4153 N VANTAGE AVE 91604
Certificate Information: 4153 N VANTAGE AVE 91604
- Application / Permit
- 18010-10000-01451
- Plan Check / Job No.
- B18LA06409
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story addition and remodeling existiong SFD.
- Permit Issued
- Issued on 6/4/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2018 | JOE VO |
| Corrections Issued | 4/23/2018 | JOE VO |
| Quality Review Completed | 4/24/2018 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/16/2018 | APPLICANT |
| Green Plans Picked Up | 5/16/2018 | APPLICANT |
| Applicant returned to address corrections | 3/27/2019 | JOE VO |
| Plan Check Approved | 5/28/2019 | SALVADOR QUINTANILLA |
| Issued | 6/4/2019 | LADBS |
| CofO in Progress | 1/23/2025 | JACK KARGODORIAN |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| CofO Issued | 3/6/2025 | RUBEN SALAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Green Code | Cleared | 10/29/2018 | SARAH ABOULHOSN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2019 | KARAN PATEL |
| Permit | Cleared | 2/25/2019 | KARAN PATEL |
| Sewer availability | Cleared | 2/25/2019 | KARAN PATEL |
| Hydrant and Access approval | Cleared | 3/21/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/21/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/21/2019 | ELENA LOPEZ |
| ZI | Cleared | 3/21/2019 | KIT AWAKUNI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/9/2020 | Partial Approval | RAYMOND KEHOE |
| Footing/Foundation/Slab | 1/9/2020 | Partial Approval | RAYMOND KEHOE |
| Excavation/Setback/Form/Re-Bar | 1/27/2020 | Partial Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 1/27/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Deputy Shotcrete | 1/29/2020 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 3/6/2020 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/22/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/15/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/24/2020 | Approved | ARAM AVEDISIAN |
| Sewer | 7/8/2020 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 7/21/2020 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 7/24/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/9/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Deputy Wood Construction | 12/9/2020 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/16/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/16/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/16/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/23/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/23/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/30/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/30/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/9/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/9/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 5/12/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 5/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/5/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/7/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/7/2023 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/26/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/6/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/6/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 1/22/2025 | Approved | JACK KARGODORIAN |
| Final | 1/22/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 1/22/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 1/22/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 1/22/2025 | Approved | JACK KARGODORIAN |