1633 N EASTERLY TER 90026
Certificate Information: 1633 N EASTERLY TER 90026
- Application / Permit
- 18010-10000-01129
- Plan Check / Job No.
- B18LA04850
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW THREE STORY SINGLE FAMILY RESIDENCE WITH ATTACH GARAGE
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2018 | APPLICANT |
| Green Plans Picked Up | 3/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2018 | CHON CHIO KUO |
| Corrections Issued | 4/18/2018 | CHON CHIO KUO |
| Quality Review Completed | 4/18/2018 | STEVEN KIM |
| Building Plans Picked Up | 4/18/2018 | APPLICANT |
| Applicant returned to address corrections | 6/14/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 8/29/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/2/2020 | CHON CHIO KUO |
| Plan Check Approved | 5/6/2020 | CHON CHIO KUO |
| Issued | 10/8/2020 | APPLICANT |
| CofO in Progress | 3/17/2022 | SCOTT FINNILA |
| CofO Issued | 3/24/2022 | DEROLD HAUFF |
| Permit Finaled | 3/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/26/2018 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 4/26/2018 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 4/26/2018 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2018 | JAMES MORALEZ |
| Permit | Cleared | 4/26/2018 | JAMES MORALEZ |
| Sewer availability | Cleared | 4/26/2018 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 6/5/2018 | ROBERT DUFF |
| Green Code | Cleared | 6/12/2018 | COLIN LOREDO |
| Low Impact Development | Cleared | 6/12/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 6/12/2018 | ADRIAN SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 6/14/2018 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 10/31/2019 | BOK GOH |
| Disturb/Remove Protected Trees | Cleared | 12/23/2019 | STEPHEN DUPREY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jung,, Jason Stanley; Lic. No.: C80569 | 1032 S PALM AVE SAN GABRIEL, CA 91776 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2020 | Partial Inspection | DAVID CHAN |
| Piling/Pier/Caisson | 10/29/2020 | Partial Approval | SCOTT FINNILA |
| Piling/Pier/Caisson | 11/6/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 11/7/2020 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 11/8/2020 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 11/10/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Partial Approval | SCOTT FINNILA |
| Piling/Pier/Caisson | 11/18/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/24/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/16/2021 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 4/14/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/21/2021 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 5/12/2021 | Conditional Approval | SCOTT FINNILA |
| Wood Frame | 6/2/2021 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 6/21/2021 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 6/24/2021 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 7/8/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/15/2021 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 7/15/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/22/2021 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 7/22/2021 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/28/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/28/2021 | Approved | SCOTT FINNILA |
| Green Building Rough | 7/28/2021 | Approved | SCOTT FINNILA |
| HVAC-Rough | 7/28/2021 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 7/28/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/10/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/10/2021 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 8/10/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 8/13/2021 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 8/25/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 8/25/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/15/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/20/2021 | Approved | THOMAS LOGRASSO |
| Gas Test | 11/10/2021 | Approved | THOMAS LOGRASSO |
| Sewer | 1/25/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 2/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 2/1/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 2/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 2/24/2022 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 2/24/2022 | Approved | RUBEN SALAS |
| Green Building Final | 2/24/2022 | Not Ready for Inspection | RUBEN SALAS |
| Reinforced Masonry Frame | 2/24/2022 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 2/24/2022 | SGSOV Approved | RUBEN SALAS |
| Service/Power Release | 2/24/2022 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 2/24/2022 | Not Ready for Inspection | RUBEN SALAS |
| Structural Steel Frame | 2/24/2022 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 3/1/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 3/1/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 3/1/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 3/1/2022 | Approved | SCOTT FINNILA |
| Service/Power Release | 3/1/2022 | Approved | SCOTT FINNILA |
| Smoke Detectors | 3/1/2022 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 3/8/2022 | Approved | SCOTT FINNILA |
| Final | 3/8/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 3/17/2022 | OK to Issue CofO | SCOTT FINNILA |