684 S NEW HAMPSHIRE AVE 1-170 90005

Certificate Information: 684 S NEW HAMPSHIRE AVE 1-170 90005

Application / Permit
18010-10000-01517
Plan Check / Job No.
B18LA06825
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW CONSTRUCTION OF A 5-STORY IN TYPE III-A CONSTRUCTION OVER TWO STORY TYPE I-A CONSTRUCTION MIXED USE OF RESIDENTIAL AND RETAIL (LOW-RISE BUILDING) . 170 UNIT APARTMENTS WITH 3 LEVELS OF SUBTERRANEAN PARKING AND RETAIL ON THE GROUND FLOOR.
Permit Issued
Issued on 8/9/2023
Issuing Office
Metro
Current Status
Issued on 8/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/13/2018 APPLICANT
Assigned to Plan Check Engineer 7/5/2018 JOHN VASQUEZ
Corrections Issued 7/10/2018 JOHN VASQUEZ
Quality Review Completed 7/11/2018 CHARLES CHANG
Building Plans Picked Up 7/12/2018 APPLICANT
Applicant returned to address corrections 7/22/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/23/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/28/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/29/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/7/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/27/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/28/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/10/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/11/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/5/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 7/13/2023 FARSHAD ALIMOHAMADI
Issued 8/9/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/20/2019 THOMAS LANG
Address approval Cleared 10/4/2019 EMIL KYUPELYAN
Permit Cleared 10/4/2019 EMIL KYUPELYAN
Highway dedication Cleared 7/16/2020 CELINA MORENO
Driveway location Cleared 6/22/2021 TAIMOUR TANAVOLI
Internal circulation Cleared 6/22/2021 TAIMOUR TANAVOLI
Encroachment in public way Cleared 7/15/2021 JEREMY CHOK
Green Code Cleared 2/1/2022 AARON COSTA
Work Adjacent to Public Way Cleared 9/16/2022 JOSE RODRIGUEZ
Building over 3-story or 36-ft Cleared 9/19/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/19/2022 CALOSHA APPROVED
Hydrant and Access approval Cleared 10/6/2022 MATTHEW CRAIG
Sewer availability Cleared 2/3/2023 JEANETTE VONG
Methane Ordinance Cleared 3/6/2023 WILLIAM JOHNS
Fire Marshall Fire Life Safety Cleared 3/7/2023 WILLIAM JOHNS
Low Impact Development Cleared 4/21/2023 JORGE MEJIA LEMUS
Stormwater Pollution Mitigatn Cleared 4/21/2023 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/10/2023 MATIAS FARFAN
DAS Clearance Cleared 5/28/2023 JOHN VASQUEZ
DCP conditions approval Cleared 6/7/2023 LOUIE MILLER
Density Bonus 12.22.A.25 Cleared 6/7/2023 LOUIE MILLER
Frnt yard landscape/Water mgmt Cleared 6/29/2023 LOUIS ORTEGA
Opn space landscape/Water mgmt Cleared 6/29/2023 LOUIS ORTEGA
Project located in CRA area Cleared 6/29/2023 LOUIS ORTEGA
Site Plan review Cleared 6/29/2023 LOUIS ORTEGA
Tract Map conditions Cleared 6/29/2023 LOUIS ORTEGA
ZA Case Cleared 6/29/2023 LOUIS ORTEGA

Contact Information

Architect Pak, Christopher C; Lic. No.: C25621 8157 ZITOLA TERRACE      PLAYA DEL REY, CA 90293
Contractor Forza Construction Inc; Lic. No.: 914162-B 25243 AVENUE TIBBITS      VALENCIA, CA 91355
Engineer Ho,, Patrick; Lic. No.: C72847 PO BOX 143      WALNUT, CA 91788
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Insulation 5/27/2026   

Inspection Request History

Deputy Reinf. Concrete 10/5/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/6/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/10/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 11/13/2023 Not Ready for Inspection NICK DANERI
METHANE-Barrier 11/13/2023 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 11/13/2023 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 12/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/15/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 12/15/2023 Partial Approval NICK DANERI
METHANE-Barrier 12/15/2023 Partial Inspection NICK DANERI
METHANE-Subgrade 12/15/2023 Partial Inspection NICK DANERI
Deputy Methane Barrier 12/28/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 12/28/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 12/28/2023 Partial Approval NICK DANERI
Green Building Rough 12/28/2023 Not Ready for Inspection NICK DANERI
METHANE-Barrier 12/28/2023 Not Ready for Inspection NICK DANERI
METHANE-Rough 12/28/2023 Partial Inspection NICK DANERI
METHANE-Subgrade 12/28/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 12/28/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/28/2023 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 1/5/2024 Conditional Approval NICK DANERI
Deputy Methane Barrier 1/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 1/8/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Methane Barrier 1/9/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 1/10/2024 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 1/11/2024 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 3/14/2024 Partial Inspection NICK DANERI
METHANE-Barrier 3/14/2024 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 3/14/2024 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 4/24/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/25/2024 Not Ready for Inspection NICK DANERI
METHANE-Barrier 4/25/2024 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 4/25/2024 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 4/26/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/26/2024 Conditional Approval NICK DANERI
Green Building Rough 4/26/2024 Not Ready for Inspection NICK DANERI
METHANE-Rough 4/26/2024 Partial Inspection NICK DANERI
Reinforced Concrete Frame 4/26/2024 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/26/2024 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 5/13/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/13/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/13/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/13/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 5/13/2024 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 5/13/2024 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 5/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/16/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/16/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/16/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 5/16/2024 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 5/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 5/21/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/21/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/21/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/21/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 5/21/2024 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 5/21/2024 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 5/31/2024 Conditional Approval JEFFREY FULTON
METHANE-Barrier 5/31/2024 Not Ready for Inspection JEFFREY FULTON
METHANE-Subgrade 5/31/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 6/1/2024 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 6/1/2024 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/7/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/7/2024 Partial Approval NICK DANERI
Footing/Foundation/Slab 6/7/2024 Partial Approval NICK DANERI
METHANE-Barrier 6/7/2024 Approved NICK DANERI
METHANE-Subgrade 6/7/2024 Partial Approval NICK DANERI
Deputy Methane Barrier 6/18/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/18/2024 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 6/18/2024 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 6/18/2024 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 6/19/2024 Partial Approval LARRY ARNICK
Deputy Methane Barrier 6/26/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/26/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/26/2024 Not Ready for Inspection NICK DANERI
Piling/Pier/Caisson 6/26/2024 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/1/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 7/1/2024 Partial Approval NICK DANERI
Deputy Shotcrete 7/2/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 7/2/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 7/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/15/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/15/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Methane Barrier 7/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/16/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/16/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/22/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/23/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/29/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/29/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/29/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/31/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 7/31/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/2/2024 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/6/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/8/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/8/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/12/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/12/2024 Partial Approval NICK DANERI
Footing/Foundation/Slab 8/12/2024 Partial Approval NICK DANERI
METHANE-Subgrade 8/12/2024 Approved NICK DANERI
Deputy Shotcrete 8/14/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/14/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/15/2024 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/15/2024 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 8/15/2024 Partial Approval RAFAEL ESPINOZA
Deputy Methane Barrier 8/20/2024 Conditional Approval NICK DANERI
Deputy Shotcrete 8/20/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/20/2024 Partial Approval NICK DANERI
Deputy Methane Barrier 8/21/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/21/2024 Conditional Approval NICK DANERI
Deputy Shotcrete 8/21/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/21/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/26/2024 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 8/27/2024 Conditional Approval NICK DANERI
Deputy Shotcrete 8/27/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/27/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/28/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/28/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/28/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/17/2024 Partial Approval NICK DANERI
Reinforced Concrete Frame 9/19/2024 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 9/24/2024 Not Ready for Inspection NICK DANERI
Piling/Pier/Caisson 9/24/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/30/2024 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 9/30/2024 Partial Approval RAFAEL ESPINOZA
Deputy Methane Barrier 10/1/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/1/2024 Conditional Approval NICK DANERI
Deputy Shotcrete 10/1/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/1/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/3/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/8/2024 Partial Approval NICK DANERI
Deputy Shotcrete 10/11/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/11/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/5/2024 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/5/2024 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/6/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/8/2024 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 11/8/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/15/2024 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/21/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/25/2024 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 11/25/2024 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Concrete 11/26/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/26/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 11/27/2024 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 11/27/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/27/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/3/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/3/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/4/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/4/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/5/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/18/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/18/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/19/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/20/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/20/2024 Partial Approval NICK DANERI
Footing/Foundation/Slab 12/20/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/23/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/23/2024 Partial Inspection NICK DANERI
Footing/Foundation/Slab 12/23/2024 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 1/15/2025 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/15/2025 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 1/16/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/16/2025 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 1/22/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/22/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/22/2025 Partial Inspection NICK DANERI
Deputy Shotcrete 1/23/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/23/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/20/2025 Conditional Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/20/2025 Conditional Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/21/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/21/2025 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 2/24/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/24/2025 Partial Inspection NICK DANERI
Footing/Foundation/Slab 2/24/2025 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 3/13/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/13/2025 Partial Approval NICK DANERI
Wood Frame 3/13/2025 Partial Inspection NICK DANERI
Drywall Nailing 3/18/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 3/18/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 3/19/2025 Conditional Approval NICK DANERI
Deputy Wood Construction 3/19/2025 Conditional Approval NICK DANERI
Drywall Nailing 3/19/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 3/19/2025 Partial Approval NICK DANERI
Drywall Nailing 3/20/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 3/20/2025 Partial Approval NICK DANERI
Deputy Methane Barrier 3/26/2025 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/26/2025 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Partial Approval NICK DANERI
Masonry Wall/Backfill 3/26/2025 Partial Approval NICK DANERI
Deputy Methane Barrier 4/2/2025 Conditional Approval NICK DANERI
Deputy Shotcrete 4/2/2025 Conditional Approval NICK DANERI
Deputy Wood Construction 4/2/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/2/2025 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 4/3/2025 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 4/8/2025 Conditional Approval NICK DANERI
Deputy Wood Construction 4/8/2025 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Not Ready for Inspection NICK DANERI
Deputy Drilled-In Anchors 4/9/2025 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/9/2025 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Partial Approval NICK DANERI
Masonry Wall/Backfill 4/11/2025 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/17/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/18/2025 Not Ready for Inspection EDWIN GREGORYONA
Deputy Methane Barrier 4/22/2025 Conditional Approval NICK DANERI
Deputy Shotcrete 4/22/2025 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/22/2025 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/28/2025 Partial Approval NICK DANERI
Drywall Nailing 5/2/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/2/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/6/2025 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 5/15/2025 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 5/16/2025 Partial Approval NICK DANERI
Deputy Methane Barrier 5/19/2025 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/19/2025 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 5/28/2025 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Partial Approval NICK DANERI
Masonry Wall/Backfill 6/2/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 6/3/2025 Conditional Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 6/4/2025 Conditional Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 6/6/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 6/16/2025 Conditional Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 6/18/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 6/20/2025 Conditional Approval JOEY BUCHANAN
Drywall Nailing 6/24/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 7/1/2025 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/2/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Partial Approval JOEY BUCHANAN
Insulation 7/9/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 7/18/2025 Conditional Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Partial Approval JOEY BUCHANAN
Insulation 7/23/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 7/24/2025 Partial Approval JOEY BUCHANAN
Insulation 7/24/2025 Partial Approval JOEY BUCHANAN
Insulation 8/1/2025 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 8/11/2025 Conditional Approval JOEY BUCHANAN
Drywall Nailing 8/11/2025 Not Ready for Inspection JOEY BUCHANAN
Light Gage Steel Frame 8/11/2025 Partial Approval JOEY BUCHANAN
Insulation 8/18/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 8/28/2025 Partial Approval CHRISTOPHER BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 9/3/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/8/2025 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 9/8/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 9/10/2025 Partial Approval JOEY BUCHANAN
Insulation 9/10/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval JOEY BUCHANAN
Wood Frame 9/11/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval JOEY BUCHANAN
Wood Frame 9/12/2025 Conditional Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 9/16/2025 Corrections Issued JOEY BUCHANAN
Drywall Nailing 9/18/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2025 Partial Approval JOEY BUCHANAN
Wood Frame 9/19/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Partial Approval JOEY BUCHANAN
Wood Frame 9/23/2025 Partial Approval JOEY BUCHANAN
Insulation 9/24/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval JOEY BUCHANAN
Insulation 9/25/2025 Partial Approval JOEY BUCHANAN
Insulation 10/2/2025 Partial Approval JOEY BUCHANAN
Insulation 10/6/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 10/9/2025 Partial Approval LARRY ARNICK
Insulation 10/9/2025 Partial Approval LARRY ARNICK
Wood Frame 10/9/2025 Partial Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Not Ready for Inspection JOEY BUCHANAN
Insulation 10/17/2025 Partial Approval JOEY BUCHANAN
Insulation 10/23/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 11/4/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 11/17/2025 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval JOEY BUCHANAN
Insulation 12/2/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 12/9/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 1/13/2026 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 1/21/2026 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 1/27/2026 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 1/27/2026 Partial Approval LARRY ARNICK
Insulation 2/3/2026 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 2/13/2026 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 3/13/2026 Partial Approval JOEY BUCHANAN
Insulation 5/1/2026 Partial Approval JOEY BUCHANAN
Insulation 5/5/2026 Partial Approval JOEY BUCHANAN
Insulation 5/7/2026 Partial Approval JOEY BUCHANAN
Drywall Nailing 5/14/2026 Partial Approval MARTIN TAVITIAN
Insulation 5/22/2026 Partial Approval JOEY BUCHANAN