1800 S WESTERN AVE 90006

Certificate Information: 1800 S WESTERN AVE 90006

Application / Permit
18010-10000-01173
Plan Check / Job No.
B18LA05068
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW 20' X 20' TRASH ENCLOSURE W/ RECYCLING ROOM.
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
Permit Finaled on 1/10/2022

Permit Application Status History

Submitted 3/16/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 JOE VO
Corrections Issued 4/17/2018 JOE VO
Quality Review Completed 4/17/2018 LAWRENCE QUIRANTE
Building Plans Picked Up 4/23/2018 APPLICANT
Disabled Access Plans Picked Up 4/23/2018 APPLICANT
Applicant returned to address corrections 8/9/2018 JOE VO
Applicant returned to address corrections 7/20/2020 JOE VO
Green Plans Picked Up 3/22/2021 APPLICANT
Applicant returned to address corrections 4/13/2021 JOE VO
Plan Check Approved 4/14/2021 JOE VO
Issued 4/26/2021 APPLICANT
Permit Finaled 11/23/2021 SORIN CIRSTOIU

Permit Application Clearance Information

Green Code Cleared 8/6/2018 COLIN LOREDO
DAS Clearance Cleared 8/24/2018 EDDIE GARIN

Contact Information

Contractor C C K Builders Inc; Lic. No.: 855822-B 625 WEST KATELLA AVENUE #2      ORANGE, CA 92867

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/30/2021 Conditional Approval LEOPOLDO MENDOZA
METHANE-Barrier 7/30/2021 Approved LEOPOLDO MENDOZA
METHANE-Subgrade 7/30/2021 Approved LEOPOLDO MENDOZA
Reinforced Masonry Frame 8/4/2021 Partial Approval LEOPOLDO MENDOZA
Reinforced Masonry Frame 8/11/2021 Approved LEOPOLDO MENDOZA
Green Building Rough 10/15/2021 Approved JONATHAN QUACH
METHANE-Rough 10/15/2021 Not Ready for Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 10/15/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 10/15/2021 Partial Inspection JONATHAN QUACH
Final 11/2/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/2/2021 Approved JAMES POWERS
Green Building Final 11/2/2021 Approved JAMES POWERS
METHANE-Final 11/2/2021 Approved JAMES POWERS
METHANE-Rough 11/2/2021 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV No Gas JAMES POWERS
Smoke Detectors 11/2/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/2/2021 Approved JAMES POWERS
Wood Frame 11/2/2021 Approved JAMES POWERS
Final 11/23/2021 Permit Finaled SORIN CIRSTOIU
Final 12/21/2021 Not Ready for Inspection NICK DANERI