1232 E 50TH ST 90011
Certificate Information: 1232 E 50TH ST 90011
- Application / Permit
- 18010-10000-01034
- Plan Check / Job No.
- B18LA04420
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADU PER AB 494 SB 229 OVER NEW PATIO
- Permit Issued
- Issued on 6/13/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2018 | SINA KHOSRAVI |
| Green Plans Picked Up | 3/22/2018 | APPLICANT |
| Corrections Issued | 3/25/2018 | SINA KHOSRAVI |
| Quality Review Completed | 4/9/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 4/10/2018 | APPLICANT |
| Applicant returned to address corrections | 5/23/2018 | SINA KHOSRAVI |
| Plan Check Approved | 6/7/2018 | SINA KHOSRAVI |
| Issued | 6/13/2018 | LADBS |
| CofO in Progress | 5/8/2020 | ROBERT MCDOWELL |
| Permit Finaled | 5/26/2020 | HORACE FULTZ |
| CofO Issued | 10/15/2020 | DEROLD HAUFF |
| Permit Finaled | 10/15/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 5/14/2018 | COLIN LOREDO |
| Address approval | Cleared | 5/23/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 5/23/2018 | GILBERT URREA |
| Low Impact Development | Cleared | 5/23/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/23/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 5/23/2018 | MICHAEL CASTILLO |
Contact Information
| Engineer | Mendez, Luis C; Lic. No.: C53453 | AMCE ENGINEERS 8301 E FLORENCE AVE STE 205 DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/20/2018 | Not Ready for Inspection | FRANCISCO MORADO |
| Footing/Foundation/Slab | 7/26/2018 | Approved | FRANCISCO MORADO |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2018 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 9/12/2018 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 9/12/2018 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2018 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 10/9/2018 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 10/9/2018 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 1/14/2019 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Rough | 1/14/2019 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 1/14/2019 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 1/25/2019 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 1/25/2019 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 1/25/2019 | Approved | ROBERT MCDOWELL |
| Insulation | 1/25/2019 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 1/25/2019 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 1/25/2019 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 1/30/2019 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 2/13/2019 | Approved | ROBERT MCDOWELL |
| Shower Pan | 2/22/2019 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/19/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 4/19/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/19/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/19/2019 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/19/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/19/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 4/29/2019 | Not Ready for Inspection | BOB DUNN |
| Green Building Final | 4/29/2019 | Not Ready for Inspection | BOB DUNN |
| HVAC-Rough | 4/29/2019 | Corrections Issued | BOB DUNN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2019 | SGSOV Not Ready | BOB DUNN |
| Service/Power Release | 4/29/2019 | Not Ready for Inspection | BOB DUNN |
| Smoke Detectors | 4/29/2019 | Not Ready for Inspection | BOB DUNN |
| BUILDING-Rough-Frame | 5/10/2019 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 5/10/2019 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/10/2019 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/10/2019 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 5/10/2019 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 5/10/2019 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/22/2019 | Conditional Approval | VICTOR PUKHALSKY |
| BUILDING-Rough-Frame | 6/3/2019 | Approved | VICTOR PUKHALSKY |
| Final | 6/3/2019 | Corrections Issued | VICTOR PUKHALSKY |
| Green Building Final | 6/3/2019 | Not Ready for Inspection | VICTOR PUKHALSKY |
| SGSOV-Seismic Gas S/O Valve | 6/3/2019 | SGSOV Not Ready | VICTOR PUKHALSKY |
| Service/Power Release | 6/3/2019 | Not Ready for Inspection | VICTOR PUKHALSKY |
| Smoke Detectors | 6/3/2019 | Approved | VICTOR PUKHALSKY |
| SGSOV-Seismic Gas S/O Valve | 6/25/2019 | SGSOV Not Ready | FREDDIE RIVERA |
| ELECTRICAL-Final | 7/1/2019 | Corrections Issued | VICTOR PUKHALSKY |
| PLUMBING-Final | 7/1/2019 | Not Ready for Inspection | VICTOR PUKHALSKY |
| Service/Power Release | 7/1/2019 | Not Ready for Inspection | VICTOR PUKHALSKY |
| ELECTRICAL-Final | 7/15/2019 | Approved | VICTOR PUKHALSKY |
| Final | 7/15/2019 | Corrections Issued | VICTOR PUKHALSKY |
| Green Building Final | 7/15/2019 | Not Ready for Inspection | VICTOR PUKHALSKY |
| PLUMBING-Final | 7/15/2019 | Approved | VICTOR PUKHALSKY |
| SGSOV-Seismic Gas S/O Valve | 7/15/2019 | SGSOV Not Ready | VICTOR PUKHALSKY |
| Service/Power Release | 7/15/2019 | Not Ready for Inspection | VICTOR PUKHALSKY |
| Final | 12/10/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 12/10/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/10/2019 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 12/10/2019 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/10/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 2/10/2020 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 2/10/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/3/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Service/Power Release | 3/3/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 4/2/2020 | Not Ready for Inspection | RUBEN SALAS |
| Service/Power Release | 4/2/2020 | Not Ready for Inspection | RUBEN SALAS |
| Final | 4/29/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| HVAC-Final | 4/29/2020 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 4/29/2020 | Approved | ROBERT MCDOWELL |