1657 N MICHELTORENA ST 90026

Certificate Information: 1657 N MICHELTORENA ST 90026

Application / Permit
18010-10000-01493
Plan Check / Job No.
B18LA06635
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY 23' X 33', TYPE VB, R3-OCC SINGLE FAMILY DWELLING WITH ATTACHED 13' X 16', U-OCC CARPORT. FULLY FIRE SPRINKLERED PER NFPA-13D.
Permit Issued
Issued on 6/25/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2018 APPLICANT
Assigned to Plan Check Engineer 4/26/2018 DEVIN GORDON
Corrections Issued 4/30/2018 DEVIN GORDON
Quality Review Completed 5/4/2018 KESETE HAREGOT
Building Plans Picked Up 5/4/2018 APPLICANT
Green Plans Picked Up 5/9/2018 APPLICANT
Plan Check Approved 6/21/2018 DEVIN GORDON
Issued 6/25/2018 LADBS
CofO in Progress 6/19/2020 SCOTT FINNILA
Permit Finaled 6/19/2020 DEROLD HAUFF
CofO Issued 6/19/2020 DEROLD HAUFF
Permit Finaled 6/19/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/9/2018 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 5/9/2018 JAMES MORALEZ
Hydrant and Access approval Cleared 5/9/2018 JOHN CONNEALLY
Sewer availability Cleared 5/9/2018 JAMES MORALEZ
Grading Pre-Inspection Cleared 5/10/2018 PATRICK MISCHLICH
Low Impact Development Cleared 6/6/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 6/6/2018 CELINA MORENO
Green Code Cleared 6/20/2018 COLIN LOREDO
GPI Written Notices Cleared 6/21/2018 DEVIN GORDON

Contact Information

Contractor Owner-Builder       ,
Engineer Evangelista, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2018 Partial Approval DAVID CHAN
Footing/Foundation/Slab 8/30/2018 Partial Approval DAVID CHAN
HVAC-Rough 1/7/2019 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2019 Corrections Issued ANDEY CHAPARRO
PLUMBING-Rough 1/10/2019 Approved ANDEY CHAPARRO
ELECTRICAL-Rough 1/28/2019 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2019 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 3/5/2019 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 3/5/2019 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 3/8/2019 Corrections Issued DAVID CHAN
Green Building Rough 3/8/2019 Approved DAVID CHAN
Verify Sprinkler Sign Off 3/8/2019 Approved DAVID CHAN
Excavation/Setback/Form/Re-Bar 4/5/2019 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 4/9/2019 Approved DAVID CHAN
Excavation/Setback/Form/Re-Bar 5/3/2019 Conditional Approval DAVID CHAN
Drywall Nailing 5/21/2019 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 8/20/2019 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 10/25/2019 Not Ready for Inspection DAVID CHAN
BUILDING-Rough-Frame 11/18/2019 Not Ready for Inspection AJA COLLAY
Drywall Nailing 11/18/2019 Not Ready for Inspection AJA COLLAY
Final 11/18/2019 Not Ready for Inspection AJA COLLAY
Green Building Final 11/18/2019 Not Ready for Inspection AJA COLLAY
SGSOV-Seismic Gas S/O Valve 11/18/2019 SGSOV Not Ready AJA COLLAY
Service/Power Release 11/18/2019 Not Ready for Inspection AJA COLLAY
Smoke Detectors 11/18/2019 Not Ready for Inspection AJA COLLAY
BUILDING-Rough-Frame 12/3/2019 Not Ready for Inspection AJA COLLAY
Drywall Nailing 12/3/2019 Not Ready for Inspection AJA COLLAY
Final 12/3/2019 Corrections Issued AJA COLLAY
Green Building Final 12/3/2019 Not Ready for Inspection AJA COLLAY
SGSOV-Seismic Gas S/O Valve 12/3/2019 SGSOV Not Ready AJA COLLAY
Service/Power Release 12/3/2019 Not Ready for Inspection AJA COLLAY
Smoke Detectors 12/3/2019 Not Ready for Inspection AJA COLLAY
BUILDING-Rough-Frame 1/10/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 2/7/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Deputy Steel/Welding 2/18/2020 Approved MATTHEW NUCKOLLS
BUILDING-Rough-Frame 2/19/2020 Corrections Issued AJA COLLAY
BUILDING-Rough-Frame 2/28/2020 Partial Inspection AJA COLLAY
Gas Test 3/17/2020 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 3/31/2020 SGSOV Not Ready ROBERT MCDOWELL
Service/Power Release 3/31/2020 Not Ready for Inspection ROBERT MCDOWELL
Pre-Inspection 4/7/2020 Not Ready for Inspection GORDON ZUBER
Final 4/17/2020 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/29/2020 Approved SCOTT FINNILA
Drywall Nailing 5/29/2020 Approved SCOTT FINNILA
Final 5/29/2020 Corrections Issued SCOTT FINNILA
Green Building Final 5/29/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 5/29/2020 Not Ready for Inspection SCOTT FINNILA
Smoke Detectors 5/29/2020 Approved SCOTT FINNILA
Final 6/4/2020 Partial Inspection SCOTT FINNILA
Service/Power Release 6/4/2020 Partial Inspection SCOTT FINNILA
Final 6/16/2020 Partial Inspection RUBEN SALAS
Service/Power Release 6/16/2020 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 6/17/2020 Approved SCOTT FINNILA
HVAC-Final 6/17/2020 Approved SCOTT FINNILA
PLUMBING-Final 6/17/2020 Approved SCOTT FINNILA
Final 6/22/2020 OK to Issue CofO SCOTT FINNILA
Service/Power Release 6/22/2020 Approved SCOTT FINNILA