1633 N EASTERLY TER 90026

Certificate Information: 1633 N EASTERLY TER 90026

Application / Permit
18010-10000-01129
Plan Check / Job No.
B18LA04850
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW THREE STORY SINGLE FAMILY RESIDENCE WITH ATTACH GARAGE
Permit Issued
Issued on 10/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2018 APPLICANT
Green Plans Picked Up 3/23/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 CHON CHIO KUO
Corrections Issued 4/18/2018 CHON CHIO KUO
Quality Review Completed 4/18/2018 STEVEN KIM
Building Plans Picked Up 4/18/2018 APPLICANT
Applicant returned to address corrections 6/14/2018 CHON CHIO KUO
Applicant returned to address corrections 8/29/2019 CHON CHIO KUO
Applicant returned to address corrections 1/2/2020 CHON CHIO KUO
Plan Check Approved 5/6/2020 CHON CHIO KUO
Issued 10/8/2020 APPLICANT
CofO in Progress 3/17/2022 SCOTT FINNILA
CofO Issued 3/24/2022 DEROLD HAUFF
Permit Finaled 3/24/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/26/2018 JAMES MORALEZ
BHO/Hillside ordinance Cleared 4/26/2018 JAMES MORALEZ
BHO/Hillside ordinance Cleared 4/26/2018 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 4/26/2018 JAMES MORALEZ
Permit Cleared 4/26/2018 JAMES MORALEZ
Sewer availability Cleared 4/26/2018 JAMES MORALEZ
Hydrant and Access approval Cleared 6/5/2018 ROBERT DUFF
Green Code Cleared 6/12/2018 COLIN LOREDO
Low Impact Development Cleared 6/12/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 6/12/2018 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 6/14/2018 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 10/31/2019 BOK GOH
Disturb/Remove Protected Trees Cleared 12/23/2019 STEPHEN DUPREY

Contact Information

Contractor Owner-Builder       ,
Engineer Jung,, Jason Stanley; Lic. No.: C80569 1032 S PALM AVE      SAN GABRIEL, CA 91776
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2020 Partial Inspection DAVID CHAN
Piling/Pier/Caisson 10/29/2020 Partial Approval SCOTT FINNILA
Piling/Pier/Caisson 11/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 11/7/2020 Off-Hour Fees Due
Piling/Pier/Caisson 11/8/2020 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 11/9/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 11/10/2020 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 11/12/2020 Partial Approval SCOTT FINNILA
Piling/Pier/Caisson 11/18/2020 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/22/2020 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/24/2020 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 1/20/2021 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/16/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 4/14/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/21/2021 Partial Approval SCOTT FINNILA
Wood Frame 5/12/2021 Conditional Approval SCOTT FINNILA
Wood Frame 6/2/2021 Partial Approval SCOTT FINNILA
Wood Frame 6/21/2021 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval SCOTT FINNILA
Green Building Rough 6/24/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 7/6/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/8/2021 Approved SCOTT FINNILA
ELECTRICAL-Rough 7/15/2021 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 7/15/2021 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 7/22/2021 Partial Approval SCOTT FINNILA
HVAC-Rough 7/22/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 7/28/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 7/28/2021 Approved SCOTT FINNILA
Green Building Rough 7/28/2021 Approved SCOTT FINNILA
HVAC-Rough 7/28/2021 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 7/28/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/10/2021 Approved THOMAS LOGRASSO
HVAC-Rough 8/10/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/10/2021 Partial Approval THOMAS LOGRASSO
Shower Pan 8/10/2021 Approved THOMAS LOGRASSO
Insulation 8/13/2021 Partial Approval THOMAS LOGRASSO
Drywall Nailing 8/25/2021 Approved THOMAS LOGRASSO
Insulation 8/25/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 9/15/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 9/20/2021 Approved THOMAS LOGRASSO
Gas Test 11/10/2021 Approved THOMAS LOGRASSO
Sewer 1/25/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 2/1/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 2/1/2022 Approved THOMAS LOGRASSO
Service/Power Release 2/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 2/24/2022 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 2/24/2022 Approved RUBEN SALAS
Green Building Final 2/24/2022 Not Ready for Inspection RUBEN SALAS
Reinforced Masonry Frame 2/24/2022 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Approved RUBEN SALAS
Service/Power Release 2/24/2022 Not Ready for Inspection RUBEN SALAS
Smoke Detectors 2/24/2022 Not Ready for Inspection RUBEN SALAS
Structural Steel Frame 2/24/2022 Approved RUBEN SALAS
ELECTRICAL-Final 3/1/2022 Corrections Issued SCOTT FINNILA
Final 3/1/2022 Corrections Issued SCOTT FINNILA
Green Building Final 3/1/2022 Approved SCOTT FINNILA
HVAC-Final 3/1/2022 Approved SCOTT FINNILA
Service/Power Release 3/1/2022 Approved SCOTT FINNILA
Smoke Detectors 3/1/2022 Approved SCOTT FINNILA
ELECTRICAL-Final 3/8/2022 Approved SCOTT FINNILA
Final 3/8/2022 Corrections Issued SCOTT FINNILA
Final 3/17/2022 OK to Issue CofO SCOTT FINNILA