3609 W OLYMPIC BLVD 1-50 90019

Certificate Information: 3609 W OLYMPIC BLVD 1-50 90019

Application / Permit
18010-10000-01450
Plan Check / Job No.
B18LA06408
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6 STORY, TYPE IIIA, 50 UNIT APARTMENT BUILDING OVER, TYPE IA, GRADE LEVEL AND 1 SUBTERRANEAN PARKING GARAGES. TOC TIER 2 AFFORDABLE HOUSING INCENTIVE PROJECT WITH 6 VLI UNITS.
Permit Issued
Issued on 3/1/2023
Issuing Office
Metro
Current Status
Issued on 3/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2018 APPLICANT
Assigned to Plan Check Engineer 5/10/2018 KESETE HAREGOT
Corrections Issued 5/23/2018 KESETE HAREGOT
Quality Review Completed 5/31/2018 ARMEN JIVALAGIAN
Building Plans Picked Up 6/21/2018 APPLICANT
Disabled Access Plans Picked Up 9/9/2019 APPLICANT
Applicant returned to address corrections 10/1/2019 KESETE HAREGOT
Applicant returned to address corrections 3/10/2020 KESETE HAREGOT
Green Plans Picked Up 8/19/2021 APPLICANT
Plan Check Approved 12/28/2021 KESETE HAREGOT
Issued 3/1/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/6/2018 STEVE MELGAR
Highway dedication Cleared 11/6/2018 STEVE MELGAR
Hydrant and Access approval Cleared 11/6/2018 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 11/8/2018 STEVE MELGAR
Tract Map conditions Cleared 11/29/2018 BLAYNE SUTTON-WILLS
Work Adjacent to Public Way Cleared 7/3/2019 TERRY PHAN
DCP conditions approval Cleared 1/24/2020 RICHARD TRUONG
Density Bonus 12.22.A.31 Cleared 1/24/2020 RICHARD TRUONG
Building over 3-story or 36-ft Cleared 3/10/2020 CALOSHA APPROVED
Permit Cleared 6/8/2020 EMIL KYUPELYAN
Green Code Cleared 10/8/2020 NEGAR NEJAD
Low Impact Development Cleared 5/3/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/5/2021 JEANIE LAM
DAS Clearance Cleared 5/11/2021 SHINE LIN
Comm Cor/Mini-Mall Cleared 8/2/2021 RICHARD REASER
Comm Cor/Mini-Mall Cleared 8/2/2021 RICHARD REASER
Frnt yard landscape/Water mgmt Cleared 8/2/2021 RICHARD REASER
Miscellaneous Cleared 8/2/2021 RICHARD REASER
Opn space landscape/Water mgmt Cleared 8/2/2021 RICHARD REASER
Prkng lot landscape/Water mgmt Cleared 8/2/2021 RICHARD REASER
Site Plan review Cleared 8/2/2021 RICHARD REASER
Miscellaneous Cleared 8/6/2021 RICHARD REASER
Sewer availability Cleared 9/27/2021 WALLIE JONG
Fire Marshall Fire Life Safety Cleared 12/21/2021 PEJMAN NOORI

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Owner-Builder       ,
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Kim,, Taik Yul; Lic. No.: C40432 1110 S BERENDO ST APT. C      LOS ANGELES, CA 90006
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Landscape Architect Lir,, Yael; Lic. No.: LA3171 1010 SYCAMORE AVE STE 313      S PASADENA, CA 91030

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/13/2023 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/25/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/26/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/16/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/20/2024 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/22/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/23/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/27/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/27/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/22/2024 No Access for Inspection EDWIN GREGORYONA
METHANE-Barrier 3/22/2024 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/22/2024 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/3/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/3/2024 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/3/2024 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/15/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/15/2024 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/29/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/29/2024 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 5/29/2024 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 5/29/2024 Approved EDWIN GREGORYONA
METHANE-Rough 5/29/2024 Approved EDWIN GREGORYONA
METHANE-Subgrade 5/29/2024 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 5/29/2024 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/29/2024 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 6/17/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 6/25/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/8/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/2/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/5/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/17/2024 Partial Approval LARRY ARNICK
Wood Frame 9/17/2024 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval RONALD JIMENEZ
Wall Anchors 9/18/2024 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 9/18/2024 Not Ready for Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 12/2/2024 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 12/4/2024 Partial Approval EDWIN GREGORYONA
Insulation 12/11/2024 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 12/16/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/26/2024 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 1/7/2025 Partial Approval MARTIN TAVITIAN
Wood Frame 1/9/2025 Partial Approval EDWIN GREGORYONA
Insulation 1/22/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 1/27/2025 Not Ready for Inspection JEFFREY FULTON
Deputy Wood Construction 2/3/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/4/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 2/5/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/7/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/19/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 2/27/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 3/10/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/17/2025 Partial Approval EDWIN GREGORYONA
Insulation 3/27/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/27/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/2/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 4/4/2025 Partial Approval EDWIN GREGORYONA
Insulation 4/8/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/17/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 4/21/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 4/23/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 4/24/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 5/16/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 5/20/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 5/27/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/3/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/9/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/13/2025 Partial Approval EDWIN GREGORYONA
Insulation 7/3/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/14/2025 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 7/14/2025 Approved EDWIN GREGORYONA
Drywall Nailing 7/21/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 7/22/2025 Partial Approval EDWIN GREGORYONA
Insulation 7/24/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/30/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 8/5/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 8/12/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/14/2025 Partial Approval EDWIN GREGORYONA
Insulation 9/22/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 10/1/2025 Partial Approval EDWIN GREGORYONA
Insulation 10/3/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/10/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 10/10/2025 Partial Approval EDWIN GREGORYONA
Insulation 10/14/2025 Partial Approval MARTIN TAVITIAN
Insulation 10/15/2025 Partial Approval MARTIN TAVITIAN
Wood Frame 10/31/2025 Partial Approval EDWIN GREGORYONA
Insulation 11/5/2025 Partial Inspection EDWIN GREGORYONA
Insulation 11/12/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/21/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Partial Approval JAMES POWERS
Drywall Nailing 12/18/2025 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 1/13/2026 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/20/2026 Partial Inspection JEFFREY FULTON
Wood Frame 5/11/2026 Approved MARTIN TAVITIAN
Insulation 5/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 5/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Drywall Nailing 5/27/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/3/2026 Partial Approval MARTIN TAVITIAN
Special/Order Compliance 6/3/2026 Approved MARTIN TAVITIAN