1804 N KEMPER ST 90065

Certificate Information: 1804 N KEMPER ST 90065

Application / Permit
18010-10000-01576
Plan Check / Job No.
B18LA07087
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2- STORY SINGLE FAMILY DWELLING WITH NFPA 13-D FIRE SPRINKLER SYSTEM THROUGOUT.
Permit Issued
Issued on 12/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2018 APPLICANT
Assigned to Plan Check Engineer 5/17/2018 KESETE HAREGOT
Corrections Issued 5/19/2018 JEFFREY MACHADO
Quality Review Completed 5/23/2018 DAVID CHANG
Applicant returned to address corrections 12/4/2019 KESETE HAREGOT
Plan Check Approved 12/18/2019 KESETE HAREGOT
Issued 12/20/2019 LADBS
Green Plans Picked Up 8/19/2020 APPLICANT
CofO in Progress 11/29/2021 OSVALDO PARAMO
CofO in Progress 11/29/2021 OSVALDO PARAMO
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/17/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 4/17/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/17/2019 JEANETTE VONG
Hydrant and Access approval Cleared 4/17/2019 GEORGE SUCHAND
Sewer availability Cleared 4/17/2019 JEANETTE VONG
Green Code Cleared 5/8/2019 SARAH ABOULHOSN
Low Impact Development Cleared 7/8/2019 ORVAL HERNANDEZ-MARCI
Permit Cleared 7/8/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 7/19/2019 ELENA LOPEZ
Landscape for retaining wall Cleared 12/3/2019 ANNA VAN
Specific Plan Cleared 12/3/2019 ANNA VAN
ZA Case Cleared 12/3/2019 ANNA VAN
BHO/Hillside ordinance Cleared 12/4/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 12/17/2019 NGOC KIEM
Miscellaneous Cleared 12/17/2019 NGOC KIEM
GPI Written Notices Cleared 12/18/2019 JEFFREY MACHADO
Grading Pre-Inspection Cleared 12/18/2019 JEFFREY MACHADO
Hold Cleared 1/27/2020 CYNTHIA RYAN

Contact Information

Architect , ; Lic. No.: C35798       ,
Contractor T N L Renovation Inc; Lic. No.: 1052062-B 6949 RESEDA BLVD STE #225      RESEDA, CA 91335
Engineer Hanbali, Amjad Moh'D; Lic. No.: C42213 514 W COMMERCE AVE STE C      PALMDALE, CA 93551
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVE      VAN NUYS, CA 91406
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403
Geologist Ruberti,, Rudolph F; Lic. No.: EG1708 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2020 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/13/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/14/2020 No Access for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/16/2020 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 4/21/2020 Partial Inspection OSVALDO PARAMO
Piling/Pier/Caisson 4/22/2020 Not Ready for Inspection OSVALDO PARAMO
Piling/Pier/Caisson 4/27/2020 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 5/1/2020 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 6/2/2020 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 6/5/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/15/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/22/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/9/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/9/2020 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 7/10/2020 Partial Approval OSVALDO PARAMO
Wood Frame 7/10/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/7/2020 Approved OSVALDO PARAMO
HVAC-Rough 10/7/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 10/16/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 10/16/2020 Corrections Issued OSVALDO PARAMO
Masonry Wall/Backfill 10/21/2020 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 11/2/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 11/2/2020 Approved OSVALDO PARAMO
Deputy Wood Construction 11/4/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 11/10/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 11/10/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Approved OSVALDO PARAMO
Green Building Rough 11/10/2020 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 11/10/2020 Not Ready for Inspection OSVALDO PARAMO
Insulation 11/13/2020 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 12/1/2020 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 1/21/2021 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 1/25/2021 Approved OSVALDO PARAMO
Green Building Rough 1/25/2021 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 1/25/2021 Approved OSVALDO PARAMO
Insulation 2/3/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/12/2021 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 2/16/2021 Approved OSVALDO PARAMO
Shower Pan 2/16/2021 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 2/18/2021 Not Ready for Inspection OSVALDO PARAMO
Shower Pan 3/8/2021 Not Ready for Inspection OSVALDO PARAMO
Shower Pan 3/11/2021 Approved OSVALDO PARAMO
Sewer 5/6/2021 Approved OSVALDO PARAMO
PLUMBING-Final 5/10/2021 Not Ready for Inspection OSVALDO PARAMO
HVAC-Final 6/7/2021 Corrections Issued OSVALDO PARAMO
HVAC-Final 6/8/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 6/16/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 6/28/2021 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 7/1/2021 Corrections Issued DAVID FEILER
HVAC-Final 7/6/2021 Partial Approval OSVALDO PARAMO
Gas Test 7/7/2021 Approved OSVALDO PARAMO
PLUMBING-Final 7/7/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 7/9/2021 Not Ready for Inspection OSVALDO PARAMO
HVAC-Final 7/12/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 7/19/2021 Approved OSVALDO PARAMO
Service/Power Release 8/10/2021 Not Ready for Inspection OSVALDO PARAMO
Drywall Nailing 8/18/2021 Approved OSVALDO PARAMO
Green Building Final 8/18/2021 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 8/18/2021 Not Ready for Inspection OSVALDO PARAMO
Final 8/19/2021 Partial Inspection OSVALDO PARAMO
Final 8/24/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 8/24/2021 Not Ready for Inspection OSVALDO PARAMO
Service/Power Release 8/24/2021 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 8/24/2021 Not Ready for Inspection OSVALDO PARAMO
Final 11/9/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 11/9/2021 Approved OSVALDO PARAMO
Service/Power Release 11/9/2021 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 11/9/2021 Approved OSVALDO PARAMO
Service/Power Release 11/17/2021 Approved OSVALDO PARAMO
Final 11/19/2021 OK to Issue CofO OSVALDO PARAMO