9842 W VIDOR DR 90035

Certificate Information: 9842 W VIDOR DR 90035

Application / Permit
18010-10000-01433
Plan Check / Job No.
B18LA06304
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4-STORY, 8-UNIT APARTMENT W/ 1-LEVEL SUBTERRANEAN PARKING.
Permit Issued
Issued on 10/15/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2018 APPLICANT
Green Plans Picked Up 4/10/2018 APPLICANT
Disabled Access Plans Picked Up 4/23/2018 APPLICANT
Assigned to Plan Check Engineer 4/26/2018 HERNAN ARREOLA
Building Plans Picked Up 5/17/2018 APPLICANT
Corrections Issued 7/3/2018 HERNAN ARREOLA
Quality Review Completed 7/5/2018 MINYE PAK
Applicant returned to address corrections 10/3/2018 HERNAN ARREOLA
Applicant returned to address corrections 5/24/2019 HERNAN ARREOLA
Applicant returned to address corrections 8/6/2019 HERNAN ARREOLA
Plan Check Approved 8/30/2019 HERNAN ARREOLA
Issued 10/15/2019 LADBS
CofO in Progress 2/15/2023 DERRICK SPENCER
CofO in Progress 2/28/2023 DERRICK SPENCER
Permit Finaled 3/3/2023 DAVID TSAU
CofO Issued 3/3/2023 DAVID TSAU
Permit Finaled 3/3/2023 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 6/21/2018 SEAN VEAL
Address approval Cleared 6/26/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/26/2018 STEVE MELGAR
Sewer availability Cleared 8/3/2018 ADRIAN SANCHEZ
Highway dedication Cleared 8/9/2018 CHRISTOPHER LAW
Specific Plan Cleared 8/28/2018 EDER ROMERO
Building over 3-story or 36-ft Cleared 9/7/2018 CALOSHA APPROVED
Green Code Cleared 9/27/2018 NEGAR NEJAD
Hydrant and Access approval Cleared 10/5/2018 JOHN CONNEALLY
Work Adjacent to Public Way Cleared 1/23/2019 BOK GOH
DAS Clearance Cleared 1/29/2019 ELIZABETH TOMS
Construction near power lines Cleared 4/3/2019 RIDWAN HARDY
Low Impact Development Cleared 4/23/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/14/2019 ELENA LOPEZ
Fire Marshall Fire Life Safety Cleared 5/22/2019 PEJMAN NOORI
Excavation more than 5-ft deep Cleared 5/24/2019 CALOSHA APPROVED
Opn space landscape/Water mgmt Cleared 8/6/2019 DIANA JIMENEZ

Contact Information

Architect Vanos, Vincent Jay; Lic. No.: C22269 1733 S LA CIENEGA BLVD      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Park, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD      LOS ANGELES, CA 90010
Engineer Sahebi,, Mo; Lic. No.: C33508 1330 OLYMPIC BL      SANTA MONICA, CA 90404

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2019 Partial Approval JEFF BYTHEWAY
METHANE-Barrier 12/20/2019 Partial Approval JEFF BYTHEWAY
METHANE-Subgrade 12/20/2019 Partial Approval JEFF BYTHEWAY
METHANE-Barrier 1/6/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 1/6/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 1/6/2020 Not Ready for Inspection JEFF BYTHEWAY
Deputy Shotcrete 1/7/2020 Approved JEFF BYTHEWAY
Green Building Rough 1/7/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Rough 1/7/2020 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 1/7/2020 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 1/7/2020 Not Ready for Inspection JEFF BYTHEWAY
Deputy Shotcrete 1/9/2020 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 1/14/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Barrier 1/14/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 1/14/2020 Not Ready for Inspection JEFF BYTHEWAY
Green Building Rough 1/15/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Rough 1/15/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 1/15/2020 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 1/15/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Barrier 1/23/2020 Approved JEFF BYTHEWAY
METHANE-Subgrade 1/23/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Masonry Frame 1/23/2020 Partial Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 1/27/2020 Partial Approval JEFF BYTHEWAY
METHANE-Subgrade 1/27/2020 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/4/2020 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 2/7/2020 Partial Approval JEFF BYTHEWAY
Deputy Methane Barrier 2/14/2020 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/18/2020 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 2/21/2020 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 3/6/2020 Partial Approval TED RIES
Deputy Methane Barrier 4/15/2020 Approved JEFF BYTHEWAY
Deputy Methane Barrier 4/16/2020 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/17/2020 Partial Approval JEFF BYTHEWAY
Special/Order Compliance 5/20/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/18/2020 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 6/18/2020 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/19/2020 Approved JEFF BYTHEWAY
Green Building Rough 7/7/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Rough 7/7/2020 Approved JEFF BYTHEWAY
Verify Sprinkler Sign Off 7/7/2020 Approved JEFF BYTHEWAY
Wood Frame 7/7/2020 Partial Inspection JEFF BYTHEWAY
Special/Order Compliance 7/14/2020 Corrections Issued JEFF BYTHEWAY
Special/Order Compliance 7/15/2020 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Partial Approval JEFF BYTHEWAY
Green Building Rough 8/3/2020 Not Ready for Inspection JEFF BYTHEWAY
Green Building Rough 8/24/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 8/24/2020 Not Ready for Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/25/2020 Partial Approval DERRICK SPENCER
Green Building Rough 9/18/2020 Not Ready for Inspection ALAN NOVAK
Wood Frame 9/18/2020 Not Ready for Inspection ALAN NOVAK
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval SORIN CIRSTOIU
Green Building Rough 9/25/2020 Not Ready for Inspection DERRICK SPENCER
Wood Frame 9/25/2020 Partial Approval DERRICK SPENCER
Green Building Rough 10/19/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 10/19/2020 Not Ready for Inspection JEFF BYTHEWAY
Pre-Inspection 10/30/2020 Approved JEFF BYTHEWAY
Green Building Rough 11/4/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 11/4/2020 Partial Approval JEFF BYTHEWAY
Green Building Rough 12/4/2020 Partial Inspection SORIN CIRSTOIU
Wood Frame 12/4/2020 Partial Approval SORIN CIRSTOIU
Green Building Rough 1/8/2021 Not Ready for Inspection DERRICK SPENCER
Wood Frame 1/8/2021 Partial Approval DERRICK SPENCER
Green Building Rough 2/3/2021 Approved JEFF BYTHEWAY
Wood Frame 2/3/2021 Partial Inspection JEFF BYTHEWAY
Wood Frame 2/25/2021 Not Ready for Inspection JEFF BYTHEWAY
Deputy Steel/Welding 2/26/2021 Approved JEFF BYTHEWAY
Wood Frame 3/1/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 3/3/2021 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 3/9/2021 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 3/17/2021 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 3/19/2021 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 3/31/2021 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 4/5/2021 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 4/12/2021 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 4/14/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 4/28/2021 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 5/4/2021 Partial Approval JEFF BYTHEWAY
Insulation 5/6/2021 Partial Approval JEFF BYTHEWAY
Insulation 5/12/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 5/14/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 5/25/2021 Not Ready for Inspection JEFF BYTHEWAY
Insulation 5/26/2021 Partial Approval JEFF BYTHEWAY
Masonry Wall/Backfill 6/3/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 6/16/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 9/7/2021 Partial Approval DERRICK SPENCER
Drywall Nailing 9/14/2021 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 9/29/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 1/25/2022 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 2/2/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 3/29/2022 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 9/27/2022 Approved NICK LAROCCA
Final 9/27/2022 Not Ready for Inspection NICK LAROCCA
Footing/Foundation/Slab 9/27/2022 Approved NICK LAROCCA
Green Building Final 9/27/2022 Approved NICK LAROCCA
Reinforced Masonry Frame 9/27/2022 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Approved NICK LAROCCA
Smoke Detectors 9/27/2022 Approved NICK LAROCCA
Structural Steel Frame 9/27/2022 Approved NICK LAROCCA
Wood Frame 9/27/2022 Approved NICK LAROCCA
Final 10/7/2022 Not Ready for Inspection DERRICK SPENCER
Final 11/4/2022 Not Ready for Inspection DERRICK SPENCER
Final 11/15/2022 Not Ready for Inspection DERRICK SPENCER
Final 11/17/2022 Not Ready for Inspection DERRICK SPENCER
Final 1/9/2023 Not Ready for Inspection DERRICK SPENCER
Final 1/18/2023 Not Ready for Inspection DERRICK SPENCER
Final 1/20/2023 Not Ready for Inspection DERRICK SPENCER
Final 1/26/2023 Not Ready for Inspection DERRICK SPENCER
Final 2/8/2023 OK to Issue CofO DERRICK SPENCER
Final 2/15/2023 OK to Issue CofO DERRICK SPENCER