Neil Martin; Lic. No.: C29351 NEIL M. DENARI ARCHITECTS   4335 W. ADAMS BLVD.    LOS ANGELES, CA 90018
Contractor Owner-Builder       ,
Engineer Conaway,, Johnny Ray; Lic. No.: C19689 PO BOX 155      OAK VIEW, CA 93022
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Gavazza,, Jeffrey Bryan; Lic. No.: C59894 472 35TH ST      MANHATTAN BEACH, CA 90266

Inspector Information

JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2021 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/12/2021 Not Ready for Inspection DAVID TSAU
Excavation/Setback/Form/Re-Bar 7/16/2021 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 7/16/2021 Approved RAFAEL ESPINOZA
Deputy Methane Barrier 7/22/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 7/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/27/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 7/29/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 7/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/3/2021 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 8/3/2021 Conditional Approval DAVID TSAU
METHANE-Barrier 8/3/2021 Partial Approval DAVID TSAU
METHANE-Subgrade 8/3/2021 Partial Approval DAVID TSAU
Deputy Methane Barrier 8/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/4/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/10/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/11/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/11/2021 Partial Approval JAMES POWERS
METHANE-Barrier 8/11/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 8/11/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/12/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 8/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/18/2021 Partial Approval JAMES POWERS
Green Building Rough 8/18/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 8/18/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/18/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/18/2021 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 8/19/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/20/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/23/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/24/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/25/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/26/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/27/2021 Partial Approval JAMES POWERS
Green Building Rough 8/27/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 8/27/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/27/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/27/2021 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 8/30/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/31/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 8/31/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/31/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2021 Partial Approval JAMES POWERS
Special/Order Compliance 9/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/2/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/3/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/7/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/7/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 9/22/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/12/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/12/2021 Partial Approval JAMES POWERS
METHANE-Barrier 10/12/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 10/12/2021 Approved JAMES POWERS
Deputy Reinf. Concrete 10/14/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 10/22/2021 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 11/19/2021 Partial Inspection TED RIES
Green Building Rough 11/19/2021 Not Ready for Inspection TED RIES
METHANE-Barrier 11/19/2021 Not Ready for Inspection TED RIES
METHANE-Rough 11/19/2021 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 11/19/2021 Partial Inspection TED RIES
Verify Sprinkler Sign Off 11/19/2021 Not Ready for Inspection TED RIES
Footing/Foundation/Slab 11/22/2021 Partial Approval TED RIES
Deputy Reinf. Concrete 11/24/2021 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/29/2021 Partial Approval JAMES POWERS
Green Building Rough 11/29/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 11/29/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 11/29/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/29/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 12/2/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Approval JAMES POWERS
Wall Anchors 12/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 12/6/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/6/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 12/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/28/2021 Partial Approval JAMES POWERS
Green Building Rough 1/10/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 1/10/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/10/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/10/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 1/11/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/11/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/12/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/13/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/19/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/20/2022 Partial Approval JAMES POWERS
Insulation 1/20/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 1/20/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/21/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 1/24/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/23/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval JAMES POWERS
Deputy Other (see comments) 3/3/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/14/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval JAMES POWERS
Insulation 3/16/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/5/2022 Partial Approval JAMES POWERS
Green Building Rough 4/5/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 4/5/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/5/2022 Not Ready for Inspection JAMES POWERS
Insulation 4/7/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Approved DARRYL ARNOLD
Deputy Steel/Welding 4/19/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval NICK DANERI
Deputy Steel/Welding 4/20/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 4/22/2022 Conditional Approval DAVID BURKHEAD
Wood Frame 4/22/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 4/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/26/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 4/26/2022 Not Ready for Inspection JAMES POWERS
Insulation 4/26/2022 Partial Approval JAMES POWERS
METHANE-Rough 4/26/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/26/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 4/26/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 4/27/2022 Partial Approval JAMES POWERS
Special/Order Compliance 4/27/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 4/28/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/29/2022 Partial Approval JAMES POWERS
Insulation 5/2/2022 Partial Approval JAMES POWERS
Green Building Rough 5/18/2022 Approved JAMES POWERS
Insulation 5/18/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/18/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/18/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 5/18/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/19/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval JAMES POWERS
Insulation 6/3/2022 Not Ready for Inspection JAMES POWERS
Insulation 6/8/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/8/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/9/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval JAMES POWERS
Wood Frame 6/10/2022 Partial Approval JAMES POWERS
Insulation 6/15/2022 Partial Approval JAMES POWERS
Insulation 6/17/2022 Partial Approval JAMES POWERS
Wood Frame 6/17/2022 Partial Approval JAMES POWERS
Insulation 6/24/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/28/2022 Partial Approval JAMES POWERS
Pre-Inspection 6/28/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 6/28/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/1/2022 Partial Approval JAMES POWERS
Insulation 7/1/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/1/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/6/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/11/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/15/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/21/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/21/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/22/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/27/2022 Conditional Approval WINSTON DUNNING
Special/Order Compliance 8/11/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Partial Approval JAMES POWERS
Insulation 8/29/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/29/2022 Partial Approval JAMES POWERS
Drywall Nailing 9/2/2022 Partial Approval JAMES POWERS
Special/Order Compliance 9/19/2022 Partial Approval JAMES POWERS
Pre-Inspection 10/17/2022 Approved DAVID BURKHEAD
Insulation 10/25/2022 Partial Approval JAMES POWERS
Drywall Nailing 10/31/2022 Approved JAMES POWERS
Footing/Foundation/Slab 10/31/2022 Approved JAMES POWERS
METHANE-Barrier 10/31/2022 Approved JAMES POWERS
Special/Order Compliance 11/10/2022 Partial Approval JAMES POWERS
Deputy Fireproofing 1/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 1/25/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 2/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 3/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 3/13/2023 Conditional Approval MICHAEL ROSENBERG
Special/Order Compliance 3/16/2023 Partial Approval JAMES POWERS
Special/Order Compliance 4/2/2024 Not Ready for Inspection JAMES POWERS
Final 4/4/2024 Not Ready for Inspection JAMES POWERS
Pre-Inspection 4/4/2024 Approved JAMES POWERS
Final 4/12/2024 OK for TCO JAMES POWERS
Green Building Final 4/12/2024 Approved JAMES POWERS
METHANE-Final 4/12/2024 Approved JAMES POWERS
METHANE-Rough 4/12/2024 Approved JAMES POWERS
Reinforced Concrete Frame 4/12/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved JAMES POWERS
SUSMP-Std. Urban Storm Water 4/12/2024 Approved JAMES POWERS
Smoke Detectors 4/12/2024 Partial Approval JAMES POWERS
Special/Order Compliance 4/12/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 4/12/2024 Approved JAMES POWERS
Wood Frame 4/12/2024 Approved JAMES POWERS
Final 4/25/2024 OK for TCO JAMES POWERS
Pre-Inspection 4/25/2024 Approved JAMES POWERS
Smoke Detectors 4/25/2024 Approved JAMES POWERS
Special/Order Compliance 4/25/2024 Approved JAMES POWERS
Final 6/11/2024 OK to Issue CofO JAMES POWERS