2840 E LUGO ST 90023

Certificate Information: 2840 E LUGO ST 90023

Application / Permit
18010-10000-01412
Plan Check / Job No.
B18LA06261
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
1 STORY WAREHOUSE AND OFFICE BLDG. W/ MEZZANINE
Permit Issued
Issued on 10/12/2021
Issuing Office
Metro
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2018 APPLICANT
Application Withdrawn 4/2/2018 APPLICANT
Re-Activate Applicaton 4/2/2018 APPLICANT
Disabled Access Plans Picked Up 4/13/2018 APPLICANT
Green Plans Picked Up 4/13/2018 APPLICANT
Assigned to Plan Check Engineer 4/19/2018 HERNAN ARREOLA
Corrections Issued 4/26/2018 HERNAN ARREOLA
Quality Review Completed 5/11/2018 HERNAN ARREOLA
Building Plans Picked Up 5/14/2018 APPLICANT
Applicant returned to address corrections 1/9/2020 HERNAN ARREOLA
Applicant returned to address corrections 2/4/2020 HERNAN ARREOLA
Applicant returned to address corrections 6/11/2020 HERNAN ARREOLA
Plan Check Approved 9/30/2021 HERNAN ARREOLA
Issued 10/12/2021 APPLICANT
TCO Issued (Expire Date: 12-23-2023) 6/26/2023 TED RIES
TCO Issued (Expire Date: 06-08-2024) 12/11/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 12-02-2024) 6/5/2024 RAFAEL ESPINOZA
TCO Issued (Expire Date: 05-25-2025) 11/26/2024 ADAM BURGESS
CofO in Progress 12/10/2024 RAFAEL ESPINOZA
CofO Issued 12/10/2024 RAFAEL ESPINOZA
Permit Finaled 12/10/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Project located in CRA area Cleared 10/15/2019 JIM URQUHART
Address approval Cleared 11/7/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/7/2019 CELINA MORENO
Hydrant and Access approval Cleared 11/8/2019 ROBERT DUFF
Comm Cor/Mini-Mall Cleared 12/5/2019 JOE LUCKEY
Prkng lot landscape/Water mgmt Cleared 12/5/2019 JOE LUCKEY
ZI Cleared 12/5/2019 JOE LUCKEY
Green Code Cleared 12/17/2019 COLIN LOREDO
Low Impact Development Cleared 1/7/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/7/2020 JEANIE LAM
Sewer availability Cleared 1/16/2020 ELENA LOPEZ
DAS Clearance Cleared 1/30/2020 CHOI YAN
Work Adjacent to Public Way Cleared 4/16/2020 BOK GOH
Highway dedication Cleared 4/17/2020 RENZ SORIANO
Building over 3-story or 36-ft Cleared 6/17/2020 CALOSHA APPROVED
Permit Cleared 9/8/2021 MATIAS FARFAN

Contact Information

Architect Coatsworth, Calvin John; Lic. No.: C14388 2495 CAMPUS DRIVE SECOND FLOOR      IRVINE, CA 92612
Contractor Anvil Construction Company Inc; Lic. No.: 998987-B 8895 RESEARCH DRIVE      IRVINE, CA 92618
Engineer Bushra, Rafeek L; Lic. No.: S4490 2564 W WOODLAND DR      ANAHEIM, CA 92801

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2021 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/20/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 10/20/2021 Partial Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 10/29/2021 Partial Approval DANIEL COLLINS
Green Building Rough 10/29/2021 Approved DANIEL COLLINS
Reinforced Concrete Frame 10/29/2021 Partial Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 11/5/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 11/5/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/17/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/19/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 11/19/2021 Not Ready for Inspection DANIEL COLLINS
Footing/Foundation/Slab 11/19/2021 Not Ready for Inspection DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 11/23/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 11/23/2021 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/21/2021 Partial Approval TED RIES
Reinforced Concrete Frame 12/21/2021 Partial Approval TED RIES
Verify Sprinkler Sign Off 12/21/2021 Not Ready for Inspection TED RIES
Excavation/Setback/Form/Re-Bar 1/7/2022 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 1/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 1/12/2022 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 1/26/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 1/27/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/1/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/11/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/16/2022 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/17/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/17/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/18/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 2/18/2022 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/3/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 3/4/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/4/2022 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/8/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/11/2022 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 3/11/2022 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/14/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/15/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/18/2022 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 3/21/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/25/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/25/2022 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 3/25/2022 Partial Inspection ERNESTO CORRAL
Deputy Steel/Welding 3/31/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/1/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/7/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/15/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/29/2022 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/11/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/17/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/17/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/1/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 7/1/2022 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 7/14/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/18/2022 Conditional Approval WINSTON DUNNING
Special/Order Compliance 7/22/2022 Approved RAFAEL ESPINOZA
T-Bar Ceiling 7/28/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/9/2022 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 8/9/2022 Partial Approval TED RIES
Light Gage Steel Frame 8/9/2022 Partial Inspection TED RIES
T-Bar Ceiling 8/9/2022 Approved TED RIES
Deputy Steel/Welding 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 8/23/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 8/24/2022 Conditional Approval WINSTON DUNNING
Light Gage Steel Frame 8/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/9/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/12/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/14/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/5/2022 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/1/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 12/20/2022 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 1/11/2023 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 1/17/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 1/25/2023 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 1/25/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved RAFAEL ESPINOZA
Green Building Final 1/31/2023 Partial Inspection RAFAEL ESPINOZA
Smoke Detectors 1/31/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/31/2023 Approved RAFAEL ESPINOZA
Drywall Nailing 2/3/2023 Approved RAFAEL ESPINOZA
Final 2/3/2023 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 2/3/2023 Approved RAFAEL ESPINOZA
Green Building Final 2/3/2023 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 2/3/2023 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 2/3/2023 Approved RAFAEL ESPINOZA
Special/Order Compliance 11/28/2023 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/10/2024 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 11/6/2024 Partial Inspection RAFAEL ESPINOZA
Final 12/10/2024 OK to Issue CofO RAFAEL ESPINOZA