9857 N MASON AVE 91311
Certificate Information: 9857 N MASON AVE 91311
- Application / Permit
- 18010-10000-01049
- Plan Check / Job No.
- B18LA04512
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CORE AND SHELL FOR NEW 1-STORY TYPE VB RESTAURANT AND SITE DEVELOPMENT. BUILDING 6
- Permit Issued
- Issued on 8/20/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2018 | APPLICANT |
| Green Plans Picked Up | 3/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2018 | HERNAN ARREOLA |
| Corrections Issued | 4/23/2018 | HERNAN ARREOLA |
| Quality Review Completed | 4/23/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 4/25/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 4/25/2018 | APPLICANT |
| Applicant returned to address corrections | 6/8/2018 | HERNAN ARREOLA |
| Plan Check Approved | 8/20/2018 | HERNAN ARREOLA |
| Issued | 8/20/2018 | LADBS |
| TCO Issued (Expire Date: 09-06-2020) | 3/10/2020 | RICKEY JACKSON |
| CofO in Progress | 6/23/2020 | ROBERT COLE |
| CofO Issued | 7/9/2020 | RICKEY JACKSON |
| Permit Finaled | 7/9/2020 | RICKEY JACKSON |
Permit Application Clearance Information
| Driveway location | Cleared | 5/3/2018 | KEN AITCHISON |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2018 | CARLA VALLADARES |
| Stormwater Pollution Mitigatn | Cleared | 5/25/2018 | SAM NAVID |
| Food Service Establishment | Cleared | 5/29/2018 | RAMESHBHAIR PATEL |
| Hydrant and Access approval | Cleared | 5/30/2018 | JOHN DALLAS |
| Address approval | Cleared | 5/31/2018 | HOWARD COOPER |
| Roof/Waste drainage to street | Cleared | 5/31/2018 | EDUARDO PEDROZA |
| Sewer availability | Cleared | 5/31/2018 | EDUARDO PEDROZA |
| Highway dedication | Cleared | 6/22/2018 | KAYLA PEJI |
| Permit | Cleared | 6/22/2018 | KAYLA PEJI |
| DAS Clearance | Cleared | 6/26/2018 | ELIZABETH TOMS |
| Green Code | Cleared | 7/17/2018 | NEGAR NEJAD |
| "Q" conditions | Cleared | 7/18/2018 | EDBER MACEDO |
| "T" removal | Cleared | 7/18/2018 | EDBER MACEDO |
| Comm Cor/Mini-Mall | Cleared | 7/18/2018 | EDBER MACEDO |
| Comm Cor/Mini-Mall | Cleared | 7/18/2018 | EDBER MACEDO |
| Miscellaneous | Cleared | 7/18/2018 | EDBER MACEDO |
| Miscellaneous | Cleared | 7/18/2018 | EDBER MACEDO |
| Miscellaneous | Cleared | 7/18/2018 | EDBER MACEDO |
| Miscellaneous | Cleared | 7/18/2018 | EDBER MACEDO |
| Site Plan review | Cleared | 7/18/2018 | EDBER MACEDO |
| Food establishment approval | Cleared | 8/20/2018 | LACDHS APPROVED |
Contact Information
| Architect | Mc, Kently Kenneth; Lic. No.: C19257 | 1708 LAS FLORES DRIVE GLENDALE, CA 91207 |
| Contractor | J G Construction; Lic. No.: 671997-B | 15632 EL PRADO ROAD CHINO, CA 91710 |
| Engineer | Sklepko, Ronald William; Lic. No.: C46216 | PO BOX 78283 CORONA, CA 92877 |
| Engineer | Yu, Andy Man-Fai; Lic. No.: C27612 | 2350 ROUTH DR ROWLAND HTS, CA 91748 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/27/2018 | Partial Inspection | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 1/31/2019 | Not Ready for Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 2/1/2019 | Partial Approval | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 2/19/2019 | Corrections Issued | ROBERT COLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2019 | Partial Inspection | ROBERT COLE |
| Deputy Wood Construction | 3/8/2019 | Conditional Approval | JAMES STEPHENS |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2019 | Partial Inspection | ROBERT COLE |
| Green Building Rough | 3/12/2019 | Not Ready for Inspection | ROBERT COLE |
| Verify Sprinkler Sign Off | 3/12/2019 | Not Ready for Inspection | ROBERT COLE |
| Wood Frame | 3/12/2019 | Not Ready for Inspection | ROBERT COLE |
| Insulation | 3/27/2019 | Partial Approval | ROBERT COLE |
| Deputy Reinf. Concrete | 3/29/2019 | Conditional Approval | ROBERT COLE |
| Deputy Steel/Welding | 4/15/2019 | Conditional Approval | ROBERT COLE |
| Deputy Drilled-In Anchors | 4/23/2019 | Conditional Approval | ROBERT COLE |
| Deputy Steel/Welding | 4/23/2019 | Conditional Approval | ROBERT COLE |
| Interior/Exterior Lathing | 4/25/2019 | Partial Inspection | ROBERT COLE |
| Interior/Exterior Lathing | 4/29/2019 | Partial Approval | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 6/5/2019 | Corrections Issued | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 6/14/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Reinf. Concrete | 7/1/2019 | Conditional Approval | ROBERT COLE |
| Deputy Reinf. Concrete | 7/3/2019 | Conditional Approval | ROBERT COLE |
| Drywall Nailing | 10/31/2019 | Partial Inspection | ROBERT COLE |
| Final | 10/31/2019 | Partial Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 10/31/2019 | Not Ready for Inspection | ROBERT COLE |
| Green Building Final | 10/31/2019 | Not Ready for Inspection | ROBERT COLE |
| Green Building Rough | 10/31/2019 | Not Ready for Inspection | ROBERT COLE |
| SGSOV-Seismic Gas S/O Valve | 10/31/2019 | SGSOV Not Ready | ROBERT COLE |
| Smoke Detectors | 10/31/2019 | Not Ready for Inspection | ROBERT COLE |
| Verify Sprinkler Sign Off | 10/31/2019 | Not Ready for Inspection | ROBERT COLE |
| Wood Frame | 10/31/2019 | Not Ready for Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 1/22/2020 | Corrections Issued | ROBERT COLE |
| Special/Order Compliance | 2/19/2020 | Partial Inspection | ROBERT COLE |
| Drywall Nailing | 2/20/2020 | Approved | ROBERT COLE |
| Final | 2/20/2020 | Not Ready for Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 2/20/2020 | Approved | ROBERT COLE |
| Green Building Final | 2/20/2020 | Approved | ROBERT COLE |
| Green Building Rough | 2/20/2020 | Approved | ROBERT COLE |
| SGSOV-Seismic Gas S/O Valve | 2/20/2020 | SGSOV Not Ready | ROBERT COLE |
| Smoke Detectors | 2/20/2020 | Approved | ROBERT COLE |
| Special/Order Compliance | 2/20/2020 | Approved | ROBERT COLE |
| Verify Sprinkler Sign Off | 2/20/2020 | Approved | ROBERT COLE |
| Wood Frame | 2/20/2020 | Approved | ROBERT COLE |
| Final | 2/26/2020 | Partial Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 2/26/2020 | Not Ready for Inspection | ROBERT COLE |
| Green Building Final | 2/26/2020 | Not Ready for Inspection | ROBERT COLE |
| SGSOV-Seismic Gas S/O Valve | 2/26/2020 | SGSOV Not Ready | ROBERT COLE |
| Smoke Detectors | 2/26/2020 | Not Ready for Inspection | ROBERT COLE |
| Wood Frame | 2/26/2020 | Not Ready for Inspection | ROBERT COLE |
| Final | 6/10/2020 | Not Ready for Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 6/10/2020 | Approved | ROBERT COLE |
| Green Building Final | 6/10/2020 | Approved | ROBERT COLE |
| SGSOV-Seismic Gas S/O Valve | 6/10/2020 | SGSOV Approved | ROBERT COLE |
| Smoke Detectors | 6/10/2020 | Approved | ROBERT COLE |
| Wood Frame | 6/10/2020 | Approved | ROBERT COLE |
| Final | 6/19/2020 | Conditional Approval | ROBERT COLE |
| Final | 6/23/2020 | OK to Issue CofO | ROBERT COLE |