200 BAUCHET ST 90012

Certificate Information: 200 BAUCHET ST 90012

Application / Permit
18010-10000-00872
Plan Check / Job No.
B18LA03766
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
CONSTRUCTION OF NEW 4-STORY DATA CENTER BUILDING AND OFFICE PER APCC-2017-2421-SPE-SPP (2ND/3RD FLOOR CORE&SHELL ONLY). **The 1st floor is used entirley for batteries. **see comment
Permit Issued
Issued on 7/2/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2018 APPLICANT
Disabled Access Plans Picked Up 3/14/2018 APPLICANT
Assigned to Plan Check Engineer 3/15/2018 ARMEN JIVALAGIAN
Green Plans Picked Up 4/10/2018 APPLICANT
Corrections Issued 4/12/2018 ARMEN JIVALAGIAN
Quality Review Completed 4/12/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 4/24/2018 APPLICANT
Applicant returned to address corrections 7/18/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/10/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/30/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/18/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/15/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/30/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/12/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/19/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/7/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/24/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 6/6/2019 ARMEN JIVALAGIAN
Plan Check Approved 6/21/2019 ARMEN JIVALAGIAN
Issued 7/2/2019 LADBS
TCO Issued (Expire Date: 05-04-2021) 11/5/2020 ERNESTO CORRAL
TCO Issued (Expire Date: 12-01-2021) 6/4/2021 ERNESTO CORRAL
CofO in Progress 6/9/2021 RAFAEL ESPINOZA
Permit Finaled 6/11/2021 ERNESTO CORRAL
CofO Issued 6/11/2021 ERNESTO CORRAL
Permit Finaled 6/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 4/30/2018 STEVE MELGAR
Address approval Cleared 5/23/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/23/2018 ADRIAN SANCHEZ
Project located in CRA area Cleared 5/24/2018 JIM URQUHART
Miscellaneous Cleared 6/13/2018 WILLIAM JOHNS
Metro Rail approval Cleared 6/22/2018 ARMEN JIVALAGIAN
Low Impact Development Cleared 7/18/2018 MARTIN FRAGOSO
Sewer availability Cleared 7/24/2018 ADRIAN SANCHEZ
APC Cleared 8/10/2018 EDBER MACEDO
Building over 3-story or 36-ft Cleared 8/10/2018 CALOSHA APPROVED
Certificate of Compliance Cleared 8/10/2018 EDBER MACEDO
Miscellaneous Cleared 8/10/2018 EDBER MACEDO
Grading Pre-Inspection Cleared 8/15/2018 PATRICK MISCHLICH
Hydrant and Access approval Cleared 8/30/2018 GILBERT URREA
Miscellaneous Cleared 8/30/2018 GILBERT URREA
Roof/Waste drainage to street Cleared 10/16/2018 MICHAEL CASTILLO
Highway dedication Cleared 10/18/2018 MICHAEL CASTILLO
DAS Clearance Cleared 10/30/2018 SHINE LIN
Drainage to Storm Drain Cleared 10/30/2018 SOPHEA EK
Miscellaneous Cleared 10/30/2018 SOPHEA EK
City Hist. Cultural Monument Cleared 11/2/2018 LAMBERT GIESSINGER
Construction near power lines Cleared 11/2/2018 WALTER RAMIREZ
Construction within easement Cleared 11/2/2018 WALTER RAMIREZ
Historic monument Cleared 11/2/2018 LAMBERT GIESSINGER
Private street Cleared 11/20/2018 EDBER MACEDO
Miscellaneous Cleared 12/11/2018 NAZILA NOORIFAR
Driveway location Cleared 1/9/2019 MOHAMMAD HASAN
Internal circulation Cleared 1/9/2019 MOHAMMAD HASAN
Specific Plan Cleared 1/9/2019 MOHAMMAD HASAN
Transportation Demand Ord. Cleared 1/9/2019 MOHAMMAD HASAN
Green Code Cleared 1/18/2019 COLIN LOREDO
APC Cleared 6/21/2019 EDBER MACEDO
Prkng lot landscape/Water mgmt Cleared 6/21/2019 EDBER MACEDO
Site Plan review Cleared 6/21/2019 EDBER MACEDO
Specific Plan Cleared 6/21/2019 EDBER MACEDO
ZI Cleared 6/21/2019 EDBER MACEDO

Contact Information

Architect Dotterweich,, August Jeffrey; Lic. No.: C28590 336 BURNTSIDE DRIVE      GOLDEN VALLEY, MN 55422
Engineer Bueno,, Jaime Luis; Lic. No.: C65389 1111 S GRAND AVE UNIT 510      LOS ANGELES, CA 90015
Engineer Chung,, Justin Jeesung; Lic. No.: S6038 950 S GRAND AVE 4TH FLOOR      LOS ANGELES, CA 90015
Engineer Luzuriaga, David Alexander; Lic. No.: C56734 600 S MAIN STREET SUITE 920      ORANGE, CA 92868

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/16/2019 Approved ERNESTO CORRAL
Pre-Inspection 10/11/2019 Partial Inspection DANIEL MC AULIFFE
Pre-Inspection 10/23/2019 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/28/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/28/2019 Partial Approval DANIEL MC AULIFFE
Piling/Pier/Caisson 10/29/2019 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 11/4/2019 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 11/7/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/8/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 11/12/2019 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 11/15/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/18/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/19/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/20/2019 Partial Inspection ERNESTO CORRAL
Deputy Steel/Welding 11/22/2019 Conditional Approval ERNESTO CORRAL
Deputy Other (see comments) 12/13/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 12/13/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 12/17/2019 Conditional Approval ERNESTO CORRAL
Green Building Rough 12/17/2019 Not Ready for Inspection ERNESTO CORRAL
Structural Steel Frame 12/17/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 12/17/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Steel/Welding 12/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 12/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 12/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 12/31/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 12/31/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/31/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/6/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/7/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 1/8/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 1/9/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 1/10/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/15/2020 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 1/16/2020 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/17/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/22/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 1/23/2020 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 1/24/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/27/2020 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 1/28/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/29/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/30/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/3/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 2/3/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 2/5/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/7/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/10/2020 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 2/11/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/12/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/14/2020 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 2/14/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 2/14/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 2/19/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/20/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/25/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/28/2020 Approved DANIEL MC AULIFFE
Light Gage Steel Frame 2/28/2020 Partial Inspection DANIEL MC AULIFFE
Light Gage Steel Frame 3/5/2020 Partial Inspection ERNESTO CORRAL
Pre-Inspection 3/10/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 3/13/2020 No Access for Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/13/2020 No Access for Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/17/2020 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 3/23/2020 No Access for Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/25/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/31/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/3/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/9/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/16/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 4/22/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/22/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/29/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 4/29/2020 Partial Approval JONATHAN QUACH
Insulation 5/4/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/4/2020 Partial Approval RAFAEL ESPINOZA
Grading Pre-Inspection 5/11/2020 Partial Inspection RAFAEL ESPINOZA
Insulation 5/11/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/13/2020 Partial Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 5/14/2020 Partial Inspection RAFAEL ESPINOZA
Insulation 5/18/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/21/2020 Partial Approval RAFAEL ESPINOZA
Insulation 5/21/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/21/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/29/2020 Partial Approval RAFAEL ESPINOZA
Insulation 5/29/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/29/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/2/2020 Partial Approval NICK DANERI
Drywall Nailing 6/10/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/10/2020 Partial Approval RAFAEL ESPINOZA
Insulation 6/12/2020 Partial Approval RAFAEL ESPINOZA
T-Bar Ceiling 6/24/2020 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 7/1/2020 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 7/2/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 7/2/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/8/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 7/14/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/17/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/24/2020 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/17/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/31/2020 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/3/2020 Partial Inspection RAFAEL ESPINOZA
T-Bar Ceiling 9/3/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/8/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 9/8/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/10/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 9/10/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/17/2020 Conditional Approval RAFAEL ESPINOZA
T-Bar Ceiling 9/17/2020 Partial Approval RAFAEL ESPINOZA
Insulation 9/24/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/24/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/1/2020 Conditional Approval RAFAEL ESPINOZA
T-Bar Ceiling 10/1/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/8/2020 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/9/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/13/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/13/2020 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 10/15/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/19/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/22/2020 Conditional Approval RAFAEL ESPINOZA
Special/Order Compliance 10/27/2020 Approved RAFAEL ESPINOZA
Green Building Final 11/5/2020 Approved RAFAEL ESPINOZA
Special/Order Compliance 11/5/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/8/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 12/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/4/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/12/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 1/26/2021 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/27/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 1/28/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 1/29/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/1/2021 Conditional Approval RAFAEL ESPINOZA
Final 2/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 2/1/2021 Approved RAFAEL ESPINOZA
Green Building Rough 2/1/2021 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 2/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 2/1/2021 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 2/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
Structural Steel Frame 2/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 2/2/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/3/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/4/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/5/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/9/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/10/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/17/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/1/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/2/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/4/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/8/2021 Conditional Approval RAFAEL ESPINOZA
Final 3/25/2021 Partial Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 3/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 3/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Structural Steel Frame 3/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 4/7/2021 Partial Inspection RAFAEL ESPINOZA
Final 6/9/2021 OK to Issue CofO RAFAEL ESPINOZA
Reinforced Masonry Frame 6/9/2021 Approved RAFAEL ESPINOZA
Smoke Detectors 6/9/2021 Approved RAFAEL ESPINOZA
Structural Steel Frame 6/9/2021 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/9/2021 Approved RAFAEL ESPINOZA