1923 1/2 E PENNSYLVANIA AVE 90033
Certificate Information: 1923 1/2 E PENNSYLVANIA AVE 90033
- Application / Permit
- 18010-10000-01290
- Plan Check / Job No.
- B18LA05668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ONE STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 9/17/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2018 | GEORGE ALVAREZ |
| Green Plans Picked Up | 5/9/2018 | APPLICANT |
| Corrections Issued | 5/16/2018 | GEORGE ALVAREZ |
| Quality Review Completed | 5/18/2018 | TIEN JEN WANG |
| Building Plans Picked Up | 5/23/2018 | APPLICANT |
| Plan Check Approved | 8/6/2018 | GEORGE ALVAREZ |
| Issued | 9/17/2018 | LADBS |
| CofO in Progress | 3/6/2026 | FREDDIE RIVERA |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
| CofO Issued | 3/7/2026 | DEROLD HAUFF |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/23/2018 | BARTON HOLMES |
| Miscellaneous | Cleared | 5/23/2018 | IVORY CHAMBESHI |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2018 | NAZILA NOORIFAR |
| Low Impact Development | Cleared | 7/19/2018 | MATTHEW JIMENEZ |
| Roof/Waste drainage to street | Cleared | 7/19/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 7/19/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 9/17/2018 | SARAH ABOULHOSN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh, Jasbir; Lic. No.: C38767 | 15095 CALLE DEL ORO CHINO HILLS, CA 91709 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/2/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/2/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/2/2023 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 5/2/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 5/2/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/2/2023 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 5/2/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/27/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/26/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/26/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/7/2023 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 3/13/2025 | Approved | FREDDIE RIVERA |
| Final | 3/13/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/13/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 3/13/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 3/13/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/13/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 3/13/2025 | Approved | FREDDIE RIVERA |
| Structural Steel Frame | 3/13/2025 | Approved | FREDDIE RIVERA |
| Final | 8/18/2025 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 8/18/2025 | Partial Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 8/18/2025 | Partial Inspection | OSVALDO PARAMO |
| Final | 3/4/2026 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 3/4/2026 | Approved | FREDDIE RIVERA |