1856 S WILTON PL 90019

Certificate Information: 1856 S WILTON PL 90019

Application / Permit
18010-10000-00904
Plan Check / Job No.
B18LA03879
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4-story, 64-unit, affordable housing apartment building over 1 level of subterranean parking. Per toc guidelines. 9 very low income, and 53 low income units.
Permit Issued
Issued on 5/14/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 MICHAEL PEREZ
Corrections Issued 4/10/2018 MOHAMMAD FIROUZBAKHT
Quality Review Completed 4/12/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 4/17/2018 APPLICANT
Applicant returned to address corrections 4/16/2019 MICHAEL PEREZ
Applicant returned to address corrections 4/19/2019 MICHAEL PEREZ
Plan Check Approved 4/30/2019 MICHAEL PEREZ
Issued 5/14/2019 LADBS
TCO Issued (Expire Date: 11-14-2021) 5/18/2021 ERNESTO CORRAL
CofO in Progress 12/3/2021 RAFAEL ESPINOZA
Permit Finaled 12/3/2021 ERNESTO CORRAL
CofO Issued 12/3/2021 ERNESTO CORRAL
Permit Finaled 12/3/2021 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/18/2018 STEVE MELGAR
Sewer availability Cleared 12/18/2018 STEVE MELGAR
Address approval Cleared 1/4/2019 ERIK BEASLEY
Green Code Cleared 1/4/2019 MOHAMMAD FIROUZBAKHT
City owned building/parcel Cleared 1/7/2019 HAROOT AVANESIAN
Hydrant and Access approval Cleared 2/6/2019 GEORGE SUCHAND
Low Impact Development Cleared 2/13/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 2/15/2019 ERIK BEASLEY
DAS Clearance Cleared 3/4/2019 ELIZABETH TOMS
Permit Cleared 3/15/2019 MICHAEL CASTILLO
Building over 3-story or 36-ft Cleared 3/19/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/19/2019 CALOSHA APPROVED
Project located in CRA area Cleared 3/26/2019 JIM URQUHART
Project located in CRA area Cleared 3/26/2019 JIM URQUHART
Work Adjacent to Public Way Cleared 4/15/2019 BOK GOH
"Q" conditions Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Highway dedication Cleared 4/18/2019 MICHAEL CASTILLO
Miscellaneous Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Opn space landscape/Water mgmt Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Site Plan review Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 4/18/2019 SOPHIE GABEL-SCHEINBAU
Fire Marshall Fire Life Safety Cleared 4/26/2019 MENOA AGHAJANI
DCP conditions approval Cleared 4/29/2019 KENNETH LE
Density Bonus 12.22.A.31 Cleared 4/29/2019 KENNETH LE
Density Bonus 12.22.A.31 Cleared 4/29/2019 KENNETH LE

Contact Information

Architect Daly,, Kevin Michael; Lic. No.: C19005 653 RAYMOND AVENUE      SANTA MONICA, CA 90405
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Arriola,, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Gsell,, Thomas George; Lic. No.: C34734 11416 VICTORIA AVE      LOS ANGELES, CA 90066
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Zangoli,, Fabio; Lic. No.: S6191 13245 FIJI WY UNIT J      MARINA DEL REY, CA 90292

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2019 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/12/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/7/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/7/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Barrier 8/7/2019 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 8/7/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/8/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 8/8/2019 Partial Approval JAMES POWERS
Deputy Methane Barrier 8/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 8/15/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 8/15/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/15/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/15/2019 Partial Inspection LESLIE TRUJILLO
Deputy Methane Barrier 8/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 8/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 8/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/23/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 8/23/2019 Partial Approval JAMES POWERS
Green Building Rough 8/23/2019 Partial Approval LESLIE TRUJILLO
METHANE-Rough 8/23/2019 Partial Approval LESLIE TRUJILLO
Masonry Wall/Backfill 8/23/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/23/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Masonry Frame 8/23/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/28/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 8/28/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 8/28/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Rough 8/28/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/28/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/28/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Masonry 8/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 8/30/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 8/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/3/2019 Conditional Approval LESLIE TRUJILLO
Green Building Rough 9/3/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Rough 9/3/2019 Not Ready for Inspection LESLIE TRUJILLO
Piling/Pier/Caisson 9/3/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 9/3/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 9/3/2019 Not Ready for Inspection LESLIE TRUJILLO
Deputy Shotcrete 9/4/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 9/4/2019 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 9/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/23/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 9/23/2019 Partial Inspection LESLIE TRUJILLO
Deputy Methane Barrier 9/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/3/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/3/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/3/2019 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/3/2019 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 10/3/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 10/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 10/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 10/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/22/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/22/2019 Partial Approval JAMES POWERS
METHANE-Barrier 10/22/2019 Approved JAMES POWERS
METHANE-Subgrade 10/22/2019 Approved JAMES POWERS
Deputy Reinf. Concrete 10/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/28/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/31/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/31/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/1/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/4/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/22/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 11/25/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/25/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/2/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 12/2/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Other (see comments) 12/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 12/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 12/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 12/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 12/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/24/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/26/2019 Partial Approval LESLIE TRUJILLO
Deputy Wood Construction 12/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/30/2019 Partial Approval LESLIE TRUJILLO
Deputy EIFS 12/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 1/6/2020 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/6/2020 Partial Approval DAVID BURKHEAD
Structural Steel Frame 1/6/2020 Not Ready for Inspection DAVID BURKHEAD
Deputy Steel/Welding 1/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/10/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 1/23/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/23/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 1/23/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 1/23/2020 Approved LESLIE TRUJILLO
Structural Steel Frame 1/23/2020 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 1/23/2020 Conditional Approval LESLIE TRUJILLO
Wood Frame 1/23/2020 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/3/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/3/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 2/3/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/3/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/3/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/4/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Partial Approval RAFAEL ESPINOZA
Deputy Other (see comments) 2/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/11/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 2/20/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/28/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/9/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/12/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 3/12/2020 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 3/12/2020 Conditional Approval LESLIE TRUJILLO
Wood Frame 3/12/2020 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/17/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 3/17/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/18/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/20/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 3/20/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 3/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/25/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 3/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/25/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 3/25/2020 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 3/26/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 3/31/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 3/31/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 4/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/2/2020 Conditional Approval RAFAEL ESPINOZA
Wood Frame 4/2/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/3/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/10/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 4/10/2020 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/13/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 4/13/2020 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 4/13/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 4/13/2020 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/13/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 4/14/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 4/14/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/24/2020 Conditional Approval RONALD PACHECO
Deputy Steel/Welding 4/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/30/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 4/30/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/1/2020 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 5/4/2020 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 5/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/6/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/7/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/7/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/7/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/7/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/8/2020 Conditional Approval RAFAEL ESPINOZA
Structural Steel Frame 5/11/2020 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/11/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/11/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 5/15/2020 Partial Approval RAFAEL ESPINOZA
Insulation 5/18/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/18/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/19/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 5/19/2020 Partial Approval RAFAEL ESPINOZA
Insulation 5/19/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/19/2020 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/20/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 5/20/2020 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 5/20/2020 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/22/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 5/26/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/26/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/28/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 5/28/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/28/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/2/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 6/2/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/2/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/4/2020 Conditional Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 6/5/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 6/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 6/8/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/8/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 6/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/9/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 6/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Fireproofing 6/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/10/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/10/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 6/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 6/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/12/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 6/12/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/12/2020 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 6/15/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 6/16/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/17/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/18/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 6/19/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 6/22/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/22/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 6/23/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 6/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/25/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 6/25/2020 Corrections Issued RAFAEL ESPINOZA
Deputy Steel/Welding 6/26/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/26/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 6/26/2020 Approved RAFAEL ESPINOZA
Wood Frame 6/26/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/29/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/29/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/30/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/1/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/2/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 7/2/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/6/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/6/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/8/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 7/8/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/21/2020 Conditional Approval RAFAEL ESPINOZA
Wood Frame 7/21/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/29/2020 Conditional Approval RAFAEL ESPINOZA
Wall Anchors 7/29/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/30/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 7/31/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 8/3/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/4/2020 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/6/2020 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 8/6/2020 Conditional Approval TIMOTHY BUXTON
Verify Sprinkler Sign Off 8/6/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 8/6/2020 Partial Approval JONATHAN QUACH
Deputy Fireproofing 8/7/2020 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 8/7/2020 Conditional Approval DAVID BURKHEAD
Insulation 8/7/2020 Partial Approval JONATHAN QUACH
Deputy Fireproofing 8/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/14/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/14/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 8/18/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/25/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/25/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 8/26/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/26/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 8/26/2020 No Access for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 8/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 8/28/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 8/28/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 8/28/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Approved RAFAEL ESPINOZA
Deputy Steel/Welding 9/1/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/4/2020 Conditional Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/4/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/18/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/24/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 9/24/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/25/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/25/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Fireproofing 9/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 9/30/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/30/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/1/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 10/1/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/2/2020 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 10/2/2020 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 10/5/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 10/8/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/13/2020 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 10/19/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/5/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 11/5/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/6/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 11/17/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 11/17/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 11/17/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 11/18/2020 Conditional Approval RAFAEL ESPINOZA
Final 1/13/2021 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 1/13/2021 Approved RAFAEL ESPINOZA
Green Building Final 1/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 1/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/13/2021 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 1/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 1/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 2/3/2021 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 2/4/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/8/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/9/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 2/16/2021 Conditional Approval RAFAEL ESPINOZA
Final 2/16/2021 Partial Inspection RAFAEL ESPINOZA
Green Building Final 2/16/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 2/16/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 2/16/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/16/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/16/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 2/17/2021 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 2/17/2021 Approved RAFAEL ESPINOZA
Final 3/3/2021 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 3/3/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/3/2021 Conditional Approval RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/3/2021 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 3/3/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/3/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/3/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Final 3/8/2021 Approved RAFAEL ESPINOZA
Final 3/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 3/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Not Ready RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 3/11/2021 Partial Inspection RAFAEL ESPINOZA
Green Building Final 3/18/2021 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 4/8/2021 Partial Inspection RAFAEL ESPINOZA
Final 4/20/2021 Partial Inspection RAFAEL ESPINOZA
Green Building Final 4/20/2021 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 4/20/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 4/20/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/20/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/20/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 4/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 4/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 10/4/2021 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/4/2021 Approved RAFAEL ESPINOZA
Smoke Detectors 10/4/2021 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/4/2021 Approved RAFAEL ESPINOZA
Wood Frame 10/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 10/20/2021 Partial Inspection RAFAEL ESPINOZA
Final 12/3/2021 OK to Issue CofO RAFAEL ESPINOZA
Wood Frame 12/3/2021 Approved RAFAEL ESPINOZA