Grading Pre-Inspection
|
2/13/2019
|
Partial Inspection
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/1/2019
|
Partial Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
3/1/2019
|
Partial Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/14/2019
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/18/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
3/19/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
3/20/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/21/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/22/2019
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/22/2019
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/26/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/27/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/28/2019
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/28/2019
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/1/2019
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
4/1/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
4/1/2019
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
4/1/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
4/2/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/3/2019
|
Conditional Approval
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
4/3/2019
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
4/4/2019
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
4/4/2019
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/4/2019
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/5/2019
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
4/8/2019
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/9/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/9/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/10/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/11/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/12/2019
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/15/2019
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/15/2019
|
Partial Approval
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
4/15/2019
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/15/2019
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/16/2019
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
5/1/2019
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
5/7/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
5/8/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
5/8/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
5/9/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
5/10/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/3/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/4/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/5/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/6/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/12/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/13/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/14/2019
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
6/14/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
6/14/2019
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/14/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/17/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/18/2019
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
6/18/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/27/2019
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
6/27/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/28/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
7/1/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Wood Construction
|
7/2/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/3/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
7/10/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Pre-Inspection
|
7/15/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
7/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/23/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/25/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/25/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/6/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/13/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/15/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Steel/Welding
|
8/16/2019
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
8/16/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
8/16/2019
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/16/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/21/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/26/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/27/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/28/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/28/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/28/2019
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
8/28/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
8/28/2019
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/28/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
8/29/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/29/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/29/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
8/30/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/5/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Steel/Welding
|
9/6/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Wood Construction
|
9/6/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Steel/Welding
|
9/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/11/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/13/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/17/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/18/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/24/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/25/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/25/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/26/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
9/27/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Steel/Welding
|
10/1/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/2/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/2/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/3/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/16/2019
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
10/16/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/23/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/24/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/25/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Steel/Welding
|
10/28/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/29/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/30/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/30/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/30/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/31/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/1/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/5/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/6/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/13/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/13/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/14/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/15/2019
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
11/18/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
T-Bar Ceiling
|
11/18/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/21/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/21/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/22/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/26/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/27/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Interior/Exterior Lathing
|
11/27/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
T-Bar Ceiling
|
11/27/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
12/3/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/4/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
T-Bar Ceiling
|
12/4/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/5/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/6/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/9/2020
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/22/2020
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/24/2020
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/28/2020
|
Partial Approval
|
JAMES POWERS
|
|
T-Bar Ceiling
|
1/28/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
1/30/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
1/31/2020
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
2/3/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
T-Bar Ceiling
|
2/3/2020
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
2/10/2020
|
Partial Inspection
|
JAMES POWERS
|
|
Deputy Fireproofing
|
2/20/2020
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Fireproofing
|
2/21/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
2/24/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
2/25/2020
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
2/25/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
3/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
3/2/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
3/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
3/3/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Fireproofing
|
3/4/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/21/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/12/2020
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/12/2020
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
5/20/2020
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
5/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Rough
|
5/20/2020
|
Approved
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
5/20/2020
|
Approved
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
5/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
5/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
5/20/2020
|
SGSOV Not Ready
|
JAMES POWERS
|
|
Smoke Detectors
|
5/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2020
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
6/5/2020
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
6/24/2020
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
6/25/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Grading
|
7/7/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Grading
|
7/8/2020
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
8/7/2020
|
Approved
|
JAMES POWERS
|
|
Pre-Inspection
|
9/23/2020
|
Approved
|
JAMES POWERS
|
|
Insulation
|
9/25/2020
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
9/28/2020
|
OK for TCO
|
JAMES POWERS
|
|
Green Building Final
|
9/28/2020
|
Approved
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
9/28/2020
|
Approved
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
9/28/2020
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
9/28/2020
|
SGSOV Approved
|
JAMES POWERS
|
|
Smoke Detectors
|
9/28/2020
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/28/2020
|
Approved
|
JAMES POWERS
|
|
Final
|
1/27/2021
|
OK to Issue CofO
|
JAMES POWERS
|