2380 N ALVARADO ST 90039
Certificate Information: 2380 N ALVARADO ST 90039
- Application / Permit
- 18010-10000-01086
- Plan Check / Job No.
- B18LA04622
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD PER STATE APPROVED PLANS. FOUNDATION + ZONING CHECK ONLY WITH ATTACHED GARAGE. NFPA 13D THRUOUT MULTIPLE 1 OF 3
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- Permit Expired on 7/21/2025
- Certificate of Occupancy
- Permit Expired More Information
Permit Application Status History
| Submitted | 3/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2018 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 4/16/2018 | APPLICANT |
| Corrections Issued | 4/27/2018 | AUNG SOE |
| Quality Review Completed | 5/4/2018 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 5/14/2018 | APPLICANT |
| Applicant returned to address corrections | 6/1/2018 | AUNG SOE |
| Applicant returned to address corrections | 4/11/2019 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/21/2020 | ARMEN JIVALAGIAN |
| Plan Check Approved | 2/3/2020 | AUNG SOE |
| Issued | 3/6/2020 | LADBS |
| Permit Expired | 7/21/2025 | OSVALDO PARAMO |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/11/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2018 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/20/2018 | JOHN CONNEALLY |
| Excavation more than 5-ft deep | Cleared | 7/31/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/31/2018 | AUNG SOE |
| Grading Pre-Inspection | Cleared | 7/31/2018 | AUNG SOE |
| Low Impact Development | Cleared | 5/14/2019 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 5/14/2019 | ERIK BEASLEY |
| Green Code | Cleared | 1/30/2020 | KHEDER ALRAZAA |
| Disturb/Remove Protected Trees | Cleared | 2/3/2020 | STEPHEN DUPREY |
Contact Information
| Architect | Jennifer, Rebecca Marmon; Lic. No.: C32219 | 2404 WILSHIRE BLVD 9E LOS ANGELES, CA 90057 |
| Contractor | Duarte Building And Construction Inc; Lic. No.: 991991-B | 5022 W AVENUE N STE 102 #11 PALMDALE, CA 93551 |
| Engineer | Aoanan, Virgilio Cendana; Lic. No.: C36079 | 3951 MEDFORD ST LOS ANGELES, CA 90063 |
| Engineer | Jeremy, Robert Stone; Lic. No.: C85850 | 1901 LUNDY AV PASADENA, CA 91104 |
| Engineer | Ryan, Patrick Hardie; Lic. No.: C78813 | 16154 SW UPPER BOONES FERRY RD PORTLAND, OR |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/28/2021 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 7/6/2021 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Partial Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/12/2021 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 7/12/2021 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/19/2021 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 7/19/2021 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 8/18/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 9/13/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/13/2021 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/21/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/21/2021 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/8/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/8/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/19/2021 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/20/2021 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/10/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 2/10/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/22/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/14/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 3/23/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 8/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/30/2025 | Corrections Issued | OSVALDO PARAMO |
| Special/Order Compliance | 7/21/2025 | Permit Expired | OSVALDO PARAMO |