2216 1/2 E 112TH ST 90059

Certificate Information: 2216 1/2 E 112TH ST 90059

Application / Permit
18010-10000-01043
Plan Check / Job No.
B18LA04486
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'X16'-9" ACCESSORY DWELLING UNIT AT REAR OF LOT, PER AB 494 AND SB 229. 1 STORY, . ALL WORK PER WFPP.
Permit Issued
Issued on 3/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 MICHAEL PEREZ
Corrections Issued 4/3/2018 PAUL PIERRE
Quality Review Completed 4/9/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 4/17/2018 APPLICANT
Applicant returned to address corrections 5/31/2018 MICHAEL PEREZ
Green Plans Picked Up 9/9/2019 APPLICANT
Plan Check Approved 3/3/2020 MICHAEL PEREZ
Issued 3/3/2020 LADBS
CofO in Progress 12/2/2020 KEITH EDGHILL
Permit Finaled 2/1/2021 BRUCE TODD
CofO Issued 2/1/2021 BRUCE TODD
Permit Finaled 2/1/2021 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 5/3/2018 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/14/2018 KAREN LE
Sewer availability Cleared 5/14/2018 KAREN LE
Construction near power lines Cleared 10/5/2019 RIDWAN HARDY
Construction within easement Cleared 10/5/2019 RIDWAN HARDY
Hydrant and Access approval Cleared 10/10/2019 ROBERT DUFF
Miscellaneous Cleared 10/10/2019 ANNA VIDAL
ZA Case Cleared 10/10/2019 ANNA VIDAL
Green Code Cleared 10/30/2019 COLIN LOREDO
Green Code Cleared 10/30/2019 PAUL PIERRE
Low Impact Development Cleared 10/30/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 10/30/2019 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/26/2020 Not Ready for Inspection KEITH EDGHILL
Footing/Foundation/Slab 6/26/2020 Not Ready for Inspection KEITH EDGHILL
Underground Mechanical 7/14/2020 Conditional Approval KEITH EDGHILL
Underground Mechanical 7/16/2020 Conditional Approval KEITH EDGHILL
Underground Mechanical 7/17/2020 Conditional Approval KEITH EDGHILL
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Conditional Approval KEITH EDGHILL
PLUMBING-Rough 7/30/2020 Approved KEITH EDGHILL
ELECTRICAL-Rough 8/4/2020 Approved KEITH EDGHILL
PLUMBING-Rough 8/4/2020 Approved KEITH EDGHILL
Rough-Elec/Plmb/HVAC 8/4/2020 Conditional Approval KEITH EDGHILL
Insulation 8/11/2020 Approved KEITH EDGHILL
Drywall Nailing 8/21/2020 Approved KEITH EDGHILL
Green Building Rough 8/21/2020 Approved KEITH EDGHILL
Rough-Elec/Plmb/HVAC 9/3/2020 Approved KEITH EDGHILL
Shower Pan 9/3/2020 Approved KEITH EDGHILL
Underground Mechanical 9/3/2020 Approved KEITH EDGHILL
BUILDING-Rough-Frame 9/15/2020 Conditional Approval KEITH EDGHILL
Final 9/15/2020 Corrections Issued KEITH EDGHILL
Footing/Foundation/Slab 9/15/2020 Approved KEITH EDGHILL
Green Building Final 9/15/2020 Corrections Issued KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 9/15/2020 SGSOV Not Ready KEITH EDGHILL
Service/Power Release 9/15/2020 Not Ready for Inspection KEITH EDGHILL
Smoke Detectors 9/15/2020 Approved KEITH EDGHILL
Verify Sprinkler Sign Off 9/15/2020 Not Ready for Inspection KEITH EDGHILL
BUILDING-Rough-Frame 9/25/2020 Conditional Approval KEITH EDGHILL
Final 9/25/2020 Corrections Issued KEITH EDGHILL
Green Building Final 9/25/2020 Corrections Issued KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Approved KEITH EDGHILL
Service/Power Release 9/25/2020 Not Ready for Inspection KEITH EDGHILL
Verify Sprinkler Sign Off 9/25/2020 Not Ready for Inspection KEITH EDGHILL
Special/Order Compliance 9/29/2020 Corrections Issued KEITH EDGHILL
BUILDING-Rough-Frame 12/2/2020 Approved KEITH EDGHILL
ELECTRICAL-Final 12/2/2020 Approved KEITH EDGHILL
Final 12/2/2020 Conditional Approval KEITH EDGHILL
Green Building Final 12/2/2020 Approved KEITH EDGHILL
PLUMBING-Final 12/2/2020 Approved KEITH EDGHILL
SWPPP-Const. Storm Water 12/2/2020 Completed KEITH EDGHILL
Service/Power Release 12/2/2020 Approved KEITH EDGHILL
Verify Sprinkler Sign Off 12/2/2020 Approved KEITH EDGHILL