1657 N MICHELTORENA ST 90026
Certificate Information: 1657 N MICHELTORENA ST 90026
- Application / Permit
- 18010-10000-01493
- Plan Check / Job No.
- B18LA06635
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY 23' X 33', TYPE VB, R3-OCC SINGLE FAMILY DWELLING WITH ATTACHED 13' X 16', U-OCC CARPORT. FULLY FIRE SPRINKLERED PER NFPA-13D.
- Permit Issued
- Issued on 6/25/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2018 | DEVIN GORDON |
| Corrections Issued | 4/30/2018 | DEVIN GORDON |
| Quality Review Completed | 5/4/2018 | KESETE HAREGOT |
| Building Plans Picked Up | 5/4/2018 | APPLICANT |
| Green Plans Picked Up | 5/9/2018 | APPLICANT |
| Plan Check Approved | 6/21/2018 | DEVIN GORDON |
| Issued | 6/25/2018 | LADBS |
| CofO in Progress | 6/19/2020 | SCOTT FINNILA |
| Permit Finaled | 6/19/2020 | DEROLD HAUFF |
| CofO Issued | 6/19/2020 | DEROLD HAUFF |
| Permit Finaled | 6/19/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2018 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2018 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 5/9/2018 | JOHN CONNEALLY |
| Sewer availability | Cleared | 5/9/2018 | JAMES MORALEZ |
| Grading Pre-Inspection | Cleared | 5/10/2018 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 6/6/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 6/6/2018 | CELINA MORENO |
| Green Code | Cleared | 6/20/2018 | COLIN LOREDO |
| GPI Written Notices | Cleared | 6/21/2018 | DEVIN GORDON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2018 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 8/30/2018 | Partial Approval | DAVID CHAN |
| HVAC-Rough | 1/7/2019 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2019 | Corrections Issued | ANDEY CHAPARRO |
| PLUMBING-Rough | 1/10/2019 | Approved | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 1/28/2019 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2019 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 3/5/2019 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2019 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 3/8/2019 | Corrections Issued | DAVID CHAN |
| Green Building Rough | 3/8/2019 | Approved | DAVID CHAN |
| Verify Sprinkler Sign Off | 3/8/2019 | Approved | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 4/5/2019 | Corrections Issued | DAVID CHAN |
| Footing/Foundation/Slab | 4/9/2019 | Approved | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 5/3/2019 | Conditional Approval | DAVID CHAN |
| Drywall Nailing | 5/21/2019 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 8/20/2019 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 10/25/2019 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 11/18/2019 | Not Ready for Inspection | AJA COLLAY |
| Drywall Nailing | 11/18/2019 | Not Ready for Inspection | AJA COLLAY |
| Final | 11/18/2019 | Not Ready for Inspection | AJA COLLAY |
| Green Building Final | 11/18/2019 | Not Ready for Inspection | AJA COLLAY |
| SGSOV-Seismic Gas S/O Valve | 11/18/2019 | SGSOV Not Ready | AJA COLLAY |
| Service/Power Release | 11/18/2019 | Not Ready for Inspection | AJA COLLAY |
| Smoke Detectors | 11/18/2019 | Not Ready for Inspection | AJA COLLAY |
| BUILDING-Rough-Frame | 12/3/2019 | Not Ready for Inspection | AJA COLLAY |
| Drywall Nailing | 12/3/2019 | Not Ready for Inspection | AJA COLLAY |
| Final | 12/3/2019 | Corrections Issued | AJA COLLAY |
| Green Building Final | 12/3/2019 | Not Ready for Inspection | AJA COLLAY |
| SGSOV-Seismic Gas S/O Valve | 12/3/2019 | SGSOV Not Ready | AJA COLLAY |
| Service/Power Release | 12/3/2019 | Not Ready for Inspection | AJA COLLAY |
| Smoke Detectors | 12/3/2019 | Not Ready for Inspection | AJA COLLAY |
| BUILDING-Rough-Frame | 1/10/2020 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 2/7/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Deputy Steel/Welding | 2/18/2020 | Approved | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 2/19/2020 | Corrections Issued | AJA COLLAY |
| BUILDING-Rough-Frame | 2/28/2020 | Partial Inspection | AJA COLLAY |
| Gas Test | 3/17/2020 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/31/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 3/31/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Pre-Inspection | 4/7/2020 | Not Ready for Inspection | GORDON ZUBER |
| Final | 4/17/2020 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/29/2020 | Approved | SCOTT FINNILA |
| Drywall Nailing | 5/29/2020 | Approved | SCOTT FINNILA |
| Final | 5/29/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 5/29/2020 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/29/2020 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 5/29/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Smoke Detectors | 5/29/2020 | Approved | SCOTT FINNILA |
| Final | 6/4/2020 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 6/4/2020 | Partial Inspection | SCOTT FINNILA |
| Final | 6/16/2020 | Partial Inspection | RUBEN SALAS |
| Service/Power Release | 6/16/2020 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 6/17/2020 | Approved | SCOTT FINNILA |
| HVAC-Final | 6/17/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 6/17/2020 | Approved | SCOTT FINNILA |
| Final | 6/22/2020 | OK to Issue CofO | SCOTT FINNILA |
| Service/Power Release | 6/22/2020 | Approved | SCOTT FINNILA |