1279 E 55TH ST 90011

Certificate Information: 1279 E 55TH ST 90011

Application / Permit
18010-10000-00992
Plan Check / Job No.
B18LA04235
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING W/ ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 6/8/2018
Issuing Office
Metro
Current Status
Issued on 6/8/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/6/2018 APPLICANT
Green Plans Picked Up 3/20/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 JAYDON NGUYEN
Corrections Issued 3/28/2018 JAYDON NGUYEN
Quality Review Completed 4/11/2018 BILL STUTSMAN
Building Plans Picked Up 4/12/2018 APPLICANT
Applicant returned to address corrections 5/24/2018 JAYDON NGUYEN
Plan Check Approved 6/1/2018 JAYDON NGUYEN
Plan Check Approved 6/1/2018 JAYDON NGUYEN
Issued 6/8/2018 LADBS

Permit Application Clearance Information

Address approval Cleared 4/19/2018 ADRIAN SANCHEZ
Green Code Cleared 4/27/2018 NEGAR NEJAD
Eng Process Fee Ord 176,300 Cleared 5/17/2018 CARLA VALLADARES
Hydrant and Access approval Cleared 5/17/2018 GEORGE SUCHAND
Low Impact Development Cleared 5/17/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/17/2018 CARLA VALLADARES
Frnt yard landscape/Water mgmt Cleared 5/21/2018 IVORY CHAMBESHI
Sewer availability Cleared 6/1/2018 STEVE MELGAR

Contact Information

Contractor Fashion Remodeling Inc; Lic. No.: 1019446-B 2185 CAMBRIDGE STREET      LOS ANGELES, CA 90006
Engineer Velasco, Jose Luis; Lic. No.: C76091 15 DRAKE RD      FITCHBURG, MA 01420

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/20/2018 Partial Approval FRANCISCO MORADO
Footing/Foundation/Slab 9/24/2018 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 9/11/2019 Partial Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/11/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 9/11/2019 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 9/11/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 9/11/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 11/2/2022 Approved HORACE FULTZ
Special/Order Compliance 11/8/2022 Approved HORACE FULTZ
Special/Order Compliance 1/6/2023 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 2/3/2023 Corrections Issued BRENDAN MORELLI
Wood Frame 9/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Corrections Issued WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Approved SABAS ALONSO