310 N NEWLAND ST 90042
Certificate Information: 310 N NEWLAND ST 90042
- Application / Permit
- 18010-10000-01445
- Plan Check / Job No.
- B18LA06381
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) 20'-0" x 25'-0" detached 2-Car Garage with Rec-Room above.
- Permit Issued
- Issued on 8/2/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2018 | OMID HEDAYAT |
| Corrections Issued | 5/11/2018 | OMID HEDAYAT |
| Quality Review Completed | 5/23/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 5/25/2018 | APPLICANT |
| Green Plans Picked Up | 5/29/2018 | APPLICANT |
| Applicant returned to address corrections | 7/26/2018 | OMID HEDAYAT |
| Plan Check Approved | 7/26/2018 | OMID HEDAYAT |
| Issued | 8/2/2018 | LADBS |
| CofO in Progress | 4/7/2020 | CRAIG VAUGHAN |
| Permit Finaled | 6/17/2020 | DEROLD HAUFF |
| CofO Issued | 6/17/2020 | DEROLD HAUFF |
| Permit Finaled | 6/17/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/11/2018 | OMID HEDAYAT |
| Grading Pre-Inspection | Cleared | 5/11/2018 | OMID HEDAYAT |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2018 | STEVE MELGAR |
| Green Code | Cleared | 6/13/2018 | SARAH ABOULHOSN |
| Sewer availability | Cleared | 6/13/2018 | STEVE MELGAR |
| Low Impact Development | Cleared | 7/17/2018 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 7/17/2018 | JAMES MORALEZ |
Contact Information
| Contractor | Dave'S Works Corporation; Lic. No.: 788467-B | 3873 MARCASEL AVENUE LOS ANGELES, CA 90066 |
| Engineer | Maalouf, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/14/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/14/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/16/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/17/2018 | Approved | RUBEN SALAS |
| Footing/Foundation/Slab | 8/17/2018 | Partial Approval | RUBEN SALAS |
| Sewer | 8/17/2018 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 8/21/2018 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2018 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2018 | Corrections Issued | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2018 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/26/2018 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/26/2018 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/26/2018 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/26/2018 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/26/2018 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/28/2018 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/28/2018 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/28/2018 | Approved | ENRIQUE MIRELES |
| Insulation | 12/4/2018 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 12/4/2018 | Partial Approval | RUBEN SALAS |
| Drywall Nailing | 12/10/2018 | Approved | ENRIQUE MIRELES |
| Shower Pan | 12/13/2018 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/4/2019 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 1/28/2019 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/15/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/15/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 10/15/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 10/15/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 10/15/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2019 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 10/15/2019 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 10/15/2019 | Corrections Issued | CRAIG VAUGHAN |
| Final | 3/17/2020 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 3/17/2020 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 3/17/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 3/17/2020 | Approved | CRAIG VAUGHAN |
| Final | 3/23/2020 | Partial Inspection | CRAIG VAUGHAN |
| Green Building Final | 3/23/2020 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 3/23/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 4/6/2020 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 4/6/2020 | Approved | CRAIG VAUGHAN |