Deputy Reinf. Concrete
|
10/18/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
10/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
10/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
10/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
10/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
10/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
10/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
MERV13>=Rough
|
10/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
10/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/25/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
10/29/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
11/12/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
11/12/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
11/12/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
11/12/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
11/12/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Pre-Inspection
|
11/13/2019
|
Partial Inspection
|
LARRY ARNICK
|
|
Structural Steel Frame
|
11/13/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
11/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
11/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Pre-Inspection
|
11/18/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
11/18/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
11/18/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
11/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
11/20/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
11/21/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
11/22/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
11/25/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
11/25/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
11/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
11/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
11/25/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
11/26/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
11/26/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
11/27/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
12/2/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
12/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
12/3/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
12/4/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
12/4/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
12/5/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
12/6/2019
|
No Access for Inspection
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
12/9/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
12/11/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/30/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/31/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
1/2/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
1/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
1/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
1/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
1/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/3/2020
|
Approved
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
1/8/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
1/10/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
1/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
1/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
1/10/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
1/15/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Shotcrete
|
1/15/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Shotcrete
|
1/16/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Shotcrete
|
1/16/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
1/16/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/17/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
1/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/22/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
1/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
1/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
1/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
1/27/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
1/27/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/27/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
1/29/2020
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
1/29/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
1/30/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
1/31/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
MERV13>=Rough
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
2/28/2020
|
Approved
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
3/27/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
4/7/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Green Building Rough
|
4/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
4/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
4/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
4/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
4/24/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
4/24/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
4/27/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
4/29/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
4/30/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/4/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
5/6/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
5/6/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/6/2020
|
Corrections Issued
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
5/7/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/7/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
5/8/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
5/11/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
5/12/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
5/12/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
5/12/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
5/22/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
5/22/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
MERV13>=Rough
|
5/22/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
5/22/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
5/22/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
5/26/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
5/26/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
5/27/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/27/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/27/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
6/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
MERV13>=Rough
|
6/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
6/2/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
6/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
6/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
6/3/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
6/4/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Insulation
|
6/10/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
6/22/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/24/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/26/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/26/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
6/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
6/30/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
7/2/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/7/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
7/7/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/9/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
7/13/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/16/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/17/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
7/23/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
7/28/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Special/Order Compliance
|
7/30/2020
|
Corrections Issued
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
7/31/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
8/3/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
8/5/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
8/6/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Insulation
|
8/12/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
8/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
8/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
8/18/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
8/20/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
8/26/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/4/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
9/4/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
9/30/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/5/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/13/2020
|
Approved
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/15/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/22/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
12/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
12/14/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
12/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/28/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/25/2021
|
Partial Approval
|
LARRY ARNICK
|
|
Pre-Inspection
|
7/26/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
2/9/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
8/19/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
1/8/2024
|
OK to Issue CofO
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Final
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
MERV13>=Final
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
MERV13>=Rough
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
1/8/2024
|
SGSOV Approved
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Wood Frame
|
1/8/2024
|
Approved
|
EDWIN GREGORYONA
|