1800 S WESTERN AVE 90006

Certificate Information: 1800 S WESTERN AVE 90006

Application / Permit
18010-10000-01172
Plan Check / Job No.
B18LA05068
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
NEW RESTAURANT WITH DUAL ORDER POINT DRIVE THROUGH LANES AND ENCLOSED PLAY PLACE PER DIR 2017-2075-CCMP.
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
CofO Issued on 1/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 JOE VO
Corrections Issued 4/17/2018 JOE VO
Quality Review Completed 4/17/2018 LAWRENCE QUIRANTE
Building Plans Picked Up 4/23/2018 APPLICANT
Disabled Access Plans Picked Up 4/23/2018 APPLICANT
Applicant returned to address corrections 8/9/2018 JOE VO
Applicant returned to address corrections 7/20/2020 JOE VO
Green Plans Picked Up 3/22/2021 APPLICANT
Applicant returned to address corrections 4/13/2021 JOE VO
Plan Check Approved 4/14/2021 JOE VO
Issued 4/26/2021 APPLICANT
CofO in Progress 1/28/2022 NICK DANERI
Permit Finaled 1/28/2022 ERNESTO CORRAL
CofO Issued 1/28/2022 ERNESTO CORRAL
Permit Finaled 1/28/2022 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 6/14/2018 STEVE MELGAR
Roof/Waste drainage to street Cleared 6/14/2018 STEVE MELGAR
ZA Case Cleared 7/12/2018 BRIAN CARR
ZA Case Cleared 7/12/2018 BRIAN CARR
ZI Cleared 7/12/2018 BRIAN CARR
ZI Cleared 7/12/2018 BRIAN CARR
Fire Marshall Fire Life Safety Cleared 7/16/2018 DOMINIQUE MEDINA
Hydrant and Access approval Cleared 7/24/2018 GEORGE SUCHAND
Green Code Cleared 8/6/2018 COLIN LOREDO
Food Service Establishment Cleared 9/25/2018 KENNETH BROWNE
Low Impact Development Cleared 9/25/2018 KENNETH BROWNE
Driveway location Cleared 10/4/2018 JOHNATHAN YU
Driveway location Cleared 10/4/2018 JOHNATHAN YU
Internal circulation Cleared 10/4/2018 JOHNATHAN YU
Eng Process Fee Ord 176,300 Cleared 10/11/2018 JEANETTE VONG
HPOZ Cleared 1/9/2019 AMANDA KAINER
Highway dedication Cleared 1/9/2019 JAMES MORALEZ
Historic monument Cleared 1/9/2019 AMANDA KAINER
Sewer availability Cleared 1/9/2019 JAMES MORALEZ
"Q" conditions Cleared 9/17/2020 KENTON TRINH
Comm Cor/Mini-Mall Cleared 11/12/2020 KENTON TRINH
Comm Cor/Mini-Mall Cleared 11/12/2020 KENTON TRINH
Prkng lot landscape/Water mgmt Cleared 11/12/2020 KENTON TRINH
ZA Case Cleared 11/12/2020 KENTON TRINH
Food establishment approval Cleared 12/18/2020 LACDHS APPROVED
Miscellaneous Cleared 12/18/2020 JOE VO
DAS Clearance Cleared 2/26/2021 EDDIE GARIN

Contact Information

Architect Bickel,, James S; Lic. No.: C20925 3600 BIRCH STREET SUITE 120      NEWPORT BEACH, CA 92660
Contractor C C K Builders Inc; Lic. No.: 855822-B 625 WEST KATELLA AVENUE #2      ORANGE, CA 92867
Engineer Thompson,, Douglas Sevier; Lic. No.: S2578 21084 BAKE PARKWAY SUITE 100      LAKE FOREST, CA 92630

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/21/2021 Conditional Approval NICK DANERI
Pre-Inspection 5/24/2021 Corrections Issued NICK DANERI
Reinforced Masonry Frame 5/24/2021 Partial Approval NICK DANERI
Wall Anchors 5/24/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/1/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/4/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 6/24/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/24/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 6/25/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 6/25/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/25/2021 Partial Approval LEOPOLDO MENDOZA
Reinforced Concrete Frame 6/28/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/7/2021 Conditional Approval LEOPOLDO MENDOZA
Green Building Rough 7/7/2021 Approved LEOPOLDO MENDOZA
METHANE-Rough 7/7/2021 Approved LEOPOLDO MENDOZA
Verify Sprinkler Sign Off 7/7/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 7/7/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/9/2021 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/13/2021 Conditional Approval LEOPOLDO MENDOZA
Wood Frame 7/13/2021 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval LEOPOLDO MENDOZA
Insulation 7/15/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 7/16/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 7/19/2021 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Partial Approval LEOPOLDO MENDOZA
Verify Sprinkler Sign Off 7/22/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 7/22/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 7/26/2021 Partial Approval LEOPOLDO MENDOZA
Insulation 7/26/2021 Approved LEOPOLDO MENDOZA
Interior/Exterior Lathing 7/26/2021 Partial Approval LEOPOLDO MENDOZA
METHANE-Barrier 7/26/2021 Approved LEOPOLDO MENDOZA
METHANE-Subgrade 7/26/2021 Approved LEOPOLDO MENDOZA
Drywall Nailing 7/30/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 8/2/2021 Conditional Approval LEOPOLDO MENDOZA
Drywall Nailing 8/3/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 8/20/2021 Conditional Approval LEOPOLDO MENDOZA
Drywall Nailing 8/20/2021 Partial Approval LEOPOLDO MENDOZA
Special/Order Compliance 8/26/2021 Partial Inspection LEOPOLDO MENDOZA
T-Bar Ceiling 8/26/2021 Partial Approval LEOPOLDO MENDOZA
T-Bar Ceiling 9/8/2021 Partial Approval LEOPOLDO MENDOZA
T-Bar Ceiling 9/14/2021 Approved LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 9/22/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Footing/Foundation/Slab 9/22/2021 Corrections Issued LEOPOLDO MENDOZA
Footing/Foundation/Slab 9/30/2021 Partial Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 10/8/2021 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 10/12/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/12/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 10/22/2021 Conditional Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/3/2021 Approved JAMES POWERS
Wood Frame 11/3/2021 Approved JAMES POWERS
Final 1/6/2022 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 1/6/2022 Approved NICK DANERI
Green Building Final 1/6/2022 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Approved NICK DANERI
Smoke Detectors 1/6/2022 Approved NICK DANERI
Final 1/28/2022 OK to Issue CofO NICK DANERI
Green Building Final 1/28/2022 Approved NICK DANERI