951 N WILCOX AVE 90038

Certificate Information: 951 N WILCOX AVE 90038

Application / Permit
18010-10000-01243
Plan Check / Job No.
B18LA05425
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
5 lot small lot subdivision. Lot 5 - plan type A3
Permit Issued
Issued on 1/28/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 4/18/2018 VLADIMIR ARUTYUNYAN
Quality Review Completed 4/25/2018 STEVEN KIM
Building Plans Picked Up 4/26/2018 APPLICANT
Green Plans Picked Up 6/22/2018 APPLICANT
Plan Check Approved 1/28/2019 VLADIMIR ARUTYUNYAN
Issued 1/28/2019 LADBS
CofO in Progress 11/20/2020 SCOTT FINNILA
Permit Finaled 11/20/2020 DEROLD HAUFF
CofO Issued 11/20/2020 DEROLD HAUFF
Permit Finaled 11/20/2020 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 7/3/2018 COLIN LOREDO
Address approval Cleared 7/30/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/30/2018 STEVE MELGAR
Permit Cleared 7/30/2018 STEVE MELGAR
Hydrant and Access approval Cleared 9/12/2018 GEORGE SUCHAND
Low Impact Development Cleared 10/5/2018 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 10/9/2018 STEVE MELGAR
Sewer availability Cleared 10/9/2018 STEVE MELGAR
Highway dedication Cleared 10/10/2018 ADRIAN SANCHEZ
Miscellaneous Cleared 10/12/2018 DANIEL KOZUBAL
Miscellaneous Cleared 1/17/2019 HERMINIGILDO AGUSTIN

Contact Information

Contractor Carteng Construction Corporation; Lic. No.: 1032972-B 970 MISSION TERRACE      CAMARILLO, CA 93010
Engineer Fischer, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/18/2019 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 4/18/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/18/2019 Partial Approval SCOTT FINNILA
METHANE-Barrier 4/18/2019 Not Ready for Inspection SCOTT FINNILA
METHANE-Subgrade 4/18/2019 Not Ready for Inspection SCOTT FINNILA
Deputy Reinf. Concrete 4/30/2019 Approved LUIS BARRALES
PLUMBING-Rough 5/1/2019 Not Ready for Inspection LUIS BARRALES
Footing/Foundation/Slab 5/8/2019 Approved SCOTT FINNILA
METHANE-Barrier 5/8/2019 Approved SCOTT FINNILA
METHANE-Rough 5/8/2019 Approved SCOTT FINNILA
METHANE-Subgrade 5/8/2019 Approved SCOTT FINNILA
METHANE-Barrier 5/9/2019 Approved SCOTT FINNILA
METHANE-Subgrade 5/9/2019 Approved SCOTT FINNILA
Deputy Steel/Welding 5/16/2019 Approved LUIS BARRALES
BUILDING-Rough-Frame 5/30/2019 Not Ready for Inspection LUIS BARRALES
Green Building Rough 5/30/2019 Not Ready for Inspection LUIS BARRALES
Verify Sprinkler Sign Off 5/30/2019 Not Ready for Inspection LUIS BARRALES
Floor/Roof Diaphrgm/Shear Wall 5/31/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 6/3/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/19/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 6/25/2019 Partial Approval SCOTT FINNILA
Deputy Wood Construction 7/3/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/8/2019 Partial Approval SCOTT FINNILA
Deputy Wood Construction 7/17/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 7/18/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/18/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 7/25/2019 Partial Approval SCOTT FINNILA
Green Building Rough 7/25/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/6/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/16/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 8/22/2019 Partial Approval SCOTT FINNILA
Green Building Rough 8/22/2019 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 8/22/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 9/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/18/2019 Partial Approval SCOTT FINNILA
Deck 9/23/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/23/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/1/2019 Partial Approval SCOTT FINNILA
Green Building Rough 10/1/2019 Partial Inspection SCOTT FINNILA
Pre-Inspection 10/1/2019 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 10/1/2019 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 10/25/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 11/1/2019 Partial Approval SCOTT FINNILA
Green Building Rough 11/1/2019 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 11/1/2019 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 11/13/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 11/21/2019 Partial Approval SCOTT FINNILA
Green Building Rough 11/21/2019 Partial Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 11/21/2019 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 11/22/2019 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 11/27/2019 Partial Inspection SCOTT FINNILA
Green Building Rough 11/27/2019 Corrections Issued SCOTT FINNILA
Rough-Elec/Plmb/HVAC 11/27/2019 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 11/27/2019 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 12/3/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 12/18/2019 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 12/18/2019 Corrections Issued SCOTT FINNILA
Green Building Rough 12/18/2019 Approved SCOTT FINNILA
HVAC-Rough 12/18/2019 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 12/18/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 12/20/2019 Conditional Approval SCOTT FINNILA
Green Building Rough 12/20/2019 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 12/20/2019 Partial Approval SCOTT FINNILA
Insulation 12/31/2019 Conditional Approval SCOTT FINNILA
Shower Pan 1/13/2020 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/23/2020 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 1/24/2020 Approved SCOTT FINNILA
Underground Mechanical 5/7/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 5/26/2020 Corrections Issued SCOTT FINNILA
Gas Test 6/10/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 6/10/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 6/25/2020 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 7/7/2020 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 7/8/2020 Approved SCOTT FINNILA
Final 7/8/2020 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 7/9/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 10/27/2020 Corrections Issued SCOTT FINNILA
Green Building Final 10/30/2020 Approved SCOTT FINNILA
Final 11/5/2020 Partial Inspection SCOTT FINNILA
PLUMBING-Final 11/5/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 11/5/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 11/5/2020 Partial Inspection SCOTT FINNILA
Smoke Detectors 11/5/2020 Approved SCOTT FINNILA
Service/Power Release 11/19/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 11/20/2020 Approved SCOTT FINNILA
Final 11/20/2020 OK to Issue CofO SCOTT FINNILA
HVAC-Final 11/20/2020 Approved SCOTT FINNILA