1440 N CURSON AVE 90046

Certificate Information: 1440 N CURSON AVE 90046

Application / Permit
18010-10000-01204
Plan Check / Job No.
B18LA05257
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Lot 2:New 4 story, Type VB, single family dwelling with attached 2-car garage, NFPA-13R throughout. Small lot subdivision pursuant to Tentative Tract Map No.: VTT-74736-SL. A certificate of occupancy (Temporary or Final) shall not be issued until after the final map has been recorded.
Permit Issued
Issued on 10/12/2018
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2018 APPLICANT
Green Plans Picked Up 3/29/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 KESETE HAREGOT
Corrections Issued 4/21/2018 KESETE HAREGOT
Building Plans Picked Up 5/1/2018 APPLICANT
Quality Review Completed 5/2/2018 SIAVOSH POURSABAHIAN
Applicant returned to address corrections 5/21/2018 KESETE HAREGOT
Applicant returned to address corrections 6/22/2018 KESETE HAREGOT
Plan Check Approved 10/12/2018 KESETE HAREGOT
Issued 10/12/2018 LADBS
CofO in Progress 9/11/2020 ALEJANDRO DE ARTOLA
Permit Finaled 9/25/2020 DEROLD HAUFF
CofO Issued 9/25/2020 DEROLD HAUFF
Permit Finaled 9/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/12/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/18/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 7/25/2018 ROBERT DUFF
CPC Cleared 8/14/2018 IVORY CHAMBESHI
Frnt yard landscape/Water mgmt Cleared 8/14/2018 IVORY CHAMBESHI
Tract Map conditions Cleared 8/14/2018 IVORY CHAMBESHI
ZA Case Cleared 8/14/2018 IVORY CHAMBESHI
Green Code Cleared 8/17/2018 KESETE HAREGOT
Green Code Cleared 8/17/2018 KESETE HAREGOT
Green Code Cleared 8/17/2018 NEGAR NEJAD
Building over 3-story or 36-ft Cleared 8/22/2018 CALOSHA APPROVED
Low Impact Development Cleared 9/12/2018 MITESH PATEL
Highway dedication Cleared 9/21/2018 DANIEL KOZUBAL
Miscellaneous Cleared 9/21/2018 DANIEL KOZUBAL
Permit Cleared 9/21/2018 DANIEL KOZUBAL
Roof/Waste drainage to street Cleared 9/21/2018 DANIEL KOZUBAL
Sewer availability Cleared 9/21/2018 NAZILA NOORIFAR

Contact Information

Contractor Raimondo Construction Company; Lic. No.: 683445-B 919 MYRTLE AVE      GLENDORA, CA 91741
Engineer , ; Lic. No.: C58650       WOODLAND HILLS, CA 91364
Engineer , ; Lic. No.: S2392 WESTLAKE VILLAGE      , CA 91362
Geologist , ; Lic. No.: EG1691       ALTADENA, CA 91001
Geologist , ; Lic. No.: GEO5361       ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/20/2018 Corrections Issued RAUL BARAJAS
Underground Mechanical 11/27/2018 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/27/2018 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/10/2019 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/20/2019 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 2/22/2019 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/28/2019 Partial Approval ALEJANDRO DE ARTOLA
Structural Steel Frame 2/28/2019 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/12/2019 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/13/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/22/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/24/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/24/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/3/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/6/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 6/10/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 6/10/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/14/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/18/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/18/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 6/20/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 6/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/21/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/1/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/11/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/11/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 7/11/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Gas Test 7/19/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/19/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/23/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 7/23/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/26/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/26/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/30/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 8/6/2019 Partial Approval ALEJANDRO DE ARTOLA
Gas Test 8/14/2019 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/21/2019 Conditional Approval ALEJANDRO DE ARTOLA
HVAC-Rough 8/22/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/23/2019 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 8/28/2019 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 9/5/2019 Approved ALEJANDRO DE ARTOLA
Insulation 9/5/2019 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/26/2019 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/26/2019 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/26/2019 Partial Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/26/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/3/2019 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/3/2019 Approved ALEJANDRO DE ARTOLA
Insulation 10/7/2019 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/22/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/23/2019 Approved ALEJANDRO DE ARTOLA
Shower Pan 12/16/2019 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/17/2019 Partial Approval SCOTT FINNILA
Shower Pan 12/17/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 1/8/2020 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/24/2020 Partial Approval ALEJANDRO DE ARTOLA
Sewer 2/18/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 2/18/2020 Approved ALEJANDRO DE ARTOLA
Gas Test 4/1/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/11/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/28/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/9/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/9/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/10/2020 Approved ALEJANDRO DE ARTOLA
Green Building Final 6/11/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 6/24/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/29/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 7/2/2020 Approved ALEJANDRO DE ARTOLA
Final 7/8/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/8/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/8/2020 Approved ALEJANDRO DE ARTOLA
Reinforced Masonry Frame 7/8/2020 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/8/2020 Approved ALEJANDRO DE ARTOLA
Structural Steel Frame 7/8/2020 Approved ALEJANDRO DE ARTOLA
Final 7/15/2020 Conditional Approval ALEJANDRO DE ARTOLA
Final 9/10/2020 OK to Issue CofO ALEJANDRO DE ARTOLA