410 E FLORENCE AVE 90003

Certificate Information: 410 E FLORENCE AVE 90003

Application / Permit
18010-10000-00910
Plan Check / Job No.
B18LA03898
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 5-story, Type VA, 51-unit, 100% affordable housing apartment building including 1 manager's unit over 1 story, Type IA, parking and recreation room and manager's office.
Permit Issued
Issued on 1/18/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2018 APPLICANT
Assigned to Plan Check Engineer 3/15/2018 KESETE HAREGOT
Corrections Issued 3/20/2018 KESETE HAREGOT
Quality Review Completed 3/21/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 3/22/2018 APPLICANT
Applicant returned to address corrections 10/23/2018 KESETE HAREGOT
Applicant returned to address corrections 10/26/2018 KESETE HAREGOT
Applicant returned to address corrections 11/14/2018 KESETE HAREGOT
Plan Check Approved 12/6/2018 KESETE HAREGOT
Issued 1/18/2019 LADBS
TCO Issued (Expire Date: 10-03-2022) 4/6/2022 ERNESTO CORRAL
CofO in Progress 7/1/2022 JAMES POWERS
Permit Finaled 7/1/2022 ERNESTO CORRAL
CofO Issued 7/1/2022 ERNESTO CORRAL
Permit Finaled 7/1/2022 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 7/3/2018 STEVE MELGAR
DCP conditions approval Cleared 8/2/2018 KENNETH LE
Density Bonus 12.22.A.31 Cleared 8/2/2018 KENNETH LE
Eng Process Fee Ord 176,300 Cleared 8/7/2018 CELINA MORENO
Hydrant and Access approval Cleared 8/7/2018 GILBERT URREA
Permit Cleared 8/7/2018 CELINA MORENO
Highway dedication Cleared 8/23/2018 JAMES MORALEZ
Green Code Cleared 9/5/2018 COLIN LOREDO
Low Impact Development Cleared 9/24/2018 IDA MEISAMI-FARD
Stormwater Pollution Mitigatn Cleared 9/24/2018 IDA MEISAMI-FARD
DAS Clearance Cleared 10/25/2018 EDDIE GARIN
Project located in CRA area Cleared 10/31/2018 JIM URQUHART
Roof/Waste drainage to street Cleared 10/31/2018 KARAN PATEL
Frnt yard landscape/Water mgmt Cleared 11/15/2018 NORA DRESSER
Miscellaneous Cleared 11/15/2018 NORA DRESSER
Miscellaneous Cleared 11/15/2018 NORA DRESSER
Opn space landscape/Water mgmt Cleared 11/15/2018 NORA DRESSER
Site Plan review Cleared 11/15/2018 NORA DRESSER
Building over 3-story or 36-ft Cleared 12/6/2018 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 12/10/2018 DOMINIQUE MEDINA
Sewer availability Cleared 1/14/2019 STEVE MELGAR

Contact Information

Architect Mohabir,, Edwin Ramkishore; Lic. No.: C23674 24979 CONSTITUTION AVENUE #1435      SANTA CLARITA, CA 91381
Contractor Unique Construction & Development Inc; Lic. No.: 830772-B 3699 WILSHIRE BLVD SUITE 660      LOS ANGELES, CA 90010
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/22/2019 Approved JAMES POWERS
Deputy Reinf. Concrete 6/3/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/8/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/10/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/11/2020 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/19/2020 Partial Approval JAMES POWERS
Green Building Rough 6/19/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 6/19/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/19/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/22/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/24/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/8/2020 Partial Approval JAMES POWERS
Green Building Rough 7/8/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/8/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/8/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 7/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/15/2020 Partial Approval JAMES POWERS
Green Building Rough 7/15/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/15/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/15/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 7/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/17/2020 Partial Approval JAMES POWERS
Green Building Rough 7/17/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/17/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/17/2020 Not Ready for Inspection JAMES POWERS
Green Building Rough 7/20/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/20/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/20/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 7/22/2020 Partial Approval JAMES POWERS
Deputy Other (see comments) 8/21/2020 Partial Approval JAMES POWERS
Green Building Rough 8/24/2020 Approved JAMES POWERS
Reinforced Concrete Frame 8/24/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/24/2020 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 9/1/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/11/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/11/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/15/2020 Partial Approval JAMES POWERS
Deputy Other (see comments) 9/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/16/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/5/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/30/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 11/24/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 12/9/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 1/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/3/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/8/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 2/16/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/25/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 2/25/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/9/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 3/9/2021 Not Ready for Inspection JAMES POWERS
Pre-Inspection 3/18/2021 Partial Approval NICK DANERI
Insulation 3/26/2021 Partial Approval JAMES POWERS
Insulation 4/7/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/16/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/22/2021 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/28/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/3/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/4/2021 Not Ready for Inspection JAMES POWERS
Insulation 6/4/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/18/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/19/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/19/2021 Partial Approval JAMES POWERS
Pre-Inspection 8/24/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/22/2021 Partial Approval TED RIES
Drywall Nailing 11/29/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/20/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 1/4/2022 Partial Approval JAMES POWERS
Drywall Nailing 4/5/2022 Approved JAMES POWERS
Final 4/5/2022 OK for TCO JAMES POWERS
Footing/Foundation/Slab 4/5/2022 Approved JAMES POWERS
Green Building Final 4/5/2022 Approved JAMES POWERS
Reinforced Concrete Frame 4/5/2022 Approved JAMES POWERS
Reinforced Masonry Frame 4/5/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Approved JAMES POWERS
Smoke Detectors 4/5/2022 Approved JAMES POWERS
Structural Steel Frame 4/5/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 4/5/2022 Approved JAMES POWERS
Wood Frame 4/5/2022 Approved JAMES POWERS
Final 7/1/2022 OK to Issue CofO JAMES POWERS