1800 S WESTERN AVE 90006
Certificate Information: 1800 S WESTERN AVE 90006
- Application / Permit
- 18010-10000-01172
- Plan Check / Job No.
- B18LA05068
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- NEW RESTAURANT WITH DUAL ORDER POINT DRIVE THROUGH LANES AND ENCLOSED PLAY PLACE PER DIR 2017-2075-CCMP.
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 1/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2018 | JOE VO |
| Corrections Issued | 4/17/2018 | JOE VO |
| Quality Review Completed | 4/17/2018 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/23/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 4/23/2018 | APPLICANT |
| Applicant returned to address corrections | 8/9/2018 | JOE VO |
| Applicant returned to address corrections | 7/20/2020 | JOE VO |
| Green Plans Picked Up | 3/22/2021 | APPLICANT |
| Applicant returned to address corrections | 4/13/2021 | JOE VO |
| Plan Check Approved | 4/14/2021 | JOE VO |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 1/28/2022 | NICK DANERI |
| Permit Finaled | 1/28/2022 | ERNESTO CORRAL |
| CofO Issued | 1/28/2022 | ERNESTO CORRAL |
| Permit Finaled | 1/28/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Permit | Cleared | 6/14/2018 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 6/14/2018 | STEVE MELGAR |
| ZA Case | Cleared | 7/12/2018 | BRIAN CARR |
| ZA Case | Cleared | 7/12/2018 | BRIAN CARR |
| ZI | Cleared | 7/12/2018 | BRIAN CARR |
| ZI | Cleared | 7/12/2018 | BRIAN CARR |
| Fire Marshall Fire Life Safety | Cleared | 7/16/2018 | DOMINIQUE MEDINA |
| Hydrant and Access approval | Cleared | 7/24/2018 | GEORGE SUCHAND |
| Green Code | Cleared | 8/6/2018 | COLIN LOREDO |
| Food Service Establishment | Cleared | 9/25/2018 | KENNETH BROWNE |
| Low Impact Development | Cleared | 9/25/2018 | KENNETH BROWNE |
| Driveway location | Cleared | 10/4/2018 | JOHNATHAN YU |
| Driveway location | Cleared | 10/4/2018 | JOHNATHAN YU |
| Internal circulation | Cleared | 10/4/2018 | JOHNATHAN YU |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2018 | JEANETTE VONG |
| HPOZ | Cleared | 1/9/2019 | AMANDA KAINER |
| Highway dedication | Cleared | 1/9/2019 | JAMES MORALEZ |
| Historic monument | Cleared | 1/9/2019 | AMANDA KAINER |
| Sewer availability | Cleared | 1/9/2019 | JAMES MORALEZ |
| "Q" conditions | Cleared | 9/17/2020 | KENTON TRINH |
| Comm Cor/Mini-Mall | Cleared | 11/12/2020 | KENTON TRINH |
| Comm Cor/Mini-Mall | Cleared | 11/12/2020 | KENTON TRINH |
| Prkng lot landscape/Water mgmt | Cleared | 11/12/2020 | KENTON TRINH |
| ZA Case | Cleared | 11/12/2020 | KENTON TRINH |
| Food establishment approval | Cleared | 12/18/2020 | LACDHS APPROVED |
| Miscellaneous | Cleared | 12/18/2020 | JOE VO |
| DAS Clearance | Cleared | 2/26/2021 | EDDIE GARIN |
Contact Information
| Architect | Bickel,, James S; Lic. No.: C20925 | 3600 BIRCH STREET SUITE 120 NEWPORT BEACH, CA 92660 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | 625 WEST KATELLA AVENUE #2 ORANGE, CA 92867 |
| Engineer | Thompson,, Douglas Sevier; Lic. No.: S2578 | 21084 BAKE PARKWAY SUITE 100 LAKE FOREST, CA 92630 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/21/2021 | Conditional Approval | NICK DANERI |
| Pre-Inspection | 5/24/2021 | Corrections Issued | NICK DANERI |
| Reinforced Masonry Frame | 5/24/2021 | Partial Approval | NICK DANERI |
| Wall Anchors | 5/24/2021 | Partial Approval | NICK DANERI |
| Deputy Reinf. Concrete | 6/1/2021 | Conditional Approval | NICK DANERI |
| Deputy Reinf. Concrete | 6/4/2021 | Conditional Approval | NICK DANERI |
| Deputy Drilled-In Anchors | 6/24/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 6/24/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 6/25/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 6/25/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 6/25/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Reinforced Concrete Frame | 6/28/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/7/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Green Building Rough | 7/7/2021 | Approved | LEOPOLDO MENDOZA |
| METHANE-Rough | 7/7/2021 | Approved | LEOPOLDO MENDOZA |
| Verify Sprinkler Sign Off | 7/7/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 7/7/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/9/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/13/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Wood Frame | 7/13/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Insulation | 7/15/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 7/16/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 7/19/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Verify Sprinkler Sign Off | 7/22/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 7/22/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 7/26/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Insulation | 7/26/2021 | Approved | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 7/26/2021 | Partial Approval | LEOPOLDO MENDOZA |
| METHANE-Barrier | 7/26/2021 | Approved | LEOPOLDO MENDOZA |
| METHANE-Subgrade | 7/26/2021 | Approved | LEOPOLDO MENDOZA |
| Drywall Nailing | 7/30/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 8/2/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/3/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Steel/Welding | 8/20/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/20/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Special/Order Compliance | 8/26/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 8/26/2021 | Partial Approval | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 9/8/2021 | Partial Approval | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 9/14/2021 | Approved | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 9/22/2021 | Corrections Issued | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 9/30/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 10/8/2021 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 10/12/2021 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 10/12/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 10/22/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 11/3/2021 | Approved | JAMES POWERS |
| Wood Frame | 11/3/2021 | Approved | JAMES POWERS |
| Final | 1/6/2022 | Not Ready for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 1/6/2022 | Approved | NICK DANERI |
| Green Building Final | 1/6/2022 | Not Ready for Inspection | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 1/6/2022 | SGSOV Approved | NICK DANERI |
| Smoke Detectors | 1/6/2022 | Approved | NICK DANERI |
| Final | 1/28/2022 | OK to Issue CofO | NICK DANERI |
| Green Building Final | 1/28/2022 | Approved | NICK DANERI |