401 E 7TH ST 1-99 90014

Certificate Information: 401 E 7TH ST 1-99 90014

Application / Permit
18010-10000-00967
Plan Check / Job No.
B18LA04121
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 6-story, 99-unit, affordable housing apartment building over 1 level of above grade parking, ancillary office uses for on-site social services, and storage (98 Very Low Income)
Permit Issued
Issued on 11/30/2018
Issuing Office
Metro
Current Status
CofO Issued on 1/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 GARO TELMI
Corrections Issued 4/16/2018 ARMEN JIVALAGIAN
Quality Review Completed 4/16/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 4/16/2018 APPLICANT
Applicant returned to address corrections 4/24/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/10/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/21/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/26/2018 ARMEN JIVALAGIAN
Plan Check Approved 11/30/2018 ARMEN JIVALAGIAN
Issued 11/30/2018 LADBS
TCO Issued (Expire Date: 03-29-2021) 9/30/2020 DAVID TSAU
CofO in Progress 1/27/2021 JAMES POWERS
Permit Finaled 1/27/2021 ERNESTO CORRAL
CofO Issued 1/27/2021 ERNESTO CORRAL
Permit Finaled 1/27/2021 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 4/25/2018 EDBER MACEDO
"Q" conditions Cleared 4/25/2018 EDBER MACEDO
Address approval Cleared 4/25/2018 CARLA VALLADARES
Permit Cleared 4/25/2018 CARLA VALLADARES
Encroachment in public way Cleared 8/10/2018 KAREN LE
Sewer availability Cleared 8/22/2018 STEVE MELGAR
Project located in CRA area Cleared 10/10/2018 JIM URQUHART
Highway dedication Cleared 10/16/2018 ADRIAN SANCHEZ
DAS Clearance Cleared 11/20/2018 ARMEN JIVALAGIAN
Green Code Cleared 11/20/2018 DONALD CRICHLOW
Construction near power lines Cleared 11/21/2018 NADER ISKANDER
Construction within easement Cleared 11/21/2018 NADER ISKANDER
DCP conditions approval Cleared 11/28/2018 RICHARD TRUONG
Density Bonus 12.22.A.25 Cleared 11/28/2018 RICHARD TRUONG
Eng Process Fee Ord 176,300 Cleared 11/28/2018 KARAN PATEL
Fire Marshall Fire Life Safety Cleared 11/28/2018 WILLIAM JOHNS
Hydrant and Access approval Cleared 11/28/2018 ROBERT DUFF
Low Impact Development Cleared 11/29/2018 MARTIN FRAGOSO
Miscellaneous Cleared 11/29/2018 DIANA JIMENEZ
Opn space landscape/Water mgmt Cleared 11/29/2018 DIANA JIMENEZ
Roof/Waste drainage to street Cleared 11/29/2018 CELINA MORENO
Site Plan review Cleared 11/29/2018 DIANA JIMENEZ
Work Adjacent to Public Way Cleared 11/29/2018 ARMEN JIVALAGIAN
ZI Cleared 11/29/2018 DIANA JIMENEZ
Building over 3-story or 36-ft Cleared 11/30/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/30/2018 CALOSHA APPROVED
Trees in Parkway Cleared 11/30/2018 JOEL HERNANDEZ

Contact Information

Architect Koning,, Hendrik; Lic. No.: C13530 1454 25TH STREET      SANTA MONICA, CA 90404
Contractor Benchmark Contractors Inc; Lic. No.: 462263-A 3330 OCEAN PARK BLVD      SANTA MONICA, CA 90405
Engineer Adams,, Jelisa Thomas; Lic. No.: GE3092 26632 EL TOBOSO      MISSION VIEJO, CA 92691
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 2/13/2019 Partial Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 3/1/2019 Partial Inspection NICK DANERI
Pre-Inspection 3/1/2019 Partial Inspection NICK DANERI
Footing/Foundation/Slab 3/14/2019 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 3/18/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/19/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 3/19/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/20/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/21/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/22/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/22/2019 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/26/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/27/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/28/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/28/2019 Partial Approval NICK DANERI
Deputy Reinf. Masonry 4/1/2019 Partial Approval JAMES POWERS
Green Building Rough 4/1/2019 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 4/1/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/1/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 4/2/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/3/2019 Conditional Approval NICK DANERI
Reinforced Concrete Frame 4/3/2019 Partial Approval NICK DANERI
Deputy Reinf. Masonry 4/4/2019 Partial Approval JAMES POWERS
Green Building Rough 4/4/2019 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 4/4/2019 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/4/2019 Not Ready for Inspection NICK DANERI
Deputy Reinf. Masonry 4/5/2019 Conditional Approval NICK DANERI
Masonry Wall/Backfill 4/8/2019 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/9/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/9/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/10/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/11/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/12/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/15/2019 Conditional Approval NICK DANERI
Green Building Rough 4/15/2019 Partial Approval NICK DANERI
Reinforced Masonry Frame 4/15/2019 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/15/2019 Not Ready for Inspection NICK DANERI
Deputy Reinf. Masonry 4/16/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 5/1/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/8/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/8/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/6/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/11/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/13/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/14/2019 Partial Approval JAMES POWERS
Green Building Rough 6/14/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/14/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/14/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/17/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/19/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/27/2019 Partial Approval JAMES POWERS
Wood Frame 6/27/2019 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 6/28/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 7/2/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/3/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/10/2019 Conditional Approval LESLIE TRUJILLO
Pre-Inspection 7/15/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 7/19/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/19/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/23/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/23/2019 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 7/25/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/25/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/6/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/7/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/8/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/8/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/13/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 8/16/2019 Partial Approval JAMES POWERS
Green Building Rough 8/16/2019 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 8/16/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/16/2019 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/20/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/20/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/20/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/21/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/22/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/22/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/22/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/22/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/23/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/26/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/27/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/27/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/28/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/28/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/28/2019 Partial Approval JAMES POWERS
Green Building Rough 8/28/2019 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 8/28/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/28/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 8/29/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/29/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 8/29/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/30/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/4/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 9/4/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 9/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 9/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 9/10/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/11/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 9/12/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 9/12/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/13/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/17/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/18/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/19/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/20/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/20/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/23/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/24/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/25/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 9/25/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/25/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/26/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 10/1/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/2/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/2/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/3/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/4/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 10/4/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/8/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/9/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/10/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/11/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 10/16/2019 Partial Approval JAMES POWERS
Insulation 10/16/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/22/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/23/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 10/23/2019 Partial Approval JAMES POWERS
Drywall Nailing 10/23/2019 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/23/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/24/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 10/28/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/29/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/30/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 10/30/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/30/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/31/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/1/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/4/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/4/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/5/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/6/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/7/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/8/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/8/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/8/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/12/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/13/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/13/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/14/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/15/2019 Partial Approval JAMES POWERS
Drywall Nailing 11/18/2019 Not Ready for Inspection JAMES POWERS
T-Bar Ceiling 11/18/2019 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 11/20/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/20/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/21/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/21/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/22/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/26/2019 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 11/27/2019 Partial Approval DANIEL MC AULIFFE
Interior/Exterior Lathing 11/27/2019 Partial Approval DANIEL MC AULIFFE
T-Bar Ceiling 11/27/2019 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 12/3/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/4/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/4/2019 Not Ready for Inspection JAMES POWERS
T-Bar Ceiling 12/4/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/5/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/6/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/11/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/19/2019 Partial Approval JAMES POWERS
Drywall Nailing 1/9/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/13/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/22/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/24/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/28/2020 Partial Approval JAMES POWERS
T-Bar Ceiling 1/28/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 1/30/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 1/31/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/3/2020 Not Ready for Inspection JAMES POWERS
T-Bar Ceiling 2/3/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/10/2020 Partial Inspection JAMES POWERS
Deputy Fireproofing 2/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 2/21/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 2/24/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 2/25/2020 Partial Approval JAMES POWERS
Insulation 2/25/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 3/2/2020 Partial Approval JAMES POWERS
Insulation 3/2/2020 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 3/2/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 3/3/2020 Partial Approval JAMES POWERS
Deputy Fireproofing 3/4/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 4/21/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/12/2020 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/20/2020 Approved JAMES POWERS
Green Building Final 5/20/2020 Not Ready for Inspection JAMES POWERS
Green Building Rough 5/20/2020 Approved JAMES POWERS
Interior/Exterior Lathing 5/20/2020 Approved JAMES POWERS
Reinforced Concrete Frame 5/20/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 5/20/2020 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 5/20/2020 SGSOV Not Ready JAMES POWERS
Smoke Detectors 5/20/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/20/2020 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/4/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/5/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/24/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/25/2020 Partial Approval JAMES POWERS
Deputy Grading 7/7/2020 Partial Approval JAMES POWERS
Deputy Grading 7/8/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/13/2020 Partial Approval JAMES POWERS
Pre-Inspection 8/7/2020 Approved JAMES POWERS
Pre-Inspection 9/23/2020 Approved JAMES POWERS
Insulation 9/25/2020 Partial Approval JAMES POWERS
Final 9/28/2020 OK for TCO JAMES POWERS
Green Building Final 9/28/2020 Approved JAMES POWERS
Reinforced Concrete Frame 9/28/2020 Approved JAMES POWERS
Reinforced Masonry Frame 9/28/2020 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Approved JAMES POWERS
Smoke Detectors 9/28/2020 Approved JAMES POWERS
Verify Sprinkler Sign Off 9/28/2020 Approved JAMES POWERS
Final 1/27/2021 OK to Issue CofO JAMES POWERS