310 N NEWLAND ST 90042

Certificate Information: 310 N NEWLAND ST 90042

Application / Permit
18010-10000-01445
Plan Check / Job No.
B18LA06381
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) 20'-0" x 25'-0" detached 2-Car Garage with Rec-Room above.
Permit Issued
Issued on 8/2/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2018 APPLICANT
Assigned to Plan Check Engineer 5/10/2018 OMID HEDAYAT
Corrections Issued 5/11/2018 OMID HEDAYAT
Quality Review Completed 5/23/2018 CHON CHIO KUO
Building Plans Picked Up 5/25/2018 APPLICANT
Green Plans Picked Up 5/29/2018 APPLICANT
Applicant returned to address corrections 7/26/2018 OMID HEDAYAT
Plan Check Approved 7/26/2018 OMID HEDAYAT
Issued 8/2/2018 LADBS
CofO in Progress 4/7/2020 CRAIG VAUGHAN
Permit Finaled 6/17/2020 DEROLD HAUFF
CofO Issued 6/17/2020 DEROLD HAUFF
Permit Finaled 6/17/2020 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 5/11/2018 OMID HEDAYAT
Grading Pre-Inspection Cleared 5/11/2018 OMID HEDAYAT
Eng Process Fee Ord 176,300 Cleared 6/13/2018 STEVE MELGAR
Green Code Cleared 6/13/2018 SARAH ABOULHOSN
Sewer availability Cleared 6/13/2018 STEVE MELGAR
Low Impact Development Cleared 7/17/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 7/17/2018 JAMES MORALEZ

Contact Information

Contractor Dave'S Works Corporation; Lic. No.: 788467-B 3873 MARCASEL AVENUE      LOS ANGELES, CA 90066
Engineer Maalouf, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/14/2018 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/14/2018 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/16/2018 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/16/2018 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/17/2018 Approved RUBEN SALAS
Footing/Foundation/Slab 8/17/2018 Partial Approval RUBEN SALAS
Sewer 8/17/2018 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 8/21/2018 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 9/5/2018 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/20/2018 Corrections Issued RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 9/24/2018 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/28/2018 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 11/26/2018 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/26/2018 Approved ENRIQUE MIRELES
Green Building Rough 11/26/2018 Approved ENRIQUE MIRELES
HVAC-Rough 11/26/2018 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/26/2018 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 11/28/2018 Approved ENRIQUE MIRELES
HVAC-Rough 11/28/2018 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/28/2018 Approved ENRIQUE MIRELES
Insulation 12/4/2018 Approved RUBEN SALAS
Interior/Exterior Lathing 12/4/2018 Partial Approval RUBEN SALAS
Drywall Nailing 12/10/2018 Approved ENRIQUE MIRELES
Shower Pan 12/13/2018 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/4/2019 Approved RUBEN SALAS
PLUMBING-Rough 1/28/2019 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Final 10/15/2019 Not Ready for Inspection CRAIG VAUGHAN
Final 10/15/2019 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 10/15/2019 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 10/15/2019 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 10/15/2019 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/15/2019 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 10/15/2019 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 10/15/2019 Corrections Issued CRAIG VAUGHAN
Final 3/17/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 3/17/2020 Corrections Issued CRAIG VAUGHAN
Service/Power Release 3/17/2020 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 3/17/2020 Approved CRAIG VAUGHAN
Final 3/23/2020 Partial Inspection CRAIG VAUGHAN
Green Building Final 3/23/2020 Approved CRAIG VAUGHAN
Service/Power Release 3/23/2020 Not Ready for Inspection CRAIG VAUGHAN
Final 4/6/2020 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 4/6/2020 Approved CRAIG VAUGHAN