4643 E CLELAND AVE 90065

Certificate Information: 4643 E CLELAND AVE 90065

Application / Permit
18010-10000-00864
Plan Check / Job No.
B18LA03753
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
PROPOSED DETACHED 2-CAR GARAGE ON SLOPING LOT TO REPLACE FIRE DAMAGED GARAGE. "COMPLY WITH DEPARTMENT ORDER effective date 01/30/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 11/9/2020
Issuing Office
Current Status
Issued on 11/9/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/27/2018 APPLICANT
Assigned to Plan Check Engineer 3/8/2018 MICHAEL LOPEZ
Corrections Issued 3/8/2018 MICHAEL LOPEZ
Applicant returned to address corrections 4/13/2018 SHANGQIN XIE
Plan Check Approved 4/18/2018 JESSE JIMENEZ
Issued 11/9/2020 APPLICANT
Building Plans Picked Up 4/20/2021 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/28/2018 NAZILA NOORIFAR
Low Impact Development Cleared 3/28/2018 SAM NAVID
Specific Plan Cleared 4/4/2018 SANTOS SANCHEZ
BHO/Hillside ordinance Cleared 4/13/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 4/13/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 4/13/2018 NAZILA NOORIFAR
Grading Pre-Inspection Cleared 4/13/2018 MICHAEL LOPEZ
Roof/Waste drainage to street Cleared 4/13/2018 NAZILA NOORIFAR

Contact Information

Contractor Gmf Construction And Development Inc; Lic. No.: 1037945-B 34145 PCH      DANA POINT, CA 92629
Engineer Hansen, Hans Christian; Lic. No.: C80546 3425 E. ALMOND AVE      ORANGE, CA 92869

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/12/2020 Corrections Issued PATRICK LIEBREGT
Footing/Foundation/Slab 3/5/2021 Not Ready for Inspection PATRICK LIEBREGT
Footing/Foundation/Slab 3/9/2021 Corrections Issued PATRICK LIEBREGT
Excavation/Setback/Form/Re-Bar 3/31/2022 Approved PATRICK LIEBREGT
Footing/Foundation/Slab 7/8/2022 Approved PATRICK LIEBREGT
BUILDING-Rough-Frame 8/5/2022 Approved PATRICK LIEBREGT
Wood Frame 8/5/2022 Approved PATRICK LIEBREGT
Interior/Exterior Lathing 10/11/2022 Approved PATRICK LIEBREGT