2416 S LOUELLA AVE 90291

Certificate Information: 2416 S LOUELLA AVE 90291

Application / Permit
18010-10000-01149
Plan Check / Job No.
B18LA04899
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'-10" X 29' (2)-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ROOFTOP DECK
Permit Issued
Issued on 2/4/2022
Issuing Office
Current Status
Issued on 2/4/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/14/2018 APPLICANT
Green Plans Picked Up 4/2/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 SELLA BENYAMIN
Corrections Issued 4/11/2018 SELLA BENYAMIN
Quality Review Completed 4/13/2018 STEVEN KIM
Building Plans Picked Up 4/24/2018 APPLICANT
Plan Check Approved 9/4/2019 SELLA BENYAMIN
Issued 2/4/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/23/2018 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/23/2018 CELINA MORENO
Hydrant and Access approval Cleared 7/23/2018 GILBERT URREA
Permit Cleared 7/23/2018 CELINA MORENO
Sewer availability Cleared 7/23/2018 CELINA MORENO
Low Impact Development Cleared 2/14/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/14/2019 ELAINE LEI
Green Code Cleared 5/23/2019 SARAH ABOULHOSN

Contact Information

Contractor Best All Inc; Lic. No.: 1032431-B 18351 COLIMA RD      ROWLAND HEIGHTS, CA 91748

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/23/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/28/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/10/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/10/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Corrections Issued PATRICK QUALEY
Deputy Wood Construction 4/27/2022 No Access for Inspection PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Partial Approval PATRICK QUALEY
Wood Frame 5/13/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Corrections Issued JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 6/29/2022 Corrections Issued PATRICK QUALEY
Rough-Elec/Plmb/HVAC 7/5/2022 Corrections Issued PATRICK QUALEY
Rough-Elec/Plmb/HVAC 7/20/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 7/20/2022 Partial Approval JESUS RODRIGUEZ
Shower Pan 8/3/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 8/16/2022 Partial Approval CLAYTON GRAHAM
Shower Pan 8/16/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 8/19/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 9/12/2022 Conditional Approval JESUS RODRIGUEZ
Green Building Final 9/12/2022 Approved JESUS RODRIGUEZ
Insulation 9/15/2022 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 9/15/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 9/20/2022 Approved DAVID FEILER
Insulation 9/20/2022 Approved DAVID FEILER
Gas Test 11/3/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 12/9/2022 Corrections Issued DAVID FEILER
HVAC-Final 12/9/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 12/9/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Final 4/18/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 4/18/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Final 4/18/2023 Partial Approval JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 4/18/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 7/30/2025 Corrections Issued DAVID FEILER