Pre-Inspection
|
3/22/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/16/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/24/2019
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/24/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/25/2019
|
Approved
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/25/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/29/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Deputy Reinf. Masonry
|
5/3/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/6/2019
|
Approved
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
5/8/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/13/2019
|
Approved
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
5/13/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/14/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
5/14/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
5/14/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/15/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/27/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Reinforced Concrete Frame
|
6/27/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
6/27/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
7/5/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
7/8/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/8/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
7/8/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
7/8/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
7/9/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/10/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
8/28/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
8/28/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/28/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/9/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/9/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/15/2019
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/29/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
11/1/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/27/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/3/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/9/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
12/20/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
12/20/2019
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/20/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/17/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
1/17/2020
|
Conditional Approval
|
ROBERT COLE
|
|
Wood Frame
|
1/17/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
1/22/2020
|
Partial Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
1/23/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/27/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/27/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/27/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/28/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/30/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/31/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/3/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
2/3/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/10/2020
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
2/10/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/11/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
2/11/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/18/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
2/18/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
2/18/2020
|
OK to Expire Permit
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
3/6/2020
|
Partial Approval
|
JAMES STEPHENS
|
|
Green Building Rough
|
3/6/2020
|
Not Ready for Inspection
|
JAMES STEPHENS
|
|
Interior/Exterior Lathing
|
3/6/2020
|
Partial Approval
|
JAMES STEPHENS
|
|
Drywall Nailing
|
4/13/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
4/13/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Special/Order Compliance
|
5/11/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/30/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
6/30/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Special/Order Compliance
|
7/31/2020
|
Corrections Issued
|
RICKEY JACKSON
|
|
Special/Order Compliance
|
8/3/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Special/Order Compliance
|
3/9/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
3/22/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
3/22/2021
|
SGSOV Approved
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
3/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
8/9/2021
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
8/9/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
8/9/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
8/9/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Final
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Green Building Final
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Reinforced Concrete Frame
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Reinforced Masonry Frame
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Verify Sprinkler Sign Off
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Wood Frame
|
9/9/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Drywall Nailing
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Final
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Footing/Foundation/Slab
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Green Building Final
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Reinforced Concrete Frame
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Reinforced Masonry Frame
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Verify Sprinkler Sign Off
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Wood Frame
|
9/13/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Drywall Nailing
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Final
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Footing/Foundation/Slab
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Green Building Final
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Reinforced Concrete Frame
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Reinforced Masonry Frame
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Verify Sprinkler Sign Off
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Wood Frame
|
9/20/2021
|
Not Ready for Inspection
|
JOE VELASQUEZ
|
|
Drywall Nailing
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
9/24/2021
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
9/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
9/30/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
9/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
9/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
9/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
9/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
9/30/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
9/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
1/4/2022
|
Not Ready for Inspection
|
RICKEY JACKSON
|
|
Final
|
1/4/2022
|
Corrections Issued
|
RICKEY JACKSON
|
|
Footing/Foundation/Slab
|
1/4/2022
|
Not Ready for Inspection
|
RICKEY JACKSON
|
|
Green Building Final
|
1/4/2022
|
Not Ready for Inspection
|
RICKEY JACKSON
|
|
Reinforced Concrete Frame
|
1/4/2022
|
Not Ready for Inspection
|
RICKEY JACKSON
|
|
Reinforced Masonry Frame
|
1/4/2022
|
Not Ready for Inspection
|
RICKEY JACKSON
|
|
Wood Frame
|
1/4/2022
|
Not Ready for Inspection
|
RICKEY JACKSON
|
|
Drywall Nailing
|
6/10/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Final
|
6/10/2022
|
OK to Issue CofO
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
6/10/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
6/10/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
6/10/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
6/10/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
6/10/2022
|
Approved
|
DANNY RODRIGUEZ
|