22331 S NORMANDIE AVE 90501
Certificate Information: 22331 S NORMANDIE AVE 90501
- Application / Permit
- 18010-10000-00837
- Plan Check / Job No.
- B18LA03694
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NWE THREE STORY SINGLE FAMILY HOME WITH GARAGE.
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2018 | APPLICANT |
| Green Plans Picked Up | 3/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2018 | TSE MING HUANG |
| Corrections Issued | 4/5/2018 | TSE MING HUANG |
| Quality Review Completed | 4/19/2018 | VERONICA LOPEZ |
| Building Plans Picked Up | 4/25/2018 | APPLICANT |
| Plan Check Approved | 3/13/2020 | TSE MING HUANG |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 6/6/2022 | EUGENE CASSIDY |
| CofO Issued | 6/22/2022 | DEROLD HAUFF |
| Permit Finaled | 6/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/8/2018 | MITESH PATEL |
| Address approval | Cleared | 7/16/2018 | NEIL TUANO |
| Encroachment in public way | Cleared | 7/16/2018 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2018 | NEIL TUANO |
| Highway dedication | Cleared | 7/16/2018 | NEIL TUANO |
| Miscellaneous | Cleared | 7/16/2018 | NEIL TUANO |
| Permit | Cleared | 7/16/2018 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 7/16/2018 | NEIL TUANO |
| Sewer availability | Cleared | 7/16/2018 | NEIL TUANO |
| Hydrant and Access approval | Cleared | 9/26/2018 | GEORGE SUCHAND |
| Construction near power lines | Cleared | 11/21/2018 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/21/2018 | RIDWAN HARDY |
| CPC | Cleared | 11/26/2018 | BLAYNE SUTTON-WILLS |
| ZA Case | Cleared | 11/26/2018 | BLAYNE SUTTON-WILLS |
| ZA Case | Cleared | 11/26/2018 | BLAYNE SUTTON-WILLS |
| Green Code | Cleared | 1/29/2020 | NEGAR NEJAD |
Contact Information
| Architect | Knitter,, M J; Lic. No.: C10524 | 1401 DOVE STREET SUITE 240 NEWPORT BEACH, CA 92660 |
| Contractor | Pacific Communities Builder Inc; Lic. No.: 660968-B | 1000 DOVE STREET SUITE 100 NEWPORT BEACH, CA 92600 |
| Engineer | Atkinson,, Christopher Joseph; Lic. No.: S4055 | 1215 W RIO SALADO PKWY__STE 200 TEMPE, AZ 85281 |
| Engineer | Mohammadabadi,, Mohammad; Lic. No.: C42615 | 21715 BELLCROFT EL TORO, CA 92630 |
| Engineer | Toney,, Noelle Camille; Lic. No.: C84700 | 2085 HIGHPOINTE DRIVE UNIT 204 CORONA, CA 92879 |
| Landscape Architect | Dierking,, Ryan L.F; Lic. No.: LA5625 | 365 S PIXLEY STREET ORANGE, CA 92868 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| Sewer | 5/18/2021 | Approved | JOHN KLARIN |
| Underground Mechanical | 5/18/2021 | Partial Approval | JOHN KLARIN |
| METHANE-Barrier | 5/25/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 5/25/2021 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 5/27/2021 | Approved | JOHN KLARIN |
| Underground Mechanical | 5/27/2021 | Partial Approval | JOHN KLARIN |
| Deputy Reinf. Concrete | 6/1/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 9/9/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 9/9/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 9/9/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 9/9/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 9/9/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/9/2021 | Approved | JOHN KLARIN |
| Insulation | 9/15/2021 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 9/15/2021 | Approved | CRAIG DAVIS |
| Drywall Nailing | 9/20/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 9/21/2021 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 9/22/2021 | Not Ready for Inspection | JOHN KLARIN |
| Gas Test | 10/21/2021 | Not Ready for Inspection | JOHN KLARIN |
| Gas Test | 10/22/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 12/28/2021 | Approved | JOHN KLARIN |
| HVAC-Final | 12/28/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 12/28/2021 | Approved | JOHN KLARIN |
| Final | 1/25/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/25/2022 | Approved | EUGENE CASSIDY |
| Green Building Final | 1/25/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 1/25/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 1/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 1/25/2022 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 1/25/2022 | Approved | EUGENE CASSIDY |
| Final | 4/14/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 4/14/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 4/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 5/17/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 5/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 5/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 5/25/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 5/31/2022 | Approved | EUGENE CASSIDY |
| Final | 6/1/2022 | OK to Issue CofO | EUGENE CASSIDY |