Pre-Inspection
|
11/22/2019
|
Approved
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/3/2020
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
6/8/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/10/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/10/2020
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
6/11/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
6/12/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/15/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
6/16/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
6/19/2020
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
6/19/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
6/19/2020
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/19/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/22/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
6/22/2020
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
6/23/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/24/2020
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
6/30/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
7/1/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/8/2020
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
7/8/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
7/8/2020
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
7/8/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/10/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/13/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/15/2020
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
7/15/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
7/15/2020
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
7/15/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/16/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/17/2020
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
7/17/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
7/17/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
7/17/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Rough
|
7/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
7/20/2020
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
7/20/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
7/22/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
8/21/2020
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
8/24/2020
|
Approved
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
8/24/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/24/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/1/2020
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
9/11/2020
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/11/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/15/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
9/16/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/16/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/5/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/5/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
10/30/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/9/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/24/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/2/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
12/9/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/16/2020
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/24/2020
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/15/2021
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
2/3/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
2/8/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
2/16/2021
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
2/25/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
2/25/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
3/9/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
3/9/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
3/18/2021
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
3/26/2021
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
4/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/16/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
4/22/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
4/28/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
6/3/2021
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
6/4/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
6/4/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/18/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/19/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
8/19/2021
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
8/24/2021
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
11/22/2021
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
11/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
12/20/2021
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
1/4/2022
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Final
|
4/5/2022
|
OK for TCO
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
4/5/2022
|
SGSOV Approved
|
JAMES POWERS
|
|
Smoke Detectors
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Structural Steel Frame
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Wood Frame
|
4/5/2022
|
Approved
|
JAMES POWERS
|
|
Final
|
7/1/2022
|
OK to Issue CofO
|
JAMES POWERS
|