20148 W BALTAR ST 91306

Certificate Information: 20148 W BALTAR ST 91306

Application / Permit
18010-10000-01057
Plan Check / Job No.
B18LA04545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 SOTRY SFD W/ ATTACHED GARAGE PER PARCEL MAP LA NO.2009-3238.
Permit Issued
Issued on 8/28/2018
Issuing Office
Metro
Current Status
CofO Issued on 11/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2018 APPLICANT
Green Plans Picked Up 3/27/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 ZAW HAN
Corrections Issued 4/3/2018 ZAW HAN
Quality Review Completed 4/4/2018 KESETE HAREGOT
Building Plans Picked Up 4/9/2018 APPLICANT
Applicant returned to address corrections 5/17/2018 ZAW HAN
Applicant returned to address corrections 6/13/2018 ZAW HAN
Plan Check Approved 7/16/2018 Zaw Han
Issued 8/28/2018 LADBS
CofO in Progress 10/29/2021 STEVEN BACK
Permit Finaled 11/1/2021 JOHN JANSON
CofO Issued 11/1/2021 JOHN JANSON
Permit Finaled 11/1/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/16/2018 STEVE MELGAR
Green Code Cleared 4/16/2018 NEGAR NEJAD
Permit Cleared 4/16/2018 STEVE MELGAR
Certificate of Compliance Cleared 5/29/2018 BRIAN CARR
Miscellaneous Cleared 5/29/2018 BRIAN CARR
Hydrant and Access approval Cleared 6/21/2018 ROBERT DUFF
Low Impact Development Cleared 7/2/2018 IDA MEISAMI-FARD
Eng Process Fee Ord 176,300 Cleared 7/16/2018 MICHAEL CASTILLO
Roof/Waste drainage to street Cleared 7/16/2018 MICHAEL CASTILLO
Sewer availability Cleared 7/16/2018 MICHAEL CASTILLO

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/26/2018 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 12/31/2018 Partial Approval JOHN COLEMAN
Footing/Foundation/Slab 1/10/2019 Approved JOHN COLEMAN
Special/Order Compliance 6/12/2019 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 11/29/2019 Not Ready for Inspection MATTHEW NUCKOLLS
Green Building Rough 11/29/2019 Not Ready for Inspection MATTHEW NUCKOLLS
Verify Sprinkler Sign Off 11/29/2019 Not Ready for Inspection MATTHEW NUCKOLLS
BUILDING-Rough-Frame 6/2/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 6/2/2020 Not Ready for Inspection HENRY KIM
Deputy Wood Construction 6/5/2020 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 8/3/2020 Corrections Issued HENRY KIM
ELECTRICAL-Rough 8/3/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Approved HENRY KIM
HVAC-Rough 8/3/2020 Approved HENRY KIM
PLUMBING-Rough 8/3/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 8/13/2020 Corrections Issued DAVID SCANTLIN
Green Building Rough 8/13/2020 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 8/13/2020 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 8/25/2020 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 8/25/2020 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 9/2/2020 Not Ready for Inspection HENRY KIM
HVAC-Final 9/2/2020 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 9/2/2020 Approved HENRY KIM
Insulation 9/23/2020 Approved HENRY KIM
BUILDING-Rough-Frame 10/1/2020 Partial Approval HENRY KIM
PLUMBING-Rough 10/2/2020 Approved HENRY KIM
Pre-Inspection 10/2/2020 Approved HENRY KIM
BUILDING-Rough-Frame 10/6/2020 Partial Approval HENRY KIM
Drywall Nailing 10/6/2020 Approved HENRY KIM
Interior/Exterior Lathing 10/6/2020 Approved HENRY KIM
Interior/Exterior Lathing 2/19/2021 Approved HENRY KIM
Pre-Inspection 2/19/2021 Corrections Issued HENRY KIM
Shower Pan 2/19/2021 Approved HENRY KIM
Pre-Inspection 4/7/2021 Corrections Issued HENRY KIM
Sewer 4/7/2021 Partial Approval HENRY KIM
Sewer 4/14/2021 Corrections Issued HENRY KIM
Sewer 5/3/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 10/14/2021 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 10/20/2021 Approved HENRY KIM
ELECTRICAL-Final 10/20/2021 Corrections Issued HENRY KIM
Final 10/20/2021 Corrections Issued HENRY KIM
Gas Test 10/20/2021 Corrections Issued HENRY KIM
Green Building Final 10/20/2021 Corrections Issued HENRY KIM
HVAC-Final 10/20/2021 Corrections Issued HENRY KIM
PLUMBING-Final 10/20/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Approved HENRY KIM
Sewer 10/20/2021 Approved HENRY KIM
Smoke Detectors 10/20/2021 Corrections Issued HENRY KIM
Final 10/26/2021 Not Ready for Inspection STEVEN BACK
Green Building Final 10/26/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved STEVEN BACK
Service/Power Release 10/26/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 10/26/2021 Corrections Issued STEVEN BACK
Final 10/29/2021 OK to Issue CofO STEVEN BACK
Service/Power Release 10/29/2021 Approved STEVEN BACK
Smoke Detectors 10/29/2021 Approved STEVEN BACK