9592 W SHIRLEY LANE 90210

Certificate Information: 9592 W SHIRLEY LANE 90210

Application / Permit
18010-10000-01497
Plan Check / Job No.
B18LA06669
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
HILLSIDE NEW 2-STORY SINGLE FAMILY DWELLING ABOVE BASEMENT WITH ATTACHED GARAGE
Permit Issued
Issued on 3/19/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2018 APPLICANT
Assigned to Plan Check Engineer 4/26/2018 YOUNG KIM
Green Plans Picked Up 4/27/2018 APPLICANT
Corrections Issued 5/2/2018 YOUNG KIM
Quality Review Completed 5/2/2018 DAVID CHANG
Building Plans Picked Up 6/7/2018 APPLICANT
Applicant returned to address corrections 12/11/2018 YOUNG KIM
Applicant returned to address corrections 1/14/2019 YOUNG KIM
Applicant returned to address corrections 1/31/2019 YOUNG KIM
Applicant returned to address corrections 2/11/2019 YOUNG KIM
Plan Check Approved 2/26/2019 YOUNG KIM
Issued 3/19/2019 LADBS
CofO in Progress 4/26/2022 RUBEN SALAS
Permit Finaled 5/6/2022 DEROLD HAUFF
CofO Issued 5/6/2022 DEROLD HAUFF
Permit Finaled 5/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/24/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 7/24/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 10/2/2018 JOHN CONNEALLY
Construction within easement Cleared 10/25/2018 RIDWAN HARDY
Green Code Cleared 10/30/2018 KHEDER ALRAZAA
Miscellaneous Cleared 11/6/2018 YOVANA PEREZ
Specific Plan Cleared 11/6/2018 YOVANA PEREZ
Low Impact Development Cleared 11/28/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 11/28/2018 MICHAEL CASTILLO
Sewer availability Cleared 11/28/2018 MICHAEL CASTILLO
GPI Written Notices Cleared 12/11/2018 YOUNG KIM
Grading Pre-Inspection Cleared 12/11/2018 YOUNG KIM

Contact Information

Architect Arc, Pac (Usa) Inc.; Lic. No.: C33135 2854 E LARKHILL DRIVE      WEST COVINA, CA 91791
Contractor Ozair Construction & Design Inc; Lic. No.: 992682-B 1145 N MCCADDEN PLACE      LOS ANGELES, CA 90038
Engineer Cai, Luo B; Lic. No.: C80352 5244 HUCKLEBERRY OAK STREET      SIMI VALLEY, CA 93063
Engineer Saljooghi, Sanjar; Lic. No.: C53610 23265 PARK ENSENADA      CALABASAS, CA 91302
Engineer Tsao, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/2/2019 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 5/14/2019 No Access for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 10/18/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/26/2019 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/2/2020 Not Ready for Inspection RICHARD STEINBACH
Footing/Foundation/Slab 1/13/2020 Not Ready for Inspection RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 1/17/2020 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 2/26/2020 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 5/11/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 5/11/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/20/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 6/22/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Reinforced Concrete Frame 6/24/2020 No Access for Inspection RAUL BARAJAS
Footing/Foundation/Slab 6/26/2020 Partial Inspection RAUL BARAJAS
Piling/Pier/Caisson 6/30/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 7/9/2020 Corrections Issued ENRIQUE MIRELES
Deputy Steel/Welding 7/10/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/3/2020 Partial Approval RAUL BARAJAS
Green Building Rough 8/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Structural Steel Frame 8/11/2020 Corrections Issued ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 8/13/2020 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 8/13/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/13/2020 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 8/17/2020 No Access for Inspection RAUL BARAJAS
Structural Steel Frame 8/17/2020 No Access for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/17/2020 No Access for Inspection RAUL BARAJAS
Green Building Rough 8/20/2020 Not Ready for Inspection JOSEPH MCGARRY
Structural Steel Frame 8/20/2020 Partial Approval JOSEPH MCGARRY
Verify Sprinkler Sign Off 8/20/2020 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 9/16/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Partial Approval DONALD CRICHLOW
ELECTRICAL-Rough 12/18/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 12/18/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 12/18/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/28/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 12/28/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 12/28/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 1/4/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 1/4/2021 Approved RAUL BARAJAS
ELECTRICAL-Rough 1/14/2021 Approved RAUL BARAJAS
HVAC-Rough 1/14/2021 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 1/26/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 1/26/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 1/26/2021 Not Ready for Inspection RAUL BARAJAS
Grading Pre-Inspection 2/24/2021 Not Ready for Inspection RAUL BARAJAS
Shower Pan 2/26/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 3/4/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 3/4/2021 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 3/4/2021 Not Ready for Inspection RAUL BARAJAS
Deputy Wood Construction 3/8/2021 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 3/11/2021 Partial Inspection RAUL BARAJAS
Insulation 3/11/2021 Partial Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 3/11/2021 Not Ready for Inspection RAUL BARAJAS
Insulation 3/19/2021 Conditional Approval RAUL BARAJAS
Pre-Inspection 4/5/2021 Partial Inspection RAUL BARAJAS
Drywall Nailing 4/14/2021 Partial Approval RAUL BARAJAS
Pre-Inspection 4/14/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 4/26/2021 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 4/26/2021 Conditional Approval JOSEPH MCGARRY
Pre-Inspection 4/26/2021 Corrections Issued JOSEPH MCGARRY
Verify Sprinkler Sign Off 4/26/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/14/2021 Partial Inspection RUBEN SALAS
Interior/Exterior Lathing 6/11/2021 Approved RAUL BARAJAS
Pre-Inspection 6/11/2021 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 7/23/2021 Approved RICHARD STEINBACH
Drywall Nailing 7/23/2021 Approved RICHARD STEINBACH
Insulation 7/23/2021 Approved RICHARD STEINBACH
Deck 9/24/2021 Not Ready for Inspection RICHARD STEINBACH
Deck 9/30/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 11/24/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 12/27/2021 Partial Inspection RAUL BARAJAS
PLUMBING-Final 1/7/2022 Corrections Issued CRAIG DAVIS
Grading Pre-Inspection 1/11/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 1/11/2022 Partial Inspection RAUL BARAJAS
Service/Power Release 1/12/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 2/22/2022 Approved RAUL BARAJAS
HVAC-Final 2/22/2022 Corrections Issued RAUL BARAJAS
Final 3/11/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 3/11/2022 Approved RAUL BARAJAS
Green Building Final 3/11/2022 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 3/11/2022 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 3/11/2022 Approved RAUL BARAJAS
Final 3/23/2022 Corrections Issued RAUL BARAJAS
Green Building Final 3/23/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 3/23/2022 Approved RAUL BARAJAS
Final 4/14/2022 Corrections Issued RAUL BARAJAS
Final 4/26/2022 OK to Issue CofO RAUL BARAJAS