9842 W VIDOR DR 90035
Certificate Information: 9842 W VIDOR DR 90035
- Application / Permit
- 18010-10000-01433
- Plan Check / Job No.
- B18LA06304
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 4-STORY, 8-UNIT APARTMENT W/ 1-LEVEL SUBTERRANEAN PARKING.
- Permit Issued
- Issued on 10/15/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2018 | APPLICANT |
| Green Plans Picked Up | 4/10/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 4/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2018 | HERNAN ARREOLA |
| Building Plans Picked Up | 5/17/2018 | APPLICANT |
| Corrections Issued | 7/3/2018 | HERNAN ARREOLA |
| Quality Review Completed | 7/5/2018 | MINYE PAK |
| Applicant returned to address corrections | 10/3/2018 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/24/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/6/2019 | HERNAN ARREOLA |
| Plan Check Approved | 8/30/2019 | HERNAN ARREOLA |
| Issued | 10/15/2019 | LADBS |
| CofO in Progress | 2/15/2023 | DERRICK SPENCER |
| CofO in Progress | 2/28/2023 | DERRICK SPENCER |
| Permit Finaled | 3/3/2023 | DAVID TSAU |
| CofO Issued | 3/3/2023 | DAVID TSAU |
| Permit Finaled | 3/3/2023 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/21/2018 | SEAN VEAL |
| Address approval | Cleared | 6/26/2018 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 8/3/2018 | ADRIAN SANCHEZ |
| Highway dedication | Cleared | 8/9/2018 | CHRISTOPHER LAW |
| Specific Plan | Cleared | 8/28/2018 | EDER ROMERO |
| Building over 3-story or 36-ft | Cleared | 9/7/2018 | CALOSHA APPROVED |
| Green Code | Cleared | 9/27/2018 | NEGAR NEJAD |
| Hydrant and Access approval | Cleared | 10/5/2018 | JOHN CONNEALLY |
| Work Adjacent to Public Way | Cleared | 1/23/2019 | BOK GOH |
| DAS Clearance | Cleared | 1/29/2019 | ELIZABETH TOMS |
| Construction near power lines | Cleared | 4/3/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/23/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/14/2019 | ELENA LOPEZ |
| Fire Marshall Fire Life Safety | Cleared | 5/22/2019 | PEJMAN NOORI |
| Excavation more than 5-ft deep | Cleared | 5/24/2019 | CALOSHA APPROVED |
| Opn space landscape/Water mgmt | Cleared | 8/6/2019 | DIANA JIMENEZ |
Contact Information
| Architect | Vanos, Vincent Jay; Lic. No.: C22269 | 1733 S LA CIENEGA BLVD LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Park, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD LOS ANGELES, CA 90010 |
| Engineer | Sahebi,, Mo; Lic. No.: C33508 | 1330 OLYMPIC BL SANTA MONICA, CA 90404 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2019 | Partial Approval | JEFF BYTHEWAY |
| METHANE-Barrier | 12/20/2019 | Partial Approval | JEFF BYTHEWAY |
| METHANE-Subgrade | 12/20/2019 | Partial Approval | JEFF BYTHEWAY |
| METHANE-Barrier | 1/6/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Subgrade | 1/6/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 1/6/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Deputy Shotcrete | 1/7/2020 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 1/7/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Rough | 1/7/2020 | Partial Approval | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 1/7/2020 | Partial Approval | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 1/7/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Deputy Shotcrete | 1/9/2020 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 1/14/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Barrier | 1/14/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Subgrade | 1/14/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Rough | 1/15/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Rough | 1/15/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 1/15/2020 | Partial Approval | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 1/15/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Barrier | 1/23/2020 | Approved | JEFF BYTHEWAY |
| METHANE-Subgrade | 1/23/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Reinforced Masonry Frame | 1/23/2020 | Partial Inspection | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 1/27/2020 | Partial Approval | JEFF BYTHEWAY |
| METHANE-Subgrade | 1/27/2020 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 2/4/2020 | Partial Approval | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 2/7/2020 | Partial Approval | JEFF BYTHEWAY |
| Deputy Methane Barrier | 2/14/2020 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | JEFF BYTHEWAY |
| Reinforced Masonry Frame | 2/21/2020 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 3/6/2020 | Partial Approval | TED RIES |
| Deputy Methane Barrier | 4/15/2020 | Approved | JEFF BYTHEWAY |
| Deputy Methane Barrier | 4/16/2020 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 4/17/2020 | Partial Approval | JEFF BYTHEWAY |
| Special/Order Compliance | 5/20/2020 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 6/18/2020 | Approved | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 6/18/2020 | Partial Approval | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 6/19/2020 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 7/7/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| METHANE-Rough | 7/7/2020 | Approved | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 7/7/2020 | Approved | JEFF BYTHEWAY |
| Wood Frame | 7/7/2020 | Partial Inspection | JEFF BYTHEWAY |
| Special/Order Compliance | 7/14/2020 | Corrections Issued | JEFF BYTHEWAY |
| Special/Order Compliance | 7/15/2020 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2020 | Partial Approval | JEFF BYTHEWAY |
| Green Building Rough | 8/3/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Rough | 8/24/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 8/24/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2020 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 9/18/2020 | Not Ready for Inspection | ALAN NOVAK |
| Wood Frame | 9/18/2020 | Not Ready for Inspection | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Partial Approval | SORIN CIRSTOIU |
| Green Building Rough | 9/25/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 9/25/2020 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 10/19/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 10/19/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Pre-Inspection | 10/30/2020 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 11/4/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 11/4/2020 | Partial Approval | JEFF BYTHEWAY |
| Green Building Rough | 12/4/2020 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 12/4/2020 | Partial Approval | SORIN CIRSTOIU |
| Green Building Rough | 1/8/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 1/8/2021 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 2/3/2021 | Approved | JEFF BYTHEWAY |
| Wood Frame | 2/3/2021 | Partial Inspection | JEFF BYTHEWAY |
| Wood Frame | 2/25/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Deputy Steel/Welding | 2/26/2021 | Approved | JEFF BYTHEWAY |
| Wood Frame | 3/1/2021 | Partial Approval | JEFF BYTHEWAY |
| Wood Frame | 3/3/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 3/9/2021 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 3/17/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 3/19/2021 | Partial Approval | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 3/31/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 4/5/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 4/12/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 4/14/2021 | Partial Approval | JEFF BYTHEWAY |
| Wood Frame | 4/28/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 5/4/2021 | Partial Approval | JEFF BYTHEWAY |
| Insulation | 5/6/2021 | Partial Approval | JEFF BYTHEWAY |
| Insulation | 5/12/2021 | Partial Approval | JEFF BYTHEWAY |
| Wood Frame | 5/14/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 5/25/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Insulation | 5/26/2021 | Partial Approval | JEFF BYTHEWAY |
| Masonry Wall/Backfill | 6/3/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 6/16/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 9/7/2021 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 9/14/2021 | Partial Inspection | JEFF BYTHEWAY |
| Drywall Nailing | 9/29/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 1/25/2022 | Partial Inspection | JEFF BYTHEWAY |
| Drywall Nailing | 2/2/2022 | Partial Approval | JEFF BYTHEWAY |
| Light Gage Steel Frame | 3/29/2022 | Partial Inspection | JEFF BYTHEWAY |
| Drywall Nailing | 9/27/2022 | Approved | NICK LAROCCA |
| Final | 9/27/2022 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 9/27/2022 | Approved | NICK LAROCCA |
| Green Building Final | 9/27/2022 | Approved | NICK LAROCCA |
| Reinforced Masonry Frame | 9/27/2022 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 9/27/2022 | Approved | NICK LAROCCA |
| Structural Steel Frame | 9/27/2022 | Approved | NICK LAROCCA |
| Wood Frame | 9/27/2022 | Approved | NICK LAROCCA |
| Final | 10/7/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 11/4/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 11/15/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 11/17/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/9/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/18/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/20/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/26/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 2/8/2023 | OK to Issue CofO | DERRICK SPENCER |
| Final | 2/15/2023 | OK to Issue CofO | DERRICK SPENCER |