5933 N MONTEREY ROAD 90042

Certificate Information: 5933 N MONTEREY ROAD 90042

Application / Permit
18010-10000-01253
Plan Check / Job No.
B18LA05459
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
3-STORY 13-UNIT APARTMENT BUILDING WITH GROUND FLOOR RETAIL AND PARKING. **1 OF 2**
Permit Issued
Issued on 11/27/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2018 APPLICANT
Disabled Access Plans Picked Up 4/24/2018 APPLICANT
Assigned to Plan Check Engineer 5/2/2018 DINA ELKINAWY
Green Plans Picked Up 5/14/2018 APPLICANT
Corrections Issued 5/15/2018 DINA ELKINAWY
Quality Review Completed 5/15/2018 DAVID CHANG
Building Plans Picked Up 5/18/2018 APPLICANT
Applicant returned to address corrections 7/10/2018 DINA ELKINAWY
Applicant returned to address corrections 9/20/2018 DINA ELKINAWY
Applicant returned to address corrections 10/30/2018 DINA ELKINAWY
Applicant returned to address corrections 10/31/2018 DINA ELKINAWY
Plan Check Approved 11/27/2018 DINA ELKINAWY
Issued 11/27/2018 LADBS
CofO in Progress 2/18/2021 RAFAEL ESPINOZA
Permit Finaled 2/19/2021 DAVID TSAU
CofO Issued 2/19/2021 DAVID TSAU
Permit Finaled 2/19/2021 DAVID TSAU

Permit Application Clearance Information

DAS Clearance Cleared 7/2/2018 SHINE LIN
Address approval Cleared 8/2/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/2/2018 STEVE MELGAR
Permit Cleared 8/2/2018 STEVE MELGAR
Sewer availability Cleared 8/2/2018 STEVE MELGAR
Building over 3-story or 36-ft Cleared 9/20/2018 CALOSHA APPROVED
Hydrant and Access approval Cleared 10/12/2018 GEORGE SUCHAND
Hydrant and Access approval Cleared 10/26/2018 GEORGE SUCHAND
Opn space landscape/Water mgmt Cleared 11/5/2018 MOTOUMI SASAKI
Opn space landscape/Water mgmt Cleared 11/5/2018 MOTOUMI SASAKI
Prkng lot landscape/Water mgmt Cleared 11/5/2018 MOTOUMI SASAKI
Prkng lot landscape/Water mgmt Cleared 11/5/2018 MOTOUMI SASAKI
Green Code Cleared 11/6/2018 SARAH ABOULHOSN
Low Impact Development Cleared 11/14/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/14/2018 STEVE MELGAR
Fire Marshall Fire Life Safety Cleared 11/15/2018 WILLIAM JOHNS

Contact Information

Architect Techentin, Warren A; Lic. No.: C28100 2066 N EDGEMONT STREET      LOS ANGELES, CA 90027
Contractor 4site Construction; Lic. No.: 971233-B 1619 W TEMPLE ST      LOS ANGELES, CA 90026
Engineer , ; Lic. No.: C84086 1730 E HOLLY AVE   STE 107    EL SEGUNDO, CA
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/28/2018 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 1/29/2019 Conditional Approval ERNESTO CORRAL
Piling/Pier/Caisson 1/29/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/30/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/30/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/26/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 2/26/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/27/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 2/27/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/28/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/1/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/1/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/14/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/22/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 4/1/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/3/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 4/9/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/10/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 4/18/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/19/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 5/28/2019 Corrections Issued ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 5/31/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/21/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/24/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 8/2/2019 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 9/27/2019 Approved ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/23/2020 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Inspection ERNESTO CORRAL
Green Building Rough 2/3/2020 Approved ERNESTO CORRAL
Verify Sprinkler Sign Off 2/3/2020 Approved ERNESTO CORRAL
Wood Frame 2/3/2020 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 2/18/2020 Partial Inspection ERNESTO CORRAL
Interior/Exterior Lathing 2/26/2020 Partial Inspection ERNESTO CORRAL
Insulation 3/6/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/6/2020 Partial Inspection ERNESTO CORRAL
Insulation 3/9/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/17/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 3/18/2020 Partial Approval DANIEL COLLINS
Insulation 3/18/2020 Partial Approval DANIEL COLLINS
Insulation 3/25/2020 Not Ready for Inspection RONALD PACHECO
Insulation 3/31/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 4/15/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/15/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/15/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/29/2020 Approved RAFAEL ESPINOZA
Insulation 6/4/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/4/2020 Approved RAFAEL ESPINOZA
Masonry Wall/Backfill 7/6/2020 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 7/6/2020 Partial Inspection RAFAEL ESPINOZA
Insulation 7/14/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/17/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/5/2020 Corrections Issued RAFAEL ESPINOZA
Special/Order Compliance 10/8/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/7/2021 Approved RAFAEL ESPINOZA
Final 1/7/2021 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 1/7/2021 Approved RAFAEL ESPINOZA
Green Building Final 1/7/2021 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 1/7/2021 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/7/2021 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 1/7/2021 Approved RAFAEL ESPINOZA
Wood Frame 1/7/2021 Approved RAFAEL ESPINOZA
Final 1/27/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 1/28/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/3/2021 Corrections Issued RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/12/2021 Approved RAFAEL ESPINOZA
Final 2/16/2021 Conditional Approval RAFAEL ESPINOZA