1320 W JEFFERSON BLVD 90007

Certificate Information: 1320 W JEFFERSON BLVD 90007

Application / Permit
18010-10000-01085
Plan Check / Job No.
B18LA04614
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 6-story ( 5 story type III-A over ground level type I-A), total of 129 dwelling units, reserving thirteen (13) units for Extremely Low Income ( Tier 3) over 2-levels of subterranean parking garage. Comply with Department Order effective date 09/03/2019
Permit Issued
Issued on 9/1/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 GARO TELMI
Corrections Issued 4/10/2018 GARO TELMI
Quality Review Completed 4/12/2018 JOHN FRANCIA
Building Plans Picked Up 4/17/2018 APPLICANT
Green Plans Picked Up 4/17/2018 APPLICANT
Disabled Access Plans Picked Up 11/7/2018 APPLICANT
Applicant returned to address corrections 3/13/2019 GARO TELMI
Applicant returned to address corrections 5/22/2019 GARO TELMI
Applicant returned to address corrections 6/27/2019 GARO TELMI
Applicant returned to address corrections 1/22/2020 GARO TELMI
Applicant returned to address corrections 7/7/2020 GARO TELMI
Plan Check Approved 7/15/2020 GARO TELMI
Issued 9/1/2020 APPLICANT
TCO Issued (Expire Date: 06-25-2024) 12/28/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 11-24-2024) 5/28/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 05-24-2025) 11/25/2024 ERNESTO CORRAL
CofO in Progress 12/6/2024 JAMES POWERS
Permit Finaled 12/6/2024 ERNESTO CORRAL
CofO Issued 12/6/2024 ERNESTO CORRAL
Permit Finaled 12/6/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/11/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/11/2019 CELINA MORENO
Miscellaneous Cleared 3/11/2019 HELENE ROTOLO
Trees in Parkway Cleared 3/12/2019 JOHN KIM
Driveway location Cleared 4/2/2019 EDUARDO HERMOSO
Internal circulation Cleared 4/2/2019 EDUARDO HERMOSO
Construction near power lines Cleared 5/1/2019 RIDWAN HARDY
Hydrant and Access approval Cleared 6/4/2019 ROBERT DUFF
Green Code Cleared 6/12/2019 COLIN LOREDO
DAS Clearance Cleared 7/3/2019 ELIZABETH TOMS
Low Impact Development Cleared 9/27/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/27/2019 JEANIE LAM
Fire Marshall Fire Life Safety Cleared 10/7/2019 OSCAR SALGADO JR
Bicycle Parking Cleared 12/10/2019 ELAINE LEI
Miscellaneous Cleared 12/10/2019 ANNA VIDAL
Miscellaneous Cleared 12/10/2019 ANNA VIDAL
Highway dedication Cleared 12/18/2019 ELENA LOPEZ
Sewer availability Cleared 12/18/2019 ELENA LOPEZ
Miscellaneous Cleared 1/22/2020 KIT AWAKUNI
Work Adjacent to Public Way Cleared 4/2/2020 BOK GOH
DCP conditions approval Cleared 4/14/2020 RICHARD TRUONG
Density Bonus 12.22.A.31 Cleared 4/14/2020 RICHARD TRUONG
Comm Cor/Mini-Mall Cleared 4/23/2020 ANNA VIDAL
Comm Cor/Mini-Mall Cleared 4/23/2020 ANNA VIDAL
Opn space landscape/Water mgmt Cleared 4/23/2020 ANNA VIDAL
Site Plan review Cleared 4/23/2020 ANNA VIDAL
ZI Cleared 4/23/2020 ANNA VIDAL
Encroachment in public way Cleared 6/10/2020 ELAINE LEI
Permit Cleared 6/26/2020 NGOC KIEM
Building over 3-story or 36-ft Cleared 7/15/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/15/2020 CALOSHA APPROVED

Contact Information

Architect Buser,, Bradley A; Lic. No.: C35921 236 FORDHAM ROAD      MANHATTAN, KS 66503
Contractor Prime Built Llc; Lic. No.: 1009781-B 1532 COLLEGE AVENUE F19      MANHATTAN, KS 66502
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Foroughi,, Mohammad Hossein; Lic. No.: C66179 767 NORTH HILL STREET 407      LOS ANGELES, CA 90012
Engineer Tsalyuk,, Yefim; Lic. No.: C52871 11278 LOS ALAMITOS BLVD 354      LOS ALAMITOS, CA 90720
Engineer Vandorpe,, Thomas Daniel; Lic. No.: S4611 1845 W ORANGEWOOD AVE SUITE 200      ORANGE, CA 92868
Engineer Vassallo,, Christopher W; Lic. No.: L8418 P O BOX 3762      PALOS VERDES PENINSULA, CA 90274

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/28/2020 Approved JAMES POWERS
Deputy Steel/Welding 2/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2021 Partial Approval JAMES POWERS
Pre-Inspection 3/26/2021 Approved JAMES POWERS
Deputy Methane Barrier 4/14/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 4/15/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/15/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/15/2021 Partial Approval JAMES POWERS
METHANE-Barrier 4/15/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 4/15/2021 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 4/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/16/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/19/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 4/30/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 5/12/2021 Partial Approval JAMES POWERS
METHANE-Barrier 5/12/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/13/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/14/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/18/2021 Partial Approval JAMES POWERS
METHANE-Barrier 5/18/2021 Partial Inspection JAMES POWERS
METHANE-Subgrade 5/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/21/2021 Partial Approval JAMES POWERS
Green Building Rough 5/25/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/25/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/25/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/25/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/28/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 6/1/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/1/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/1/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 6/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/11/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/11/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/11/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 6/11/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 6/15/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/15/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/15/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/15/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 6/21/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/21/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/21/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/21/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/23/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/23/2021 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 6/24/2021 Partial Approval JAMES POWERS
Green Building Rough 6/24/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/24/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/24/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/29/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/1/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/1/2021 Partial Approval JAMES POWERS
METHANE-Barrier 7/1/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 7/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/2/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/2/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/7/2021 Partial Approval JAMES POWERS
Green Building Rough 7/7/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/7/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/7/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/7/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/9/2021 Partial Approval JAMES POWERS
METHANE-Barrier 7/9/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 7/9/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/12/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/12/2021 Conditional Approval DAVID TSAU
Deputy Shotcrete 7/12/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval JAMES POWERS
Green Building Rough 7/15/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/15/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/15/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/15/2021 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 7/16/2021 Conditional Approval RAFAEL ESPINOZA
METHANE-Barrier 7/22/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 7/22/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2021 Partial Approval JAMES POWERS
Green Building Rough 7/23/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/23/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/23/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/23/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 7/30/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/30/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/30/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/30/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/2/2021 Partial Approval JAMES POWERS
Green Building Rough 8/5/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 8/5/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 8/5/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/5/2021 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 8/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/16/2021 Partial Approval JAMES POWERS
METHANE-Barrier 8/16/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 8/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/7/2021 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 9/7/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 9/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/8/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/8/2021 Partial Approval JAMES POWERS
METHANE-Barrier 9/28/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 9/28/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/28/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/29/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/1/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/6/2021 Partial Approval JAMES POWERS
Green Building Rough 10/6/2021 Approved JAMES POWERS
METHANE-Rough 10/6/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/6/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/6/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/8/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/8/2021 Partial Approval JAMES POWERS
METHANE-Rough 10/13/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 10/13/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/13/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/13/2021 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 10/14/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 10/15/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/22/2021 Partial Approval RUSSELL BONVOULOIR
METHANE-Barrier 10/22/2021 Partial Inspection RUSSELL BONVOULOIR
METHANE-Subgrade 10/22/2021 Partial Inspection RUSSELL BONVOULOIR
METHANE-Rough 10/26/2021 Not Ready for Inspection MARK FERRARI
Reinforced Concrete Frame 10/26/2021 Partial Approval MARK FERRARI
Verify Sprinkler Sign Off 10/26/2021 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 11/19/2021 Partial Inspection TED RIES
METHANE-Barrier 11/19/2021 Not Ready for Inspection TED RIES
METHANE-Subgrade 11/19/2021 Not Ready for Inspection TED RIES
Excavation/Setback/Form/Re-Bar 11/22/2021 Partial Inspection TED RIES
METHANE-Rough 11/23/2021 Partial Approval TED RIES
Reinforced Concrete Frame 11/23/2021 Partial Approval TED RIES
Verify Sprinkler Sign Off 11/23/2021 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 11/24/2021 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 12/1/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/3/2021 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/6/2021 Partial Approval JAMES POWERS
METHANE-Rough 12/9/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/9/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 12/9/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/10/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/17/2021 Partial Approval JAMES POWERS
METHANE-Barrier 2/23/2022 Approved JAMES POWERS
METHANE-Subgrade 2/23/2022 Approved JAMES POWERS
Reinforced Concrete Frame 2/23/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 2/25/2022 Approved JAMES POWERS
Reinforced Concrete Frame 2/25/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/25/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 3/8/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/16/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/16/2022 Partial Approval JAMES POWERS
Structural Steel Frame 4/1/2022 Not Ready for Inspection TED RIES
Structural Steel Frame 4/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/7/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 4/7/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 4/19/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/25/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/19/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/27/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 5/27/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/15/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/15/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 6/16/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/16/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/17/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/21/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/21/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 6/22/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/24/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/29/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/29/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/29/2022 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/30/2022 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 7/21/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/21/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 8/24/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 8/31/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/31/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/9/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 9/13/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval EDWIN GREGORYONA
Insulation 10/13/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 10/17/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 10/28/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/17/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 11/21/2022 Partial Approval JAMES POWERS
Wood Frame 11/23/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 11/29/2022 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 12/1/2022 Partial Approval JAMES POWERS
Wood Frame 12/1/2022 Partial Approval JAMES POWERS
Wood Frame 12/2/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 12/7/2022 Partial Approval JAMES POWERS
Insulation 12/7/2022 Partial Approval JAMES POWERS
Wood Frame 12/7/2022 Partial Approval JAMES POWERS
Wood Frame 12/8/2022 Partial Approval JAMES POWERS
Pre-Inspection 12/12/2022 Approved ALAN MORELOS
Wood Frame 12/12/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/13/2022 Partial Approval JAMES POWERS
Wood Frame 12/15/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 12/16/2022 Partial Approval JAMES POWERS
Insulation 12/20/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 12/20/2022 Partial Approval JAMES POWERS
Drywall Nailing 12/21/2022 Partial Approval JAMES POWERS
Insulation 12/28/2022 Partial Approval JAMES POWERS
Insulation 1/4/2023 Partial Approval JAMES POWERS
Insulation 1/10/2023 Partial Approval JAMES POWERS
Insulation 1/11/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 1/13/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 1/18/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Partial Approval JAMES POWERS
Insulation 1/19/2023 Partial Approval JAMES POWERS
Insulation 1/20/2023 Partial Approval JAMES POWERS
Insulation 1/24/2023 Partial Approval JAMES POWERS
Insulation 1/25/2023 Partial Approval EDWIN GREGORYONA
Insulation 1/27/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/1/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Partial Approval JAMES POWERS
Insulation 2/2/2023 Partial Approval EDWIN GREGORYONA
Insulation 2/3/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 2/10/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 2/14/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 2/15/2023 Partial Approval JAMES POWERS
Insulation 2/16/2023 Partial Approval EDWIN GREGORYONA
Insulation 2/21/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval JAMES POWERS
Drywall Nailing 2/27/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/28/2023 Partial Approval NICK DANERI
Drywall Nailing 3/1/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 3/3/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval GREGORY POMISH
Insulation 3/14/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 3/16/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/29/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 4/5/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/6/2023 Partial Approval JAMES POWERS
Insulation 4/7/2023 Not Ready for Inspection JAMES POWERS
Insulation 4/11/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/18/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/19/2023 Partial Approval LARRY ARNICK
Insulation 4/20/2023 Partial Approval GREGORY POMISH
Wood Frame 4/25/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/27/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/28/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/2/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/3/2023 Partial Approval JAMES POWERS
Drywall Nailing 5/9/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/12/2023 Partial Approval LARRY ARNICK
Drywall Nailing 5/16/2023 Partial Approval LARRY ARNICK
Drywall Nailing 5/17/2023 Partial Approval JAMES POWERS
Drywall Nailing 5/19/2023 Partial Approval JAMES POWERS
Drywall Nailing 5/23/2023 Partial Approval JAMES POWERS
Drywall Nailing 5/25/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/26/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/31/2023 Not Ready for Inspection LARRY ARNICK
Insulation 6/5/2023 Not Ready for Inspection NICK DANERI
Drywall Nailing 6/6/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/14/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/21/2023 Partial Approval RAFAEL ESPINOZA
Insulation 6/22/2023 Partial Approval ALAN MORELOS
Light Gage Steel Frame 6/27/2023 Partial Approval JAMES POWERS
Wood Frame 6/27/2023 Partial Approval JAMES POWERS
Wood Frame 6/28/2023 Partial Approval JAMES POWERS
Drywall Nailing 6/30/2023 Not Ready for Inspection LARRY ARNICK
Insulation 7/5/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/11/2023 Not Ready for Inspection JAMES POWERS
Insulation 7/12/2023 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 7/12/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/14/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/18/2023 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 7/19/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/25/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 7/26/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/27/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/1/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/8/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/11/2023 Partial Approval JAMES POWERS
Insulation 8/15/2023 Partial Approval JAMES POWERS
Insulation 8/22/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/23/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/24/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/29/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/8/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/12/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/13/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 9/15/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/19/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/20/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 9/21/2023 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 9/28/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 9/29/2023 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 10/11/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/12/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 10/17/2023 Partial Approval JAMES POWERS
Final 10/30/2023 Not Ready for Inspection JAMES POWERS
Final 11/1/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/1/2023 Partial Approval JAMES POWERS
Green Building Final 11/1/2023 Approved JAMES POWERS
Reinforced Concrete Frame 11/1/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/1/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Not Ready JAMES POWERS
Smoke Detectors 11/1/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/1/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/9/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 11/14/2023 Approved RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/15/2023 Partial Approval JAMES POWERS
Final 11/17/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/17/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/17/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/17/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Not Ready JAMES POWERS
Smoke Detectors 11/17/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/17/2023 Not Ready for Inspection JAMES POWERS
Final 11/28/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/28/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/28/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/28/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Not Ready JAMES POWERS
Smoke Detectors 11/28/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/28/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 11/29/2023 Partial Approval JAMES POWERS
Final 12/1/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 12/1/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/1/2023 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 12/1/2023 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Not Ready JAMES POWERS
Smoke Detectors 12/1/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 12/1/2023 Not Ready for Inspection JAMES POWERS
Final 12/22/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 12/22/2023 Approved JAMES POWERS
Reinforced Concrete Frame 12/22/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 12/22/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 12/22/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/22/2023 Not Ready for Inspection JAMES POWERS
Final 12/28/2023 OK for TCO JAMES POWERS
Reinforced Concrete Frame 12/28/2023 Approved JAMES POWERS
Reinforced Masonry Frame 12/28/2023 Approved JAMES POWERS
Special/Order Compliance 12/28/2023 Approved ERNESTO CORRAL
Verify Sprinkler Sign Off 12/28/2023 Approved JAMES POWERS
Special/Order Compliance 12/31/2023 Off-Hour Fees Due
Special/Order Compliance 5/29/2024 Partial Approval JAMES POWERS
Special/Order Compliance 10/29/2024 Approved JAMES POWERS
Final 11/25/2024 OK for TCO JAMES POWERS
Final 12/4/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/6/2024 Partial Approval JAMES POWERS
Final 12/6/2024 OK to Issue CofO JAMES POWERS