443 N MOUNTAIN VIEW AVE 90026
Certificate Information: 443 N MOUNTAIN VIEW AVE 90026
- Application / Permit
- 18010-10000-01323
- Plan Check / Job No.
- B18LA05862
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY, 26' X 48', TYPE VB, R3-OCC SINGLE FAMILY DWELLING. NFPA-13D FIRE SPRINKLERS TO BE UNDER SEPARATE PERMIT.
- Permit Issued
- Issued on 11/20/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2018 | APPLICANT |
| Green Plans Picked Up | 4/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2018 | JOHNNY WU |
| Corrections Issued | 5/14/2018 | DEVIN GORDON |
| Quality Review Completed | 5/21/2018 | KESETE HAREGOT |
| Building Plans Picked Up | 5/22/2018 | APPLICANT |
| Applicant returned to address corrections | 9/18/2019 | JOHNNY WU |
| Applicant returned to address corrections | 9/20/2019 | JOHNNY WU |
| Applicant returned to address corrections | 10/29/2019 | JOHNNY WU |
| Plan Check Approved | 11/20/2019 | JOHNNY WU |
| Issued | 11/20/2019 | LADBS |
| CofO in Progress | 1/13/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2019 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 8/28/2019 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 8/28/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 8/28/2019 | JEANETTE VONG |
| ZI | Cleared | 8/28/2019 | RICHARD REASER |
| Construction near power lines | Cleared | 8/29/2019 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 8/29/2019 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 8/29/2019 | JORGE MEJIA LEMUS |
| Permit | Cleared | 9/4/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 9/4/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/10/2019 | KHEDER ALRAZAA |
| GPI Written Notices | Cleared | 11/20/2019 | DEVIN GORDON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2020 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 9/16/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/16/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/23/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Barrier | 11/23/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 11/23/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 11/25/2020 | Corrections Issued | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/4/2020 | Approved | ROBERT VORHIS |
| METHANE-Barrier | 12/4/2020 | Approved | ROBERT VORHIS |
| METHANE-Subgrade | 12/4/2020 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/16/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 12/16/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2021 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 2/9/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 2/18/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Corrections Issued | ROBERT VORHIS |
| HVAC-Rough | 2/18/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | ROBERT VORHIS |
| HVAC-Rough | 3/4/2021 | Approved | ROBERT VORHIS |
| MERV13>=Rough | 3/4/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 3/4/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Deputy Wood Construction | 3/9/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 3/11/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Rough | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Interior/Exterior Lathing | 3/22/2021 | Partial Approval | ROBERT VORHIS |
| Wood Frame | 3/22/2021 | Partial Approval | ROBERT VORHIS |
| BUILDING-Rough-Frame | 3/31/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 3/31/2021 | Approved | ROBERT VORHIS |
| Insulation | 3/31/2021 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Rough | 3/31/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 3/31/2021 | Approved | ROBERT VORHIS |
| Insulation | 4/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 4/20/2021 | Approved | ROBERT VORHIS |
| Shower Pan | 5/7/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 6/29/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/9/2021 | Partial Approval | SCOTT FINNILA |
| Sewer | 7/9/2021 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/28/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Not Ready for Inspection | RONALD MYRICK |
| Special/Order Compliance | 10/5/2021 | Partial Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 10/5/2021 | Partial Inspection | ADAM ESCOTO |
| Special/Order Compliance | 10/5/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 10/5/2021 | Partial Inspection | LILIANA PORTILLO |
| Masonry Wall/Backfill | 10/18/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Final | 10/28/2021 | Corrections Issued | ROBERT VORHIS |
| ELECTRICAL-Final | 11/2/2021 | Approved | ROBERT VORHIS |
| HVAC-Final | 11/2/2021 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Final | 11/2/2021 | Approved | ROBERT VORHIS |
| Final | 11/9/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Final | 11/9/2021 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Final | 11/9/2021 | Approved | ROBERT VORHIS |
| MERV13>=Final | 11/9/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | ROBERT VORHIS |
| Service/Power Release | 11/9/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Smoke Detectors | 11/9/2021 | Approved | ROBERT VORHIS |
| Final | 11/22/2021 | Corrections Issued | ROBERT VORHIS |
| Green Building Final | 11/22/2021 | Approved | ROBERT VORHIS |
| Service/Power Release | 11/22/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 12/22/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/22/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/22/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 1/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/7/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Gas Test | 1/7/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 1/7/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 1/7/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/12/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |