5801 W PICO BLVD 90019

Certificate Information: 5801 W PICO BLVD 90019

Application / Permit
18010-10000-01153
Plan Check / Job No.
B18LA04933
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
(N) 5 Story 80 unit apartment over 1 story of commercial and 2 levels of subterranian parking . 8 units set aside for Extremely low income TOC Tier 3
Permit Issued
Issued on 9/11/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2018 APPLICANT
Assigned to Plan Check Engineer 4/26/2018 MINYE PAK
Plans on Hold 4/26/2018 MINYE PAK
Hold Released 5/9/2018 MINYE PAK
Corrections Issued 5/21/2018 HERNAN ARREOLA
Building Plans Picked Up 6/6/2018 APPLICANT
Quality Review Completed 6/11/2018 BILL STUTSMAN
Applicant returned to address corrections 12/13/2018 HERNAN ARREOLA
Applicant returned to address corrections 12/14/2018 HERNAN ARREOLA
Plan Check Approved 9/6/2019 HERNAN ARREOLA
Issued 9/11/2019 LADBS
Permit Closed-Status Void 6/10/2020 LARRY ARNICK
Re-Activate Permit 6/10/2020 LARRY ARNICK
TCO Issued (Expire Date: 12-25-2023) 6/28/2023 TED RIES
CofO in Progress 8/7/2023 EDWIN GREGORYONA
Permit Finaled 8/28/2023 ERNESTO CORRAL
CofO Issued 8/28/2023 ERNESTO CORRAL
Permit Finaled 8/28/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/10/2018 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/10/2018 CELINA MORENO
Highway dedication Cleared 10/23/2018 NAZILA NOORIFAR
Hydrant and Access approval Cleared 11/14/2018 JOHN CONNEALLY
Low Impact Development Cleared 11/28/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/28/2018 KAREN LE
Driveway location Cleared 12/7/2018 TAIMOUR TANAVOLI
Project located in CRA area Cleared 12/12/2018 JIM URQUHART
Project located in CRA area Cleared 12/12/2018 JIM URQUHART
Permit Cleared 2/8/2019 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 2/20/2019 SARAH GOLDMAN
Opn space landscape/Water mgmt Cleared 2/20/2019 SARAH GOLDMAN
ZI Cleared 2/20/2019 SARAH GOLDMAN
ZI Cleared 2/20/2019 SARAH GOLDMAN
Density Bonus 12.22.A.31 Cleared 5/7/2019 KENNETH LE
Construction near power lines Cleared 6/2/2019 RIDWAN HARDY
Fire Marshall Fire Life Safety Cleared 8/23/2019 WILLIAM JOHNS
Encroachment in public way Cleared 8/26/2019 JAMES KHO
Sewer availability Cleared 8/29/2019 CELINA MORENO
Work Adjacent to Public Way Cleared 8/29/2019 BOK GOH
Building over 3-story or 36-ft Cleared 9/6/2019 CALOSHA APPROVED
DAS Clearance Cleared 9/6/2019 HERNAN ARREOLA
Excavation more than 5-ft deep Cleared 9/6/2019 CALOSHA APPROVED

Contact Information

Architect Uriu, Giovanni; Lic. No.: C7487 830 SO GLENDALE AVENUE      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 321 E FAIRVIEW AVE APT 307      GLENDALE, CA 91207

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/14/2019 Partial Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/9/2019 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 4/3/2020 Partial Approval LARRY ARNICK
METHANE-Barrier 4/3/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 4/3/2020 Not Ready for Inspection LARRY ARNICK
Deputy Methane Barrier 4/6/2020 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 4/17/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 4/17/2020 Partial Approval JONATHAN QUACH
METHANE-Barrier 4/17/2020 Not Ready for Inspection JONATHAN QUACH
METHANE-Subgrade 4/17/2020 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 4/20/2020 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 4/22/2020 Partial Approval LARRY ARNICK
METHANE-Barrier 4/22/2020 Partial Approval LARRY ARNICK
METHANE-Subgrade 4/22/2020 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 4/23/2020 Conditional Approval LARRY ARNICK
Deputy Shotcrete 4/23/2020 Conditional Approval LARRY ARNICK
Green Building Rough 4/23/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 4/23/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/23/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/23/2020 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 4/24/2020 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 4/24/2020 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 4/27/2020 Conditional Approval LARRY ARNICK
Deputy Shotcrete 4/29/2020 Conditional Approval LARRY ARNICK
Deputy Shotcrete 5/4/2020 Conditional Approval LARRY ARNICK
Green Building Rough 5/4/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 5/4/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 5/4/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/4/2020 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 5/5/2020 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/5/2020 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 5/6/2020 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 5/7/2020 Conditional Approval LARRY ARNICK
Deputy Shotcrete 5/7/2020 Conditional Approval LARRY ARNICK
Green Building Rough 5/7/2020 Partial Approval LARRY ARNICK
METHANE-Rough 5/7/2020 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 5/7/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/7/2020 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Masonry 5/13/2020 Conditional Approval LARRY ARNICK
Green Building Rough 5/15/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 5/15/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 5/15/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/15/2020 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 5/18/2020 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 6/3/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 6/3/2020 Partial Approval LARRY ARNICK
METHANE-Subgrade 6/3/2020 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 6/10/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 6/10/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 6/10/2020 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 6/19/2020 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 6/19/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 6/19/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 6/19/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/22/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 6/22/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 6/22/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 6/22/2020 Not Ready for Inspection LARRY ARNICK
Deputy Methane Barrier 6/23/2020 Conditional Approval LARRY ARNICK
Deputy Shotcrete 6/26/2020 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 6/26/2020 Partial Approval JONATHAN QUACH
METHANE-Barrier 6/26/2020 Approved JONATHAN QUACH
METHANE-Subgrade 6/26/2020 Approved JONATHAN QUACH
Deputy Methane Barrier 7/14/2020 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/17/2020 Partial Approval LARRY ARNICK
Green Building Rough 8/18/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 8/18/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 8/18/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 8/18/2020 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 8/19/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 8/20/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 8/20/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 8/20/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 8/20/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 8/27/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 8/27/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 8/27/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 8/27/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 8/28/2020 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 9/1/2020 Conditional Approval LARRY ARNICK
Green Building Rough 9/8/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/8/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/8/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 9/8/2020 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Masonry 9/9/2020 Conditional Approval JONATHAN QUACH
Green Building Rough 9/18/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/18/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 9/18/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 9/18/2020 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Masonry 9/22/2020 Conditional Approval LARRY ARNICK
Deputy Reinf. Masonry 9/23/2020 Conditional Approval LARRY ARNICK
Green Building Rough 9/25/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/25/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/25/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 9/25/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 9/29/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/29/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 9/29/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 9/29/2020 Not Ready for Inspection LARRY ARNICK
Deputy Shotcrete 10/1/2020 Conditional Approval LARRY ARNICK
Deputy Shotcrete 10/2/2020 Conditional Approval LARRY ARNICK
Deputy Drilled-In Anchors 10/7/2020 Conditional Approval LARRY ARNICK
Green Building Rough 10/9/2020 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 10/9/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 10/9/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 10/9/2020 Not Ready for Inspection LARRY ARNICK
Green Building Rough 10/16/2020 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 10/16/2020 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 10/16/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 10/16/2020 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 10/20/2020 Conditional Approval LARRY ARNICK
Green Building Rough 11/18/2020 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 11/18/2020 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 11/18/2020 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/18/2020 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 12/4/2020 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 12/4/2020 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 12/4/2020 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/4/2020 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 12/9/2020 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 12/23/2020 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 12/23/2020 Partial Approval LARRY ARNICK
Deputy Wood Construction 1/12/2021 Conditional Approval LARRY ARNICK
Wood Frame 1/12/2021 Partial Approval LARRY ARNICK
Wood Frame 1/15/2021 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Partial Approval LARRY ARNICK
Wood Frame 2/9/2021 Not Ready for Inspection NICK DANERI
Deputy Wood Construction 2/10/2021 Conditional Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 3/1/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/2/2021 Partial Approval EDWIN GREGORYONA
Insulation 3/12/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/16/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 3/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/23/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 3/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/31/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/31/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 3/31/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/20/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/20/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 4/20/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/27/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 4/27/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/28/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/12/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 5/12/2021 Partial Inspection EDWIN GREGORYONA
Deputy Wood Construction 5/13/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 5/17/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/20/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 5/20/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/25/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 5/25/2021 Order to Comply Issued EDWIN GREGORYONA
Wood Frame 6/8/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 6/10/2021 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Approved JONATHAN QUACH
Wood Frame 6/10/2021 Approved JONATHAN QUACH
Drywall Nailing 6/14/2021 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 6/14/2021 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 6/18/2021 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 6/18/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/22/2021 Partial Approval EDWIN GREGORYONA
Insulation 6/22/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/24/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 6/24/2021 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 6/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 6/28/2021 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 7/2/2021 Partial Approval JONATHAN QUACH
Wood Frame 7/2/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 7/8/2021 Partial Approval JONATHAN QUACH
Wood Frame 7/9/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 7/13/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/22/2021 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/26/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/29/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 8/5/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 8/5/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/13/2021 Partial Approval EDWIN GREGORYONA
Insulation 8/13/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/25/2021 Partial Approval EDWIN GREGORYONA
Insulation 8/25/2021 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/31/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 8/31/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/8/2021 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 9/15/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/22/2021 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/22/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/27/2021 Partial Approval EDWIN GREGORYONA
Insulation 10/7/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/18/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/17/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/27/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 2/22/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/28/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/4/2022 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 3/4/2022 Approved EDWIN GREGORYONA
Final 6/28/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 6/28/2022 Approved EDWIN GREGORYONA
Green Building Final 6/28/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 6/28/2022 Approved EDWIN GREGORYONA
METHANE-Final 6/28/2022 Approved EDWIN GREGORYONA
METHANE-Rough 6/28/2022 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 6/28/2022 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 6/28/2022 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 6/28/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/28/2022 Approved EDWIN GREGORYONA
Final 1/13/2023 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 1/13/2023 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 1/13/2023 Not Ready for Inspection EDWIN GREGORYONA
Final 6/16/2023 Partial Inspection EDWIN GREGORYONA
Green Building Final 6/16/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 6/16/2023 Approved EDWIN GREGORYONA
Final 6/26/2023 OK for TCO EDWIN GREGORYONA
Final 8/4/2023 Conditional Approval EDWIN GREGORYONA